Town Centre Evacuation Plans

Noted Scrutiny 1 paper

Safer, Stronger Communities Scrutiny Committee noted this item on Thursday 31 March 2011. Below is the council's own wording, with the papers it was decided on.

Item32

Resolved

RESOLVED – That it be noted that, as part of the post-exercise roll-out of the remaining Town Centre plans, a report on the exercise, learning points to be incorporated in the final versions of the plans, together with the plans themselves, will be submitted to a future meeting of the Committee for consideration.
Word for word from the decision Knowsley published for this meeting. Source: councillors.knowsley.gov.uk

Follow this further

Built from Knowsley's papers

What the report saysPro

Report to Safer, Stronger Communities Scrutiny Committee

Background

Emergency responders have a duty under the Civil Contingencies Act 2004 to assess the risk of major disruptive incidents occurring and to collaboratively plan to manage and respond to such emergencies. Mass evacuation of a town centre, however caused, is clearly a foreseeable risk for which multi-agency response arrangements should be in place. With this assessment in mind, some work towards compiling Town Centre Evacuation Plans for Knowsley was initially undertaken in 2007 and a brief document was produced which incorporated some suggested zoning maps and evacuation procedures for Huyton, Kirkby and 1 Prescot. However, this work was largely carried out by the incumbent Emergency Planning Officer in isolation, without the full engagement of appropriate partner agencies and other stakeholders, nor did it proceed beyond a development of an un-ratified draft document. The plan which was developed at that time was reviewed by Knowsley’s Emergency Planning team in 2010. The review comprised an assessment of the plan against publicly available town and city- centre evacuation plans and also a comparison with good practice guidance available via the Communities of Practice for Public Service website (http://www.communities.idea.gov.uk). The finding of the review was that the 2007 draft plan was not fit for purpose.

Management of the work to develop Town Centre Evacuation Plans

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Town Centre Evacuation PlansPlan 84 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Knowsley

Search all
  1. Town Centre Evacuation PlansThis decision
  2. Kirkby Town Centre Investment (*)Agreed
  3. 25/00681/FUL - The Installation oF 3No Antennas, 1No GPS Node and Associated Ancillary Development Thereto - Chads Parade, Kirkby Town Centre, Knowsley, L32 8RDNoted
  4. Prescot Town Centre InvestmentApproved
  5. Kirkby Town Centre Retail Development - Phase 2Approved
  6. Adoption of the Town Centre Uses Supplementary Planning DocumentApproved

More from Knowsley Safer, Stronger Communities Scrutiny Committee

All decisions
MeetingDecisionOutcome
31 Mar 2011 Forward Plan - April to July 2011RESOLVED – That the content of the item, which fell within the remit of the Committee and had been included in the la... Noted Open
31 Mar 2011 2010/11 Quarter 3 PerformanceRESOLVED – (i) That the summary of Quarter 3 performance outturn for 2010/11, be noted; and (ii) that the action bein... Noted Open
31 Mar 2011 Review Report: Community EmpowermentRESOLVED - That the following 15 recommendations be endorsed and referred to the Council’s Cabinet for consideration:... Approved Open
31 Mar 2011 Update Report: Scrutiny Review of Behavioural ChangeRESOLVED – (i) That the progress to date on the implementation of the recommendations of the Working Group be endorse... Decided Open
31 Mar 2011 In-meeting Review: The Preliminary Flood Risk Assessment ReportRESOLVED – (i) That the action to be taken as set out in the Preliminary Flood Risk Assessment Report be endorsed; an... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies