RESOLVED – ( i ) That the Committee be minded to grant planning permission and the Head of Planning and Highways be authorised to grant planning permission subject to:- (a) the conditions set out in the report of the Executive Director (Regeneration and Development) and any additional or amended conditions that the Head of Planning and Highways, in consultation with the Chairperson of the Planning Committee, considers appropriate; (b) the applicant entering into a Section 106 legal agreement to secure the measures set out in a social value strategy; and (c) the applicant providing additional detail in relation to Flood Risk to the satisfaction of the Lead Local Flood Authority; (ii) that in the event that the applicant does not, within 6 months of this meeting, enter into a Section 106 agreement to secure the measures set out in a social value strategy or does not provide the additional detail to the satisfaction of the Lead Local Flood Authority, the Head of Planning and Highways be authorised to refuse planning permission on such grounds; and (iii) that the Head of Planning and Highways write to the applicant expressing the Committee’s concerns about the company’s approach to the required planning processes for this retrospective application for planning permission.
Word for word from the decision Knowsley published for this meeting.Source: councillors.knowsley.gov.uk
A. It is recommended that Members delegate authority to the Head of Planning and Highways to grant planning permission under delegated powers subject to:-
(i) the conditions set out in the attached schedule, or such additional or amended conditions that the Head of Planning and Highways (in conjunction with the Chair of Planning Committee) considers appropriate;
(ii) the applicant entering into a Section 106 legal agreement to secure measures set out in a social value strategy, and;
(iii) the applicant providing additional detail in relation to Flood Risk to the satisfaction of the Lead Local Flood Authority.
B. In the event of the applicant not entering into a section 106 agreement, within 6 months of Planning Committee’s resolution, to secure measures set out in a social value strategy or not providing additional detail to the satisfaction of the Lead Local Flood Authority, that Members delegate authority to the Head of Planning and Highways to refuse planning permission under delegated powers, on such grounds.
CASE OFFICER:
Andrew Hunt (0151) -443 2204
Summary
This application relates to the retention of a 1,200 sq. metre storage unit (Use Class B8), which has already been erected.
The relevant key issues are:
The principle of development; Access and Highway Safety; Impact on Amenity; Design; Social Value, and; Flood Risk.
1. SITE AND SURROUNDINGS
1.1The application site is at Halewood International within a Primarily Industrial Area on Wilson Road, Huyton. The application specifically relates to the southern part of the site, near to Cronton Road.
2. PROPOSAL
2.1The proposal is for the retention of a 1,200sqm storage unit. The building is located at the south east part of the site and has been constructed using off-site construction methods. It is 9.57 metres high, 20.61 metres wide and 60.13 metres long. The building consists of Grey insulated steel sandwich panels and a white PVC coated roof membrane. The building is currently used for storage of bottles and crates of alcoholic beverages.
3. RELEVANT SITE HISTORY
None Relevant.
4. EQUALITIES ACT 2010
4.1In determining this application, the Local Planning Authority has considered the requirements under S149 of the Equalities Act 2010.
4.2Section 149 of the Act sets out a general duty that requires the council to have due regard to the need to:
eliminate discrimination, harassment and victimisation; advance equality of opportunity between persons who share a relevant protected characteristic and persons who do not share it, and; foster good relations between persons who share a relevant protected characteristic and persons who do not share it.
2 5. REPRESENTATIONS
5.1The application was publicised by letters sent to 23 neighbouring properties /businesses and by a site notice. No representations have been received.
6. CONSULTATIONS
Environmental Health & Consumer Protection – No objections subject to a condition to secure a construction management plan and restriction of construction hours 08:00-18:00 hours Monday to Friday, 08:00-13:00 hours Saturday and not at all on Sundays/Public Holidays.
Lead Local Flood Authority – In the absence of a site-specific flood risk assessment which is required under the National Planning Policy Framework, the Lead Local Flood Authority objects to this application and recommend refusal of planning permission until a satisfactory site-specific flood risk assessment has been submitted to the Local Planning Authority.
Local Highway Authority – No objection.
7. POLICY CONTEXT
7.1Paragraph 11 and 12 of the National Planning Policy Framework (NPPF 2019), an extract from which is set-out below, states that:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.