RESOLVED - That the Council be recommended to:- ( i ) approve the 2008/09 proposed Portfolio cash limit budgets of £123.497m and the associated assumptions outlined in section 4 of the report; (ii) approve the deduction of an additional £0.676m of Council-wide efficiencies and savings from Portfolio cash limits during the year (as per paragraphs 4.2.3 and 4.3.5 of the report); (iii) approve the 2008/09 proposed non-cash limit and contingency budgets of £37.239m and the associated assumptions outlined in sections 5 and 6 of the report; (iv) agree to passport the new Area Based Grants to the relevant Portfolios (as per paragraph 5.3.2 and Appendix B of the report); (v) agree that up to six months of continuation funding will be allocated from the Working Neighbourhoods Fund to continue existing schemes, pending the development of a new allocation methodology (as per paragraph 5.4.2 of the report); (vi) note the total available temporary resources of £5.911m in 2008/09 (as per paragraph 10.6 of the report); (vii) approve additional investment of £8.235m as detailed in section 9 and summarised in the table below:- Proposals for Additional Investment Permanent £m Temporary £m Total £m Portfolio Requests for Investment (sections 9.2 and 9.3 of the report) 2.324 0.893 3.217 Corporate Priorities (section 9.4 of the report) 0.000 4.409 4.409 Contribution to Workforce Development Reserve (section 9.4 of the report) 0.000 0.609 0.609 TOTAL BUDGET GROWTH 2.324 5.911 8.235
Word for word from the decision Knowsley published for this meeting.Source: councillors.knowsley.gov.uk
On 4 March 2008, the Council will meet to consider its 2008/09 budget and Council Tax. This report sets out budget proposals from Portfolio Holders and additional information, which can be used by the Cabinet to inform its final 2008/09 revenue budget proposals to the Council.
Recommendations
The Cabinet is recommended to make proposals to the Council on the 2008/09 revenue budget based upon the information set out in this report.
3. BACKGROUND TO THE 2008/09 REVENUE BUDGET
3.1In finalising its proposals for the Council’s 2008/09 revenue budget, the Cabinet is asked to consider the proposals set out in this report, and also the wider context of:-
• the Council’s proposed Corporate Plan for 2008/09; • the Medium-Term Financial Plan; • proposals for the 2008/09 Capital Programme; • the latest forecasts for the 2007/08 budget monitoring position; and, • the robustness of estimates and adequacy of reserves.
3.2Each of these areas is the subject of separate reports elsewhere on this agenda. 3.3 This report explains how a set of balanced budget proposals for 2008/09 could be developed based on the latest information on the following revenue budget items:-
• Portfolio Local Service Agreement budget proposals; • Options for efficiency, savings and fees and charges identified by Scrutiny Committees and Portfolio Holders; • Recommendations from the 2007/08 Service Review Programme; • Legislative changes, i.e. where new statutory responsibilities have been placed on the Council; • Demand-led and demographic changes which impact upon the level of service that the Council needs to provide; • Assumptions regarding levies and inflation; and, • Confirmation of the Local Government Finance Settlement.
3.4Where the report discusses budget pressures, efficiencies and funding options, these will usually be divided into two categories:-
(a) ‘permanent’ items – which will have an impact in 2008/09 and future years; and,
(b) ‘temporary’ items - which will have a one-off effect in 2008/09 only.
3.5Links to Corporate Objectives and Service Performance
3.5.1 In line with the Council’s policy of linking performance to financial resources through Local Service Agreements, these budget proposals should be considered in conjunction with the Council’s 2008/09 Corporate Plan, which is discussed elsewhere on this agenda.
3.5.2 The resources available to each Portfolio, both capital and revenue, are set out within Local Service Agreements, which demonstrate the relationship between the use of resources and performance. Subject to the Council’s approval of the 2008/09 budget proposals, these Local Service Agreements will be presented for discussion and approval by Portfolio Holders and the Leader early in 2008/09.
3.6Budget Consultation Process
3.6.1 Consultation has taken place with the following key stakeholders:-
• Scrutiny Committees • Individual Members of the Council; • Parish Councils; • The Chamber of Commerce; and, • Trade Unions. 3.6.2 The outcomes of this consultation are reflected in this report – in particular, the options proposed by the Scrutiny Committees for efficiencies, savings and new fees and charges (see section 4.3 of the report).
3.6.3 Any further formal representations received before the Cabinet considers this report will be presented at the meeting.
4. 2008/09 PORTFOLIO BUDGET PROPOSALS
4.1Portfolio Budget Reports
Portfolio budget proposals are detailed in the individual reports, which were considered by Portfolio Holders and circulated to all Members in January 2008. Full details of all Portfolio budgets are available on request from the Borough Treasurer, and the key issues are summarised in this report.
4.2Indicative Cash Limits
4.2.1 In developing their budgets, Portfolio Holders have identified indicative cash limits, which are available to fund current levels of service.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.