RESOLVED - ( i ) That the increase in the J Yearsley and Son Ltd contract value by £55,424.47 to the Longview Primary School alterations project to improve the reception of the School and facilitate the New Horizon Children’s Centre, be approved; and (ii) that the financial implications as detailed in section 4 of the report now submitted, be approved.
Word for word from the decision Knowsley published for this meeting.Source: councillors.knowsley.gov.uk
To report additional costs to the Longview Primary School alterations intended to improve the reception of Longview school and facilitate the new Children’s Centre that has exceeded the original contract sum approved on the 28 June 2007.
Recommendations
2.1To approve an increase in the J Yearsley and Son Ltd contract value by £55,424.47 to the Longview Primary School alterations project to improve the reception of the School and facilitate the New Horizon Children’s Centre.
2.2To approve the financial implication indicated in section 4.
Background
The project work was identified within the Directorate of Children and Family Services to redevelop and construct a new entrance and exit on Longview Primary School building to facilitate the new Children’s Centre, New Horizons.
3.1Fixed price competitive tenders were invited from six contractors. J.Yearsley and Sons Ltd submitted the lowest tender which was accepted at a contract value of £247,494.19 and approved on cabinet report DCS41/2007 28/06/07.
3.2During the execution of the contract additional costs were identified to make the overall project viable. These additional costs were not identified during initial design stage with the client. Additional requested works were for • Rewiring works to the refurbished areas ahead of the main rewiring scheme carried out during 2008. • External works to meet the extra requirements of the planning department. • Unforeseen building work to the existing area which were only identified when work commenced. • Reinstatement works to the Portakabin contract which will be claimed from and paid by Portakabin as part of their final account. • Additional costs paid due to the extended contract period and out of sequence working required to carry out the above works.
3.3To conclude the contract amount has now been increased to a value of £302,918.66 a contract increase of £55,424.47, plus additional fees of £7,490.81 and in accordance with Financial Procedure Rules this report is also presented to the Borough Treasurer for consideration and approval.
4. RESOURCE IMPLICATIONS
4.1Financial
The additional costs and associated funding have been identified to meet the project’s final account as detailed in the following financial summary, and has been contained within the contingencies of the overall project.
2007/08 Total Capital Cost £ £ Original Contract value 247,494.19 Additional Construction Costs 55,424.47 New Contract value 302,918.66 Original 2020 fees 34,929.19 Additional 2020 fees 7,490.81 Revised 2020 fees 42,420.00
New Project Total 345,338.66
Total Additional Approval 62,915.28
Financed by: Devolved Formula 15.000.00 Access Funding 122.000.00 NDC Grant 59,000.00 Children’s Centre 149,338.66
Total Funding 345,338.66
4.2Human
Advice was given in advance of any disruption that would impact on the operation of the school, any disruptive work was carried out during the weekend throughout the refurbishment programme.
4.3Information Technology
Additional IT connections and telephone lines were installed to accommodate the staffing changes to the new layouts. 4.4 Physical Assets
The new Children’s Centre, which is contained within the Directorates Asset Management Plan, has greatly improved the property assets of KMBC providing a valuable service for the community. This project is in line with the Future Schooling in Knowsley Plan for the continued improvement of Longview School.
5. RISK ASSESSMENT
5.1Had the additional work not been undertaken during the construction period it would have resulted in delivering a facility not fit for purpose and the Children Centre being unable to offer a full child care service to the community.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.