Highways Capital Delivery Programme for 2027/28 and Highway Maintenance Revenue Programme for 2026/27

Approved Executive 1 paper

AI summaryCabinet approved £6.000m of 2027/28 capital highways work and £3.058m of 2026/27 revenue work, but no capital money can be spent until the TCR Grant Funding Agreement is signed [D][P80][P23][P37].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCapital work covers 2027/28 and revenue work covers 2026/27 [D].
Money£6.000m capital; £3.058m revenue [P80][P23]No capital spend before the grant agreement is signed [P37].
What happens nextConsultations, orders and evaluation [D]Implementation may follow if objections are absent or withdrawn [D].
Who it affectsResidents, businesses and visitors [4.11]Works include maintenance, safety and sustainable travel [2.1].

What was decided

Cabinet approved the 2027/28 Highways Capital Delivery Programme in Appendix A and the 2026/27 Highway Asset Management Revenue Programme in Appendix B [D].

It approved the Principal Contractor and Principal Designer for both programmes in accordance with the Construction (Design and Management) Regulations 2015, subject to approval of all relevant health and safety documents [D].

It approved consultations and advertising, the legal process for Traffic Regulation Orders, and evaluation after implementation [D]. The Executive Director (Place) may implement schemes if no objections are received or an objection is withdrawn, and the Head of Legal Services and Information Governance may make an advertised Order if no objections remain unwithdrawn [D].

Why

The highway asset is continuing to deteriorate, and available capital and revenue funding is insufficient to maintain its current condition [4.4]. The programme aims to reduce the rate of deterioration, with the continuing network risk monitored through the Departmental Risk Register [4.4]. Report 4.4

The programmes are balanced to meet the needs of residents, businesses and visitors while supporting lifecycle planning, asset stewardship and better value for money [4.11]. Report 4.11

A two year capital programme allows preparation in the first year and construction in warmer months of the second year [4.6]. The revenue programme is mainly reactive, so a one year programme is used [4.7]. Report 4.6, 4.7

What happens next

The Executive Director (Place) will action the necessary statutory notification and consultation [D][8.2]. The Executive Director may then implement the schemes if no objections are received or an objection is withdrawn [D]. Report 8.2

The Head of Legal Services and Information Governance is authorised to complete the legal and administrative procedures needed to advertise the Traffic Regulation Orders under the Road Traffic Regulation Act 1984 and Traffic Management Act 2004 [D]. The Order can be made as advertised if no objections remain unwithdrawn [D].

No capital money may be spent until the TCR Grant Funding Agreement has been received and signed [P37]. The schemes will be evaluated after implementation [D]. Report P37

The money

  • £6.000m 2027/28 Highways Capital Delivery Programme total [P80] Report P80
  • £3.058m 2026/27 Highway Asset Management Revenue Programme resources [P23] Report P23
  • £3.058,270 Detailed total for 2026/27 reactive and routine works [P82] Report P82
  • £32.780m Knowsley Council highways allocation from 2027/28 to 2031/32 [1.2] Report 1.2
  • £3.171m Council funded highways revenue budget available for 2026/27 [P38] Report P38
  • £10.560m Five year bid for additional highways staff resources [P40] Report P40
  • £7.000m Approximate staff allocation needed to maintain current staffing levels [P40] Report P40
  • £308m Combined Authority allocation for highways maintenance, road safety and sustainability schemes [4.2] Report 4.2

Options considered

  • Chosen: Implement the 2027/28 Highways Capital Delivery Programme. Appendix A sets out the available new resources [P7][P61]. Report P7, P61
  • Chosen: Implement the 2026/27 Highway Asset Management Revenue Programme. Appendix B sets out the proposed revenue programme [P8][P81]. Report P8, P81
  • Chosen: Deliver capital works over two years. Preparation can occur in the first year so construction can occur in warmer months of the second [4.6][4.7]. Report 4.6, 4.7
  • Chosen: Deliver revenue works over one year. The revenue programme is mainly reactive [4.7]. Report 4.7
  • Chosen: Allocate £6.000m to 2027/28 and retain the remainder. The funding is intended to be split relatively equally across the five year period [4.8]. Report 4.8
  • Rejected: Undertake maintenance on unadopted highways. Limited funding means the Council cannot consider this work [4.16]. Report 4.16
  • Rejected: Build new parking facilities for residential properties. The Council is not in a position to deliver or construct these facilities [4.16]. Report 4.16

Implications

  • Financial: No capital money can be spent until the TCR Grant Funding Agreement has been received and signed [P37]. Report P37
  • Financial: Strong delivery could put Knowsley Council in a position to bid for programme wide underspends to fund additional works [4.21]. Report 4.21
  • Risk: The road network is likely to continue deteriorating if funding does not increase [4.4]. Report 4.4
  • Staffing: Knowsley Council faces a risk of insufficient staff and contractor resources for the works [P40][P42]. Experienced highway officers may be difficult to recruit, so approval of new posts may be needed quickly [P41]. Report P40, P41, P42
  • Legal: The necessary consultations, advertisements and Traffic Regulation Order procedures must follow the relevant statutory requirements and legislation [D][4.17]. Any objection that remains unwithdrawn will be referred to the Governance and Audit Committee [8.2]. Report 4.17, 8.2
  • Climate: The Highways team will work with contractors and suppliers to reduce the carbon footprint of works, collect baseline data, consider the DfT Decarbonisation Toolkit, and provide walking and cycling facilities where schemes are linked to sustainable travel [7.1]. Report 7.1
  • Equalities: The proposal has a direct impact and the report identifies many positive impacts [P46][P86]. Individual Equality Impact Assessments will be produced for the Appendix A schemes [P45]. Report P45, P46, P86
  • Other: The Council cannot use the limited funding to work on unadopted highways or deliver new parking facilities for residential properties [4.16]. Report 4.16

Who and where

  • Borough residents, businesses and visitors [4.11] Report 4.11
  • People using the adopted road, footway and cycleway network [4.17] Report 4.17
  • All road users during scheme works [P88] Report P88
  • Older people and people with limited mobility [P88] Report P88
  • Wheelchair and mobility scooter users [P89] Report P89
  • People with learning disabilities and visually impaired people [P89] Report P89
  • Unpaid carers [P88] Report P88
  • Residents in areas of multiple deprivation [P90] Report P90

Timeline

  • October 2025: Knowsley Council submitted a bid for funding for additional highways staff resources [P40]. Report P40
  • December 2025: The Combined Authority Cabinet agreed £308m for highways maintenance, road safety and sustainability schemes [4.2]. Report 4.2
  • 21 January 2026: Cabinet gave approval to accept the TCR funding [P36]. Report P36
  • 5/03/2026: The Equality Impact Assessment was completed [P83]. Report P83
  • 2026/27: The Highway Asset Management Revenue Programme covers mainly reactive maintenance works [4.7][P81]. Report 4.7, P81
  • June 2026: Allocation of the additional staff funding is currently anticipated [P40]. Report P40
  • 2027/28: The Highways Capital Delivery Programme is approved for delivery over a two year period [4.7][D]. Report 4.7
  • 2027/28 to 2031/32: The £32.780m highways allocation can be split between years as the Council sees fit [1.2]. Report 1.2

Plain English for the jargon

  • Transport for City Regions, TCR: Central Government funding settlement for eligible mayoral strategic authorities [1.1].
  • Highways Capital Delivery Programme: A two year capital works programme, with preparation in the first year and construction in warmer months of the second [4.6][4.7].
  • Highway Asset Management Revenue Programme: A one year programme focused mainly on reactive highway work [4.7].
  • Traffic Regulation Order: A legal order used for parking restrictions, moving traffic, speed limits and temporary traffic arrangements [4.17][P31].
  • Local Cycling and Walking Improvement Plan, LCWIP: The City Region and Knowsley plans used to identify linked sustainable travel schemes [4.15].
  • Equality Impact Assessment: An assessment of effects on protected characteristics, with one for the report and individual ones for Appendix A schemes [P45][P46].
  • DfT Decarbonisation Toolkit: Guidance that the Highways team will consider for scheme delivery [7.1].
  • Departmental Risk Register: The register used to monitor the continuing risk of highway network deterioration [4.4].
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item61

Resolved

RESOLVED – That:- ( i ) the Implementation of the Highways Capital Delivery Programme for new resources in 2027/28 as set out at Appendix A be approved; (ii) the Implementation of the Highway Asset Management Revenue Programme for 2026/27 as set out at Appendix B to this report be approved; (iii) the Appointment of the Principal Contractor and Principal Designer for the schemes identified in the 2027/28 Highways Capital Delivery Programme and the 2026/27 Highway Asset Management Revenue Programme be approved, in accordance with the Construction (Design and Management) Regulations 2015 subject to approval of all relevant health and safety documentation; (iv) the Carrying out of all necessary consultations and advertisements of the schemes associated with the 2027/28 Highways Capital Delivery Programme and the 2026/27 Highway Asset Management Revenue Programme, pursuant to all relevant statutory requirements and legislation be approved. Should no objections be received within an objection period, or if such an objection is lodged and then withdrawn, the Executive Director (Place) will then be authorised to implement the schemes; (v) The Head of Legal Services and Information Governance be authorised to carry out the necessary legal and administrative procedures required to advertise the Traffic Regulation Orders associated with the programme, pursuant to the Road Traffic Regulation Act 1984 and the Traffic Management Act 2004 (and Regulations made under those Acts) and to make the Order as advertised if there are no objections which remain unwithdrawn; and, (vi) the undertaking of post-implementation evaluation exercises for the schemes identified in the 2027/28 Highways Capital Delivery Programme and the 2026/27 Highways Asset Management Revenue Programme be approved.
Word for word from the decision Knowsley published for this meeting. Source: councillors.knowsley.gov.uk

Follow this further

Built from Knowsley's papers

What the report saysPro

Report to Cabinet, 21 pages

Executive summary

1.1In the 2025 Spending Review undertaken by Central Government it was confirmed that £15.6 billion would be made available between 2027 and 2032 to provide Transport for City Regions (TCR) settlements for nine eligible mayoral strategic authorities. Subsequently the Liverpool City Region Combined Authority (CA) was awarded £1.581 billion, with £308m of this being for highways maintenance as well as road safety and sustainability schemes across the City Region.

1.2The Combined Authority allocated £32.780m of the TCR funding to Knowsley Council for highways works between financial years 2027/28 and 2031/32, which can be split between years as the Council sees fit. It is proposed that £6m of the £32.780m be allocated for financial year 2027/28, with the remainder of funding retained for future years.

1.3This report seeks authorisation for the 2027/28 Highways Capital Delivery Programme and the 2026/27 Highway Asset Management Revenue Programme as set out in Appendices A and B respectively. 2 CONTRIBUTION TO THE KNOWSLEY COUNCIL PLAN 2025-2030

2.1This grant funding will facilitate a number of highway maintenance, road safety and sustainable travel schemes, which will contribute to the Council Plan by delivering an effective, high quality service which will support residents by improving the condition of the highway, sustainable travel infrastructure and road safety.

2.2The funding will also contribute to the Council Plan by encouraging growth that benefits everyone, as some of the money will be used on schemes to improve accessibility to town centres and places of employment in the Borough.

Recommendations

Members of the Cabinet are recommended to approve the:

(a) Implementation of the Highways Capital Delivery Programme for new resources in 2027/28 as set out at Appendix A;

(b) Implementation of the Highway Asset Management Revenue Programme for 2026/27 as set out at Appendix B to this report;

(c) Appointment of the Principal Contractor and Principal Designer for the schemes identified in the 2027/28 Highways Capital Delivery Programme and the 2026/27 Highway Asset Management Revenue Programme, in accordance with the Construction (Design and Management) Regulations 2015 subject to approval of all relevant health and safety documentation;

(d) Carrying out of all necessary consultations and advertisements of the schemes associated with the 2027/28 Highways Capital Delivery Programme and the 2026/27 Highway Asset Management Revenue Programme, pursuant to all relevant statutory requirements and legislation. Should no objections be received within an objection period, or if such an objection is lodged and then withdrawn, the Executive Director (Place) will then be authorised to implement the schemes;

(e) The Head of Legal Services and Information Governance to carry out the necessary legal and administrative procedures required to advertise the Traffic Regulation Orders associated with the programme, pursuant to the Road Traffic Regulation Act 1984 and the Traffic Management Act 2004 (and Regulations made under those Acts) and to make the Order as advertised if there are no objections which remain unwithdrawn; and, (f) Undertaking of post-implementation evaluation exercises for the schemes identified in the 2027/28 Highways Capital Delivery Programme and the 2026/27 Highways Asset Management Revenue Programme.

Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Highways Capital Delivery Programme for 2027/28 and Highway Maintenance Revenue Programme for 2026/27Report 21 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Knowsley

Search all
  1. Highways Capital Delivery Programme for 2027/28 and Highway Maintenance Revenue Programme for 2026/27This decision
  2. A Review of the Highways Capital ProgrammeDecided
  3. Highways Capital ProgrammeDecided
  4. Scrutiny Review of Highways Capital Programme - Cabinet ResponseAgreed
  5. Review of the Highways Capital ProgrammeApproved

More from Knowsley Cabinet

All decisions
MeetingDecisionOutcome
15 Jul 2026 Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App... Agreed Open
15 Jul 2026 2026/27 Revenue Budget - Quarter 1 Monitoring Update (*)RESOLVED – That:- (i) the key issues affecting 2026/27 budget monitoring as set out in this report be noted; and, (ii... Noted Open
15 Jul 2026 Capital Programme: 2026/27 Monitoring (*)RESOLVED – That the revised three-year Capital Programme of £118.011m in total as set out in section 4 and detailed i... Approved Open
15 Jul 2026 Local Government Association (Corporate Peer Challenge) - Progress Update on Delivery of Action PlanRESOLVED – That the draft Action Plan (attached at Appendix A) which sets out progress made to address the recommenda... Agreed Open
4 Jun 2026 2025/26 Revenue Budget Monitoring - Final Outturn Position (*)RESOLVED - That:- (i) the final 2025/26 budget monitoring position for the Council as set out in this report be noted... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies