Knowsley Metropolitan Borough Council
Cabinet, Wednesday 18 March 2026 at 4.00pm

Prescot Town Centre Investment

Approved Executive 1 paper

AI summaryCabinet approved a Cityheart contract to progress Prescot Shopping Centre design to RIBA Stage 4, the technical design stage, with £0.6m from the £2m Regeneration Capacity Building Fund. [P9] [P10] [4.16] A full business case is required before construction. [1.6]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFeasibility, detailed design and development will proceed [P9]
Money£0.6m allocated [P10]From the £2m Regeneration Capacity Building Fund [P10]
What happens nextFull business case required [1.6]Before any construction begins [1.6]
Who it affectsPrescot regeneration and housing [1.5]Shopping centre site and future homes [1.5]

What was decided

Cabinet approved a contract with Cityheart for further feasibility, detailed design and development to progress the regeneration of Prescot Shopping Centre. [D] [P9] Report P9

Cabinet approved the allocation of £0.6m from the £2m Regeneration Capacity Building Fund to enable progression to RIBA Stage 4. The fund was provided by the Liverpool City Region Combined Authority. [D] [P10] Report P10

Cabinet delegated authority to the Executive Director (Place) to negotiate contract details under the Council’s governance requirements. The Head of Legal Services and Information Governance was authorised to execute resulting legal documents. [D] [P11] Report P11

Why

Cityheart was selected as the preferred developer in October 2024. Collaborative feasibility work has since identified a workable scheme option. [1.3] Report 1.3

The covered mall floorspace no longer meets modern retailer requirements, so interest from tenants remains limited. [4.7] Report 4.7

Retaining the centre in its current format would remain a financial pressure. Early feasibility says the annual revenue requirement for regeneration would be similar to the current holding costs. [4.9] [1.6] Report 4.9, 1.6

What happens next

The Stage 4 work is likely to take up to 12 months. It will cover detailed costing, coordination, construction planning, market engagement and a comprehensive planning submission. [4.11] Report 4.11

Once full and detailed costs are known, the Council will consider the business case before tendering the works. A further report will set out the comprehensive financial implications. [4.16] [P28] Report 4.16, P28

Contract details can be negotiated under delegated authority. Relevant service areas will provide programme input, and the Major Developments Team will monitor Cityheart’s contract. The Council will continue meeting existing tenants as plans progress. [P11] [P30] [P32] [8.1] Report P11, P30, P32, 8.1

The money

  • £0.6m Allocated from the £2m fund to enable progression to RIBA Stage 4 Report P10
  • £0.550m Proposed investment to reach RIBA Stage 4, covering consultation, surveys, professional fees, design development and planning submissions Report P26
  • £0.050m Estimated cost of external solicitor support for preparing the agreement and advising on the delivery route Report P27
  • £2m External grant fund provided to the Council by the Liverpool City Region Combined Authority Report P10, P26, P27
  • £1.6m Earlier Cabinet investment in initial demolition, including the former Stephenson’s Printworks building and an unviable section of the shopping centre Report 4.3

Options considered

  • Chosen: Cityheart feasibility and detailed design contract. It will develop full and detailed costs so the Council can consider the business case before tendering the works. Report P9, 4.16
  • Rejected: Retain the shopping centre in its current form. It would remain a financial pressure, and further savings would require significant investment and extensive remodelling. Report 4.9

Implications

  • Financial: Early feasibility says the annual revenue requirement for regeneration would be similar to current holding costs. The 2026/27 budget includes a permanent revenue allocation equivalent to annual holding costs. [1.6] [4.9] Report 1.6, 4.9
  • Legal: The Council will procure an external solicitor to prepare the agreement and advise on the delivery route. The Executive Director (Place) may negotiate contract details, and the Head of Legal Services and Information Governance may sign the legal documents. [P27] [P11] Report P27, P11
  • Equalities: The Equality Impact Assessment found no negative impacts. The report says the redevelopment will positively affect socio economic status and support footfall, economic activity and jobs. [P34] Report P34
  • Climate: The mixed use nature of the scheme is expected to support active travel. Energy efficient technologies and sustainable construction methods will be explored. [P38] Report P38
  • Risk: Early plans remain subject to refinement, further engagement and approval. Construction may temporarily disrupt familiar routes and reduce parking spaces. [4.14] [P50] [P49] Report 4.14, P50, P49
  • Staffing: Relevant service areas will provide ongoing officer input through existing programme and project arrangements. Specialist advice will be commissioned under procurement arrangements, and the Major Developments Team will monitor Cityheart’s contract. [P30] [P31] [P32] Report P30, P31, P32
  • Other: The proposed scheme includes further demolition and retained retail floor space near the high street. It also includes improved parking, new public routes, a new library, museum and cultural space, and future homes including affordable homes. [4.4] [4.6] [4.13] [1.5] Report 4.4, 4.6, 4.13, 1.5
  • Other: The Council intends to secure commitments on employment, skills and training, alongside wider community benefits. [P36] Report P36

Who and where

  • Existing shopping centre tenants Report 4.7, 8.1
  • Prescot residents and the wider community Report P7, P34
  • Shoppers, visitors, local independent retailers and other businesses Report P49, 8.1, 4.13
  • People seeking homes with one or two bedrooms, including affordable homes Report 1.5, 4.6
  • Older people and disabled people relying on parking and accessible routes Report P49, P50
  • Cityheart Report P9, P32
  • Knowsley Council service areas and the Procurement Team Report P30, P32
  • Liverpool City Region Combined Authority Report P10, P26

Timeline

  • 2016: The Council adopted the Prescot Town Centre Masterplan and identified Prescot Shopping Centre as a key site. [1.1] Report 1.1
  • December 2022: The Council acquired the shopping centre. [4.9] Report 4.9
  • Spring 2023: Public and stakeholder consultation ran for three weeks, followed by ongoing tenant engagement. [P49] Report P49
  • October 2024: Cabinet approved a legal exclusivity agreement with Cityheart for 12 months and £1.6m for initial demolition works. [4.3] Report 4.3
  • 2026-03-18: Cabinet approved the Cityheart contract and £0.6m grant allocation. [D]
  • 2026/27: A permanent revenue allocation equivalent to annual holding costs was made in the budget. [4.9] Report 4.9
  • up to 12 months: The proposed Stage 4 work is likely to take this length. [4.11] Report 4.11
  • before any construction begins: The Council must consider a full business case. [1.6] [4.16] Report 1.6, 4.16

Plain English for the jargon

  • RIBA Stage 4: Technical design covering detailed costing, coordination and construction planning before the Council considers the business case and tenders the works. [4.11] [4.16]
  • Regeneration Capacity Building Fund: External grant funding of £2m provided by the Liverpool City Region Combined Authority. [P10] [P26]
  • Holding costs: The ongoing costs of retaining the shopping centre in its current state. [4.4] [4.9]
  • Full business case: The detailed case for investment that the Council must consider before tendering the works. [4.16]
  • Mixed use development: A redevelopment combining homes with other appropriate town centre uses. [4.6]
  • Social value: Commitments on employment, skills, training and wider community benefits. [P36]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item59

Resolved

RESOLVED – That:- ( i ) entering into contract with Cityheart to undertake further feasibility, and detailed design and development to progress the regeneration of Prescot Shopping Centre be approved; (ii) the allocation of £0.6m from external grant funding of £2m Regeneration Capacity Building Fund provided to the Council by the Liverpool City Region ... view the full minutes text for item 59.
Word for word from the decision Knowsley published for this meeting. Source: councillors.knowsley.gov.uk

Follow this further

Built from Knowsley's papers

What the report saysPro

Report to Cabinet, 14 pages

Executive summary

1.1The Council adopted the Prescot Town Centre Masterplan in 2016, identifying a range of opportunities to create a more vibrant town centre and introduce town centre living. Prescot Shopping Centre was identified as a key site within the Masterplan and provides an opportunity for major transformation that will support the long term regeneration of the town.

1.2Under many years of private ownership the Centre has suffered from a lack of investment. The Council acquired the centre to ensure the site could play a positive role in Prescot’s future. A first phase of demolition has already taken place at the shopping alongside excellent progress made by the Council to enhance the wider town centre by investing in high street buildings and diversifying the mix of uses.

1.3Following Cabinet approval in October 2024 to enter an exclusivity agreement with Cityheart as the preferred developer for the site, the Council has been working collaboratively with them to explore a range of options for the future of the shopping centre site that will drive further regeneration. Through this process, a positive and deliverable option has now been identified. 1.4 This report sets out how the investment in detailed design and feasibility work with preferred developer Cityheart could unlock significant growth and opportunity in Prescot Town Centre and move this project forward positively. Retaining the shopping centre in its current form is not considered a viable option due to its outdated design that has resulted in lack of retailer interest and high running costs, which the Council continues to support each year whilst in its current state.

1.5The proposed next stage of work will open up the shopping centre site for investment, retain key existing retail units closest to the high street, improve the car park, create new public routes and deliver a new library, museum and cultural space. The redevelopment will also unlock future housing opportunities to meet local needs, including affordable homes.

1.6Early feasibility work shows that the annual revenue requirement for delivering this regeneration scheme would be similar to the current cost of retaining the centre in its current state. The proposals offer much greater benefits and significantly better long-term value for money while creating a modern, vibrant heart for Prescot. A full business case will be brought forward for decision before any construction begins.

2. CONTRIBUTION TO THE KNOWSLEY COUNCIL PLAN 2025-2030

The proposed scheme will contribute to the Council Plan by enabling the delivery of effective services, supporting inclusive growth and promoting fairness for residents. The proposed changes to the shopping centre will remove several vacant, under-utilised and inefficient building spaces to create opportunities for investment and redevelopment that better meets current and future needs.

Recommendations

Members of the Cabinet are recommended to: -

(a) Approve entering into contract with Cityheart to undertake further feasibility, and detailed design and development to progress the regeneration of Prescot Shopping Centre;

(b) Approve the allocation of £0.6m from external grant funding of £2m Regeneration Capacity Building Fund provided to the Council by the Liverpool City Region Combined Authority to enable progression to RIBA Stage 4;

(c) Grant delegated authority to the Executive Director (Place) to negotiate the contract details, in line with the Council’s governance requirements; and, (d) Authorise the Head of Legal Services and Information Governance to execute any resulting legal documentation on behalf of the Council.

Background

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Prescot Town Centre InvestmentReport 14 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Knowsley

Search all
  1. Prescot Town Centre InvestmentThis decision
  2. Adoption of Prescot Town Centre Masterplan Supplementary Planning DocumentApproved
  3. Prescot Town CentreNoted
  4. Prescot Townscape Heritage Initiative (*)Approved
  5. Update on Prescot Townscape Heritage Initiative & Portas Pilot BidsNoted
  6. Prescot Townscape Heritage InitiativeDecided

More from Knowsley Cabinet

All decisions
MeetingDecisionOutcome
15 Jul 2026 Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App... Agreed Open
15 Jul 2026 2026/27 Revenue Budget - Quarter 1 Monitoring Update (*)RESOLVED – That:- (i) the key issues affecting 2026/27 budget monitoring as set out in this report be noted; and, (ii... Noted Open
15 Jul 2026 Capital Programme: 2026/27 Monitoring (*)RESOLVED – That the revised three-year Capital Programme of £118.011m in total as set out in section 4 and detailed i... Approved Open
15 Jul 2026 Local Government Association (Corporate Peer Challenge) - Progress Update on Delivery of Action PlanRESOLVED – That the draft Action Plan (attached at Appendix A) which sets out progress made to address the recommenda... Agreed Open