RESOLVED – That approval be given to the extension of the existing pooled budget arrangement for mental health services for a further three years to 2010/11 as set out in the table in 5.1.1 of the report now submitted. (Note: In accordance with the provisions of Section 81 of the Local Government Act 2000 Councillor G A Wright declared a personal interest in the above item and remained in the meeting, took part in the discussion and voted thereon.)
Word for word from the decision Knowsley published for this meeting.Source: councillors.knowsley.gov.uk
The report set out the benefits of extending the existing pooled budget for mental health services for a further three years to 2010/11 and seeks Cabinet approval to the overall contributions.
Recommendations
The Cabinet is recommended to approve the extension of the existing pooled budget arrangement for mental health services for a further three years to 2010/11 as set out in the table in 5.1.1.
Background
3.1The Health Act 1999 provides three powers to enable health and local authority partners to work together more effectively. These powers are:-
• Pooled Budgets - the ability for partners each to contribute agreed funds to a single pot to be spent on agreed projects for designated services;
• Lead Commissioning - the ability for partners to agree to delegate commissioning of a service to one lead organisation; and,
• Integrated Provision - the ability for partners to join together their employees, resources, and management structures to integrate the provision of a service from the managerial level to the front line. 3.2 A pooled budget arrangement provides an opportunity for the partners to bring money together in a discrete fund to pay for agreed services to clients. The expenditure would then be based on the needs of the users, and not on the level of contribution from each partner. This approach enhances flexibility, whilst also being bounded by agreed aims and outcomes.
3.3In 2005/06, the Cabinet approved the establishment of a pooled budget for a three- year period, drawing together existing budgets from the Primary Care Trust and the Health and Social Care Portfolio to provide community based services for people with a mental illness. This budget is hosted by the Council and currently amounts to £1.4 million per annum.
4. PROPOSALS
4.1The use of a pooled budget for these services has improved flexibility and responsiveness to service users’ needs, as it can be used to meet assessed health or social care needs without the requirement to negotiate a complex shared funding arrangement. It has also improved efficiency for both commissioners and providers by removing the duplication of commissioning, contract and funding negotiation and payment, which previously existed between the Primary Care Trust and Social Services.
4.2The phasing of partners’ contributions over the three-year period has enabled the Primary Care Trust and the Health and Social Care Portfolio to manage their respective budget pressures more effectively. It has also generated an additional capital receipt of £0.250 million for investment in modernising day services.
4.3It is therefore proposed to extend the pooled budget for mental health services for a further three years.
5. RESOURCE IMPLICATIONS
5.1Financial
5.1.1 The proposed pooled budget contributions over the three-year period are set out in the table below, together with indicative figures for the annual contributions:-
2008/09 2009/10 2010/11 Total £m £m £m £m
Health and Social Care Portfolio 0.494 0.506 0.519 1.519
Knowsley Primary Care Trust 0.938 0.961 0.985 2.884
Total Pooled Budget 1.432 1.467 1.504 4.403 5.1.2 As with the existing pooled budget arrangement, although the overall three-year contribution is set along with the proportion to be funded by each organisation over the period, the annual contributions are only indicative at this stage. This is due to one of the major benefits of the arrangement being the ability to vary each organisation’s contribution to reflect their respective funding in that year.
5.2Human
There are no human resources implications arising from these proposals.
5.3Information Technology
There are no information technology implications arising from these proposals.
5.4Physical Assets
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.