Resolved

RESOLVED – That (i) Tarmac Trading Limited be appointed as the Preferred Bidder to deliver the Authority’s Highways Term Maintenance Contract; (ii) authority be delegated to the Executive Director (Place) in consultation with the Regeneration and Economic Development Cabinet Member to finalise the procurement process and associated documentation necessary for the completion of the Highways Term Maintenance Contract; (iii) the Highways Term Maintenance Contract be awarded to Tarmac Trading Limited for an initial period of five years with up to three potential single year extensions; and (iv) the Council’s Head of Legal Services be authorised to execute all relevant contract documentation in relation to the award of the contract.
Word for word from the decision Knowsley published for this meeting. Source: councillors.knowsley.gov.uk

Follow this further

Built from Knowsley's papers

What the report saysPro

Report to Cabinet

Purpose of the report

The purpose of this report is to seek authorisation to appoint the preferred bidder for the Council’s Highways Term Maintenance Contract.

Recommendations

Members of the Cabinet are recommended to:-

(a) Appoint Tarmac Trading Limited as the Preferred Bidder to deliver the Authority’s Highways Term Maintenance Contract;

(b) Delegate authority to the Executive Director (Place) in consultation with the Regeneration and Economic Development Cabinet Member to finalise the procurement process and associated documentation necessary for the completion of the Highways Term Maintenance Contract;

(c) Subject to recommendation (b) above, agree to award the Highways Term Maintenance Contract to Tarmac Trading Limited for an initial period of five years with up to three potential single year extensions; and,

(d) Authorise the Council’s Head of Legal Services to execute all relevant contract documentation in relation to the award of the contract. 3. BACKGROUND

3.1The highway network is one of the Council’s most valuable assets and is vital to the economic, social and environmental well-being of the Borough and indeed the wider Liverpool City Region. It provides access for business and communities, as well as contributing to the Borough's character and to the quality of life for those who live and work in Knowsley. Whilst there is a statutory duty upon the Council to maintain the Borough's public highway infrastructure, Government cuts since 2010 have had a significant impact on the relevant budgets, with Knowsley being one of the hardest hit authorities in the country. This has in turn led to the Council having to make difficult financial decisions. At the same time, demand for the service shows no sign of diminishing; in summary, service user expectations are high and the asset continues to deteriorate.

3.2In this context, a Commissioning Review of the Highways service commenced in November 2013. Elected Members have played a fundamental part in that Commissioning Review in order to ensure that local needs were fully understood and reflected in the outcome. In particular, the Neighbourhoods Scrutiny Working Group carried out a thorough Scrutiny Review into the commissioning process between August 2014 and November 2014. The Scrutiny Review considered the need to deliver improved highway infrastructure more efficiently against a backdrop of tighter budgets, increased costs and greater demand from residents. The Review considered the implementation of a Highway Asset Management Framework, the use of new technologies, and the refocusing of the service to a more planned and less reactive approach.

3.3On 17 December 2014, the Cabinet endorsed the recommendations of the subsequent Overview and Scrutiny Board report. The Cabinet agreed that it would be appropriate for the Council to make use of the Highways Maintenance Efficiency Programme Toolkit to inform the selection of the most appropriate procurement route arising from the Commissioning Review. The Cabinet also recognised that achieving the most economically advantageous tender in relation to the contractual delivery of highway works would be likely lead to structural changes within the Council’s Highways and Transportation service. 4. CURRENT DELIVERY ARRANGEMENTS

4.1The current delivery arrangements for the Council’s Highways and Transportation service involve the use of private sector suppliers under seven separate contracts to deliver the overall core activities via a “mixed economy” approach. Spending across these contracts in recent years has totalled around £8m per annum. The current contracts are:-

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Schedule of Key Performance IndicatorsAppendix B 187 KB Download
PDF
Award of Highways Term Maintenance Contract (*)Report 208 KB DownloadRead as text

At this meeting

Whole meeting

More from Knowsley Cabinet

All decisions
MeetingDecisionOutcome
15 Jul 2026 Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App... Agreed Open
15 Jul 2026 2026/27 Revenue Budget - Quarter 1 Monitoring Update (*)RESOLVED – That:- (i) the key issues affecting 2026/27 budget monitoring as set out in this report be noted; and, (ii... Noted Open
15 Jul 2026 Capital Programme: 2026/27 Monitoring (*)RESOLVED – That the revised three-year Capital Programme of £118.011m in total as set out in section 4 and detailed i... Approved Open
15 Jul 2026 Local Government Association (Corporate Peer Challenge) - Progress Update on Delivery of Action PlanRESOLVED – That the draft Action Plan (attached at Appendix A) which sets out progress made to address the recommenda... Agreed Open
4 Jun 2026 2025/26 Revenue Budget Monitoring - Final Outturn Position (*)RESOLVED - That:- (i) the final 2025/26 budget monitoring position for the Council as set out in this report be noted... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies