Resolved
RESOLVED – That the response of Cabinet be welcomed.
Economic Development and Environment Scrutiny Committee decided this item on Monday 22 March 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the response of Cabinet be welcomed.
APPENDIX A
Draft Cabinet response to Recommendations contained in the Highways Capital Programme Review conducted by a working group of the Economic Development and Environment Scrutiny Committee.
Scrutiny Recommendation Proposed Cabinet Response Reasons
Recommendation 1: That the current prioritisation and allocation of The Cabinet endorses this recommendation The Cabinet agrees that the review of the funding within the highways capital programme be and requests the Executive Director of capital programme prioritisation process is reviewed and updated, including the development Regeneration Economy and Skills develops needed in order to ensure that capital is of criteria which: a prioritisation process and criteria for the directed across the Borough in a a) reflects the need to allocate monies on a Capital Programme . transparent manner and in accordance borough wide basis as well as the need to Timescale for implementation – End March with Local Transport Plan objectives. meet national and corporate policy objectives. 2010.. b) incorporate criteria for scheme selection for those schemes which have received the same/similar scoring after being considered against the revised prioritisation criteria.
Recommendation 2: That development of the highways capital The Cabinet endorses this recommendation The Cabinet agrees that a 3 year capital programme be extended such that a three year and requests the Executive Director of programme/ plan will be beneficial. It will programme is produced. This will be a rolling Regeneration Economy and Skills develops enable longer term planning and give programme which is updated and published in a template for a three year programme which members and other key stakeholders advance each year. is published annually. more information about likely timescales Timescale for implementation – End March for delivery of schemes across the 2010. Borough. Recommendation 3: That formal approval processes be reviewed and The Cabinet agrees with this The Cabinet supports the streamlined in order that one report is approved recommendation and requests the Executive recommendation to streamline the current by the Executive Director of Regeneration, Director of Regeneration, Economy and approvals process which is inefficient and Economy and Skills in consultation with the Skills to progress the appropriate approvals time consuming. The benefits of a relevant portfolio holder for the full capital as necessary streamlined process will allow more officer programme in advance of that year’s works with Timescale for implementation – End March time to be focussed on delivery of quarterly updates then being provided (if needed) 2010-11, ongoing. schemes on the ground and forward explaining any unforeseen changes/updates to planning of projects. the programme.
Recommendation 4: That a streamlined approval process be The Cabinet endorses the recommended The Cabinet supports this implemented in line with recommendation 3, thus action and requests the Executive Director of recommendation as set out in removing the need to gain both outline and Regeneration Economy and Skills progress recommendation 3 above. detailed approvals for capital schemes and the streamlined approvals process with effect providing officers with more resources to complete from 1 April 2010. forward planning and deliver schemes.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Highways Capital ProgrammeAppendix | 67 KB | DownloadRead as text |
Follow Economic Development and Environment Scrutiny Committee at Knowsley and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Mar 2011 | 2010/11 Quarter 3 PerformanceRESOLVED – That the action being taken to address areas of under performance be endorsed. | Decided | Open |
| 21 Mar 2011 | A Review of the Maintenance of High Speed Roads in the Knowsley Metropolitan AreaRESOLVED – (i) That the following recommendations of the working group be endorsed and referred to the Cabinet for ap... | Approved | Open |
| 21 Mar 2011 | A Review of the Highways Capital ProgrammeRESOLVED – (i) That satisfactory progress had been made to date on the implementation of recommendations of the Worki... | Decided | Open |
| 21 Mar 2011 | A Review of the Winter Gritting ServiceRESOLVED – (i) That satisfactory progress had been made to date on the implementation of the recommendations; and (ii... | Decided | Open |
| 21 Mar 2011 | Future Waste Collection Options ReviewRESOLVED – (i) That the response of the Cabinet be welcomed; and (ii) that an update report on the implementation of ... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.