PERFORMANCE OUTTURN QUARTER 3 2007-2008

Agreed Committee 2 papers

Halewood Partnership Board agreed this item on Tuesday 19 February 2008. Below is the council's own wording, with the papers it was decided on.

Item63

Resolved

It was AGREED – That the areas of underperformance be noted; (ii) That the proposed performance improvement activities / plan be endorsed; and (iii) That the continued development of systems and processes to capture this information be endorsed.
Word for word from the decision Knowsley published for this meeting. Source: councillors.knowsley.gov.uk

Follow this further

Built from Knowsley's papers

What the report saysPro

Report to Halewood Partnership Board

Purpose of report

The purpose of this report is to inform members;-

(i) Of the outturn performance figures for quarter three, 2007-08 (ii) What remedial action has and / or will take place to address areas of underperformance (iii) The continued developmental of a methodology to capture such information

Recommendations

The Partnership Board is asked to:

(i) Note the areas of under performance. (ii) Endorse the proposed performance improvement activities/plan (iii) Endorse the continued development of systems and processes to capture this information LINKS TO AREA PRIORITIES/ AGREEMENT

The contents of this report link directly to the identified priorities in the Halewood Area Agreement.

Background

This report has been compiled to highlight performance against agreed targets set within the Halewood Area Agreement for quarter three, 2007-2008.

Area Performance Relating to ‘A Safe Clean and Well Managed Halewood Area ’ Crime & Environmental performance Crime & Disorder Of the 5 measurable indicators, all 5 continue to be on target.

Why is there under performance? There are no areas of under performance in Halewood. All 5 targets are in line to end quarter 4 under target.

What action has taken place or is planned to address this under performance? Currently there is no under performance in Halewood. Activity will continue to ensure the positive trend is sustained.

What happens next? What role is there for the area partnership board? The APB members can support the work around these targets by; o promoting crime reduction messages with the local community and internally throughout their own organisations

Environment Of the 3 measurable targets 1 is on target and 2 are below target.

Below target - Cleanliness of Highway & Green space.

These were also off target in Q1 and Q2.

Why is there under performance? Although the two targets are still off target, performance has improved and is close to being on target. Improvement plans implemented in quarter 2 has impacted positively resulting in only one failure of forty areas inspected in the last two months. Performance on green space has improved in quarter 3 with none of the areas inspected failing. The area is only marginally away from achieving target with continued good performance it is anticipated to achieve this in quarter 4.

What action has taken place or is planned to address this under performance?

Performance on cleansing continues to be a priority in order to recover performance. There continues to be a fine focus on performance a support of patch management which should continue the improvement in performance.

What happens next? What role is there for the area partnership board?

The APB members can support the work around these indicators by; o committing to and supporting the development and delivery of patch management approach. o Encouraging Street smart in agreed locations.

A Prosperous Halewood Area Performance Summary of performance _ Worklessness Indicator data will be available on February 13th 2008. Only 1 Indicator is measurable at present. Halewood Area Partnership Board should note that at the time of producing this report, performance information for quarter 3 was unavailable apart from 1 indicator. It is anticipated that the information relating to worklessness will be available on 13th February. Where analysis of the data determines that underperformance has occurred, this will be verbally reported to the Area Partnership Board at the meeting.

o Of 1 measurable indicator, 1 is on target. o No indicators direction of travel can be reported.

Why is there under performance? There is no underperformance on the 1 indicator, worklessness indicator performance will be reported against when it becomes available on February 13th 2008.

What action has taken place or is planned to address this under performance? Performance cannot be reported against worklessness until February 13th 2008. Fresh Start Business Start Ups are on target.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
PERFORMANCE OUTTURN QUARTER 3 2007-2008Report 148 KB DownloadRead as text
PDF
Q3 Performance appendix KH2Appendix 70 KB Download

At this meeting

Whole meeting

On this subject at Knowsley

Search all
  1. PERFORMANCE OUTTURN QUARTER 3 2007-2008This decision
  2. 2012/13 Performance OutturnNoted
  3. Finance and Performance Outturn 2010/11 (*)Noted
  4. Health and Wellbeing Partnership Annual Review and Performance Outturn 2009/10Agreed
  5. Finance and Performance Outturn 2009/10Agreed
  6. Performance Outturn Quarter 2Noted

More from Knowsley Halewood Partnership Board

All decisions
MeetingDecisionOutcome
16 Jul 2013 Priorities and Pledge Activity 2013/14It was AGREED that the local interventions identified in Appendix A to the report now submitted be endorsed. Agreed Open
16 Jul 2013 Problem Solving GroupIt was AGREED that the content of the report, interventions and the impact of activity undertaken by the be noted. Agreed Open
16 Jul 2013 Area Partnership Board Forward Plan 2013/14It was AGREED that the Forward Plan be noted. Agreed Open
11 Jun 2013 Area Partnership Board Protocol and Partner Representation Framework 2013/14It was AGREED - ( i ) That the Area Partnership Board Protocol, attached at Appendix 1, be adopted as its constitutio... Agreed Open
11 Jun 2013 Area Partnership Board Annual Review 2012/13It was AGREED - ( i ) That the Annual report in relation to the work of the Area Partnership Boards during 2012/13, b... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies