RESOLVED – That (i) the final outturn position for the 2014/15 Capital Programme, as identified in paragraph 3.3 of the report, be noted; (ii) a re-phasing of over £1m for the Prescot Townscape Heritage Initiative, as set out in paragraph 4.1 of the report, be approved; (iii) a new start scheme of over £1m for the Sustainable Transport Enhancements Package, as set out in paragraph 4.2.4 of the report be approved; and (iv) as a result of the adjustments identified in section 3 and section 4 of the report, the revised total Capital Programme of £35.791m, of which £23.087m is phased to be spent in 2015/16, as set out in paragraph 6.1.3 of the report, be noted.
Word for word from the decision Knowsley published for this meeting.Source: councillors.knowsley.gov.uk
This report presents the outturn position for the Council’s 2014/15 Capital Programme and also provides an update on the position for 2015/16 and future years.
Recommendations
Members of the Cabinet are recommended to:-
(a) Note the final outturn position for the 2014/15 Capital Programme as identified in paragraph 3.3 of this report;
(b) Approve a rephasing over £1m for the Prescot Townscape Heritage Initiative as set out in paragraph 4.1 of this report;
(c) Approve a new start scheme over £1m for the Sustainable Transport Enhancements Package as set out in paragraph 4.2.4 of this report; and,
(d) Subject to the approval of recommendations (b) and (c) above and as a result of the adjustments identified in section 3 and section 4 of this report, note the revised total Capital Programme of £35.791m, of which £23.087m is phased to be spent in 2015/16 as set out in paragraph 6.1.3 of this report. 3. 2014/15 CAPITAL PROGRAMME OUTTURN POSITION
3.1In the last quarter of 2014/15, four new schemes totalling £0.301m (£0.291m in 2014/15 and £0.010m in 2015/16) were approved in accordance with the Council’s Scheme of Delegation. These schemes have been added to the Council’s Capital Programme and are summarised below:-
Nutgrove Villa Refurbishment (£0.252m in 2014/15);
Jubilee Park Football Hub Improvement (£0.018m in 2014/15);
Quernmore Road Allotment Improvement (£0.015m in 2014/15); and,
Saxon Green Park Sustainable Urban Drainage Improvement (£0.016m in total - £0.006m in 2014/15 and £0.010m in 2015/16).
3.2In addition to the four new start schemes listed in paragraph 3.1 above, Appendix A provides details of a range of further amendments to the 2014/15 Capital Programme arising from the final outturn position and together totalling £0.985m. The final Capital Programme for 2014/15 was therefore £18.240m (before the impact of any rephasings requested at the outturn stage).
3.3From the final Capital Programme of £18.240m, a total of £16.958m (93%) was actually spent at the end of the year. The remaining expenditure of £1.282m has been re-phased into 2015/16 along with the associated resources. The table below summarises those rephasings and full details are provided at Appendix B to this report. The final 2014/15 Capital Programme is shown in full at Appendix C to this report:-
Amount Programme £m Highways Programme 0.407 Schools Programme 0.245 Housing Improvements 0.151 Waste and Green Space Strategies 0.133 Prescot Townscape Heritage Initiative 0.127 Economic Development Schemes 0.083 Kirkby Town Centre Regeneration 0.077 Leisure Services 0.033 Adult Social Care 0.014 Stockbridge Village Regeneration 0.012 TOTAL 1.282 4. MONITORING OF THE 2015/16 CAPITAL PROGRAMME
4.1Expenditure against the Planned Capital Programme
Expenditure against approved schemes at 31 July 2015 was £2.888m, which represents 17% of the total Programme for 2015/16 of £17.364m. Since the original 2015/16 Programme was approved by the Council on 4 March 2015, scheme managers have identified the need to rephase £2.811m of the 2015/16 Programme into 2016/17. The basis for these rephasings is summarised below:-
(a) Prescot Townscape Heritage Initiative £1.894m – as this rephasing is over £1m, the Cabinet is recommended specifically to approve this proposal. The contractors involved in this Initiative are employed by the relevant private building owners and not by the Council. The Council’s role is to check the quality of work and reimburse claims, and therefore the Authority has limited influence over the timescales. Work to historic buildings may encounter delays when specialist materials are needed, and expenditure may also be dependent on how quickly grant applications are progressed by the building owners and their consultants;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.