Council Land and Property Review

Agreed Executive 1 paper

Cabinet agreed this item on Wednesday 5 March 2008. Below is the council's own wording, with the papers it was decided on.

Item142

Resolved

RESOLVED – ( i ) That the proposed Vision for a Council Property Plan be agreed; (ii) that the development of a 3 year rolling Property Plan to be reviewed and updated annually and aligned with the Corporate Plan process in line with best practice from other Local Authorities, be agreed; (iii) that governance arrangements be improved by closer involvement of Members through the appointment of a Cabinet champion for all Council land and property issues, namely the Portfolio lead for Regeneration; (iv) that approval be given for a lead Strategic Property team function to be developed with all land and property issues integrated, managed on a hub and spoke basis with the responsibility for overall co-ordination and oversight of delivery to be led by the Executive Director of Regeneration and Neighbourhoods working closely with other Council Directorates and key partners; and (v) that the proposed framework and robust criteria and methodology for developing the Council’s Property Plan and assessing all future land and property requirements be agreed, with examples of some of the early opportunities for rationalising the overall land and property estate detailed in paragraphs 4.4 to 4.7. of the report now submitted.
Word for word from the decision Knowsley published for this meeting. Source: councillors.knowsley.gov.uk

Follow this further

Built from Knowsley's papers

What the report saysPro

Report to Cabinet

Purpose of the report

To report on the outcome of the Council Land and Property Review. Executive Directors agreed that the Council should undertake a comprehensive review of the way its land and property assets are managed. External advisers, Drivers Jonas, were engaged to undertake this review to ensure that the future development of the land and property service takes full account of best practice at other Local Authorities. This report includes the proposed strategic Vision for a Council Property Plan and recommendations for implementation.

Implementation of the recommendations below will contribute significantly to delivery of key elements of the 7 Drivers of the Sustainable Communities Strategy and the Local Development Framework.

Recommendations

Members are recommended to:

To agree the proposed Vision for a Council Property Plan.

To agree to the development of a 3 year rolling Property Plan. This will be reviewed and updated annually. It will be aligned with the Corporate Plan process in line with best practice from other Local Authorities.

To agree that governance arrangements should be improved by closer involvement of Members through a Cabinet champion for all Council land and property issues. This should be the Portfolio lead for Regeneration. To agree that a lead Strategic Property team function should be developed with all land and property issues integrated and managed on a hub and spoke basis. Responsibility for overall co-ordination and oversight of delivery to be led by the Executive Director of Regeneration and Neighbourhoods working closely with other Council Directorates and key partners.

To agree the proposed framework and robust criteria and methodology for developing the Council’s Property Plan and assessing all future land and property requirements. Examples of some of the early opportunities for rationalising the overall land and property estate are at paras 4.4 to 4.7.

Background

Previous work has been carried out to develop a Council Estates Strategy over a significant period. Whilst this was useful it did not reach a conclusion or gain corporate acceptance. As part of the Service Review of Asset Management and the Rented Property portfolio, a study of the Council’s processes for managing land and property was undertaken. This included an overview of the current large range of land and property assets. External advisers familiar with best practice by Local Authorities provided valuable support. The review included an assessment of the Council’s current devolved process and practices for managing, reviewing and developing the land and property portfolios. As a result a series of recommendations is being made for improving management and co-ordination. This will result in a more strategic approach to assessing the Council’s existing and future land and property requirements.

The review has noted that good practice exists in the current arrangements. However, there is a need to be more strategic and joined up across the Council. The existing arrangements have not enabled fullest usage of properties, longer term planning, overall rationalisation of the estate and identifying costs and savings on a planned basis.

The proposed development of a cross Council strategic Property Plan will enable the Council to demonstrate that it is adopting best practice used by asset management beacon Local Authorities. This would include:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Council Land and Property ReviewReport 117 KB DownloadRead as text

More from Knowsley Cabinet

All decisions
MeetingDecisionOutcome
15 Jul 2026 Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App... Agreed Open
15 Jul 2026 2026/27 Revenue Budget - Quarter 1 Monitoring Update (*)RESOLVED – That:- (i) the key issues affecting 2026/27 budget monitoring as set out in this report be noted; and, (ii... Noted Open
15 Jul 2026 Capital Programme: 2026/27 Monitoring (*)RESOLVED – That the revised three-year Capital Programme of £118.011m in total as set out in section 4 and detailed i... Approved Open
15 Jul 2026 Local Government Association (Corporate Peer Challenge) - Progress Update on Delivery of Action PlanRESOLVED – That the draft Action Plan (attached at Appendix A) which sets out progress made to address the recommenda... Agreed Open
4 Jun 2026 2025/26 Revenue Budget Monitoring - Final Outturn Position (*)RESOLVED - That:- (i) the final 2025/26 budget monitoring position for the Council as set out in this report be noted... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies