RESOLVED – (i) That the positive feedback from consultation undertaken in November 2008 and the Local Authority’s response, be noted; (ii) that the preparation of a capital bid to the Learning and Skills Council on behalf of the Knowsley 14-19 Partnership to establish a new build Post 16 Centre for Learning in Huyton, be approved ; (iii) that the capital bid be approved prior to its submission to the Learning and Skills Council and that it be noted that the date of submission is to be agreed with the Learning and Skills Council; (iv) that the outcome of the site options appraisal be noted and that the bid submission proposes that the Post 16 Centre for Learning in Huyton is developed on the surplus Bowring Community Sports College site subject to a site feasibility study; and (v) that it be approved in principle that the Council agrees to the utilisation of the land on the Bowring Community Sports College site to the project at nil cost. (Note:In accordance with the provisions of Section 81 of the Local Government Act 2000 Councillors G J Morgan, R J Round JP and G A Wright declared a personal interest in the above item but remained in the meeting, took part in the discussion and voted thereon.)
Word for word from the decision Knowsley published for this meeting.Source: councillors.knowsley.gov.uk
a) To report the outcomes of the informal consultations on the proposal of Knowsley Post 16 Reform Strategy for Change undertaken during November 2008;
b) To report the outcome of a preliminary site options appraisal;
c) To request Cabinet approval to proceed with the preparation of a capital grant application to the Learning and Skills Council with a view to establishing a new build Post 16 Centre for Learning in Huyton.
Recommendations
Cabinet is recommended to:
(i) Note the positive feedback from consultation undertaken in November 2008 and the Local Authority’s response;
(ii) Approve the preparation of a capital bid to the Learning and Skills Council on behalf of the Knowsley 14-19 Partnership to establish a new build Post 16 Centre for Learning in Huyton ;
(iii) Agree to approve the capital bid prior to its submission to the Learning and Skills Council. The date of submission is to be agreed with the Learning and Skills Council.
(iv) Note the outcome of the site options appraisal and approve that the bid submission proposes that the Post 16 Centre for Learning in Huyton is developed on the surplus Bowring Community Sports College site subject to a site feasibility study; and
(v) Approve in principle that the Council agrees to the utilisation of the land on the Bowring Community Sports College site to the project at nil cost.
Background
Cabinet agreed on 15 October 2008 that key stakeholders in Post 16 Education assess the draft Strategic Business Case in advance of formal proposals for capital investment be submitted to the Learning and Skills Council. The report of that date set out in detail the local strategic options and the work undertaken to date within the 14-19 Collegiate Partnership. The outcomes of this consultation is summarised below and set out in detail in Appendix A to the report.
4. CONSULTATION PROCESS
Prior to consultation, all stakeholders were notified of the proposals. A leaflet outlining the proposal was distributed, inviting each stakeholder group to a consultation meeting. The leaflets also offered opportunities to send comments in writing, via e-mail or to call the Future Schooling in Knowsley office.
The following stakeholder groups were targeted:
• Staff, governors and students of Knowsley Community College; • Members of the governing bodies, temporary governing bodies, parents and children at the secondary schools with 6th form provision (Halewood College and All Saints Catholic High School); • Teaching staff, Year 10 and 11 students and their parents at other Knowsley secondary schools ; and • Area Partnership Board ‘Partnership Engagement Team’ networks.
The meetings were led by the Local Authority with representation from Learning and Skills Council. The meeting at All Saints was also supported by representation from the Archdiocese of Liverpool. Following the meetings there was an additional period to allow stakeholders to submit further comments until the 2nd December.
The views of stakeholders mostly centred around the practical implications to staff and students, transport links between the sites, the flexibility and range of subjects available, building design, future management & staffing arrangements, the ongoing representation of all relevant schools in the decision making process, the implications for governance and the funding and the future ownership of the new building. A summary of the generic issues raised by stakeholders is attached at Appendix A.
Overall, it is felt that the proposal received cautious support.
5. OUTCOME OF THE SITE OPTIONS APPRAISAL
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.