Knowsley Metropolitan Borough Council
Cabinet, Thursday 4 June 2026 at 3.00pm

Capital Programme: 2025/26 Final Outturn (*)

Agreed Executive 1 paper

AI summaryCabinet agreed the 2025/26 Capital Programme final outturn of £47.380m and approved a new three-year Capital Programme of £77.110m, with £66.373m planned for 2026/27.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedFinal 2025/26 spend £47.380m; three-year plan £77.110m
Money£47.380m (2025/26 outturn)Three-year programme totals £77.110m
What happens next2026/27 spend: £66.373mSchemes carry forward from rephased budgets
Who it affectsBorough residents and servicesSchools, highways, town centres, adaptations

What was decided

Cabinet agreed the 2025/26 Capital Programme final outturn of £47.380m, which was £9.102m (16%) below the original forecast of £56.482m. Report P9, 1.3, 4.2

Cabinet approved a new three-year Capital Programme totalling £77.110m, with £66.373m planned to be spent in 2026/27. Report P10, 1.4, 4.6

Cabinet noted the treasury management prudential indicators as set out in section 6 of the report. Report P11, 6.1

Why

Final expenditure was lower than forecast mainly because third party contractors made slower than expected progress on the Tarbock Island, Huyton Active Travel Corridor and Halewood Levelling Up schemes. Report 1.3, 4.2

The report says continued capital investment supports the Council Plan priorities of effective services for residents and growth that benefits everyone. Report 2.1, 2.2, P8

Total rephasings of £16.229m exceeded the assumed 10% level of £6.276m, which has prompted a review of the assumed rephasing rate for 2026/27 monitoring. Report 4.4

What happens next

The Executive Director (Resources and Partnerships) will review the assumed rephasing level for ongoing monitoring in 2026/27. Report 4.4

A further £10m of capital receipts are expected in 2026/27 from land on Knowsley Business Park and land south of Cherryfield Drive, and have been allocated to previously approved investments. Report 5.2

Updated capital receipts forecasts for current and future years will be brought to Members as part of ongoing monitoring and budget-setting. Report 5.3

The money

  • £47.380m Final 2025/26 Capital Programme expenditure Report 1.3, 4.2, 4.6
  • £9.102m (16%) Amount and percentage below the original 2025/26 forecast Report 1.3, 4.2
  • £56.482m Original 2025/26 forecast (Quarter 3 stage) Report 1.3, 4.2, 5.1
  • £77.110m New three-year Capital Programme total for 2026/27 and future years Report 1.4, 4.6, P10
  • £66.373m Scheduled to be spent in 2026/27 Report 1.4, 4.6
  • £4.6m Creating 246 new mainstream and special school places Report P14
  • £3.8m Disabled facilities and adaptations to residents' properties Report P14
  • £18.6m Highways improvements including M57 and Tarbock Island works Report P14
  • £1.2m Vehicles and food caddies for the food waste service starting April 2026 Report P14
  • £1.9m Halewood Levelling Up Fund and Halewood Leisure Centre Decarbonisation Report P14
  • £5.5m Town Centres including Prescot Shopping Centre demolition and Huyton Village Centre Phase 1 Report P14
  • £1.2m Homelessness prevention through purchase of six properties and grants to Registered Housing Providers Report P14
  • £0.851m Amendments to the Programme made during the last quarter of 2025/26 Report 4.3
  • £0.265m Additional Disabled Facilities Grant allocation announced in March 2026 Report 4.3
  • £6.276m 10% assumed rephasing built into the 2025/26 Programme Report 4.4
  • £16.229m Final rephasings at year end, above the assumed level Report 4.4
  • £0.948m Altbridge High Needs Provision Capital Allocation rephasing Report P19
  • £0.662m School Condition Allocation rephasing Report P19
  • £0.628m Copthorne Greenway Project rephasing Report P20
  • £0.612m Decent Homes for All rephasing Report P21
  • £2.928m Huyton Active Travel Corridor and Tarbock Island rephasing Report P22
  • £1.582m Halewood Levelling Up Fund rephasing Report P23
  • £0.581m Building Rationalisation and Co-location rephasing Report P24
  • £13.746m Capital receipts received during 2025/26 Report 5.1
  • £13.988m Capital receipts forecast at Quarter 3 Report 5.1
  • £10m Expected capital receipts in 2026/27 from Knowsley Business Park and Cherryfield Drive land Report 5.2
  • 6.26% Actual ratio of Financing Cost to Net Revenue Stream for 2025/26 Report 6.2
  • 5.65% Original forecast ratio for 2025/26 Report 6.2
  • 5.73% Forecast ratio for 2026/27 (excluding any Huyton Town Centre regeneration borrowing costs) Report 6.2
  • £286.940m Original estimate of Capital Financing Requirement for 2025/26 Report 6.3
  • £280.199m Actual year end Capital Financing Requirement for 2025/26 Report 6.3

Options considered

  • Chosen: Agree the 2025/26 outturn and approve the new three-year Capital Programme of £77.110m, noting the prudential indicators. Final expenditure was £47.380m and the new programme supports Council Plan priorities for residents and growth Report P9, P10, P11

Implications

  • Financial: The Capital Financing Requirement reduced below the original estimate, from £286.940m to £280.199m at the year end, with some entries still being finalised under the new IFRS 16 leases standard. Report 6.3
  • Financial: Financing costs as a share of revenue budget were 6.26% in 2025/26, higher than the 5.65% forecast because actual borrowing was higher than anticipated. Report 6.2
  • Risk: Slower progress by third party contractors on Tarbock Island, the Huyton Active Travel Corridor and Halewood Levelling Up caused a £9.102m underspend against forecast. Report 1.3, 4.2
  • Risk: Total rephasings of £16.229m exceeded the £6.276m built in assumption, prompting a review of the rephasing level for 2026/27 monitoring. Report 4.4
  • Equalities: There is no direct impact on people from the report itself; equality impact assessments are carried out for each individual capital scheme. Report 8.1, P39, P65
  • Climate: There are no direct climate implications, though the programme includes spending on decarbonisation schemes such as Halewood Leisure Centre and Knowsley Public Sector Decarbonisation. Report P14, P43
  • Legal: The treasury management prudential indicators were noted, with no variances identified as cause for concern. Report 6.1

Who and where

  • Borough residents receiving disabled facilities and adaptations Report P14
  • School pupils, with 246 new mainstream and special school places created Report P14
  • Residents at risk of homelessness, with six properties purchased and grants to Registered Housing Providers Report P14
  • Town centre users in Prescot and Huyton Report P14
  • Highway users on the M57 and around Tarbock Island Report P14, P22
  • Householders using the new food waste service starting early April 2026 Report P14
  • Halewood Leisure Centre users, with decarbonisation works delayed by procurement and substation planning issues Report P14, P23

Timeline

  • March 2026: Work by Scottish Power on the Wilson Road element of the Huyton Active Travel Corridor completed, later than originally planned. Report P22
  • March 2026: Additional Disabled Facilities Grant allocation of £0.265m announced. Report 4.3
  • 31 March 2026: End of 2025/26 financial year, with final outturn of £47.380m reported. Report 1.3, 4.6
  • Early April 2026: Food waste service to commence, supported by £1.2m of vehicle and caddie purchases. Report P14
  • July 2026: Altbridge Phase 2 scheme now expected to complete, delayed from Easter 2026 by heating system and asbestos issues. Report P19
  • September 2026: Post-16 provision planned to move to the Kirkby Centre as originally planned. Report P19
  • 2026/27: £66.373m scheduled to be spent on the Capital Programme. Report 1.4, 4.6
  • 2026/27: Five Decent Homes for All properties expected to complete and fully commit the remainder of the funding. Report P21
  • 2026/27: Building condition schemes under Building Rationalisation and Co-location to commence. Report P24
  • 2026/27: £10m of capital receipts expected from Knowsley Business Park land and land south of Cherryfield Drive. Report 5.2

Plain English for the jargon

  • Capital Programme: The council's plan for spending on long term assets and infrastructure such as buildings, roads and equipment.
  • Capital outturn: The actual final level of capital spending for a financial year, compared with the original forecast.
  • Prudential Indicators: Measures set under the Treasury Management Strategy to monitor borrowing and ensure capital expenditure is affordable and sustainable.
  • Rephasing: Moving planned capital spending from the financial year in which it was originally budgeted into a later year.
  • Capital Financing Requirement: A forecast of the council's future borrowing levels arising from capital investment.
  • Capital receipts: Money raised from selling council owned assets such as land, which can then be reinvested in the capital programme.
  • Capital Financing Requirement excluding PFI and Finance Leases: The borrowing forecast net of Private Finance Initiative schemes and finance leases, used to track underlying borrowing levels.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

RESOLVED – That:- (a) the final outturn position for the 2025/26 Capital Programme as set out in section 4 of this report be agreed ; (b) the new three-year Capital Programme of £77.110m in total as set out in paragraph 4.6 of this report be approved; and, (c) the treasury management prudential indicators as presented in section 6 of this report be noted.
Word for word from the decision Knowsley published for this meeting. Source: councillors.knowsley.gov.uk

Follow this further

Built from Knowsley's papers

What the report saysPro

Report to Cabinet, 11 pages

Executive summary

1.1This report explains how the Council’s capital resources were spent during 2025/26.

1.2The Capital Programme in 2025/26 invested in a wide range of schemes including improvements to highways across the Borough, disabled facilities and adaptations to residents’ properties, new mainstream and special school places and improvements to highways and Town Centres.

1.3The final level of Capital Programme expenditure for 2025/26 was £47.380m, which was £9.102m (16%) lower than the original forecast of £56.482m. The main reasons for this were slower than expected progress by third part contractors on the Tarbock Island, the Huyton Active Travel Corridor and the Halewood Levelling Up schemes.

1.4The Council’s total Capital Programme for the next three years is £77.110m, of which £66.373m is scheduled to be spent in 2026/27 and demonstrates the Council’s continued commitment to investing in the future of the Borough. 2. CONTRIBUTION TO THE KNOWSLEY COUNCIL PLAN 2025-2030

2.1The report demonstrates that the Council remains well placed to deliver its objectives as set out in the Council Plan. The level of expenditure included in the three-year Capital Programme demonstrates the Council’s continued commitment to investing in the future of the Borough. The importance of supporting the development of local jobs and local businesses is more important than ever, and the Council must do all it can to support the Borough’s economy amid the worsening national economic conditions.

2.2Continued capital investment will help to meet the Council’s priorities of delivering effective, high-quality support for residents, and encouraging growth that benefits everyone.

2.3The impact of the allocation of all capital resources will continue to be monitored as part of the ongoing capital programme monitoring and performance monitoring processes in 2026/27.

Recommendations

Members of the Cabinet are recommended to:-

(a) Agree the final outturn position for the 2025/26 Capital Programme as set out in section 4 of this report;

(b) Approve the new three-year Capital Programme of £77.110m in total as set out in paragraph 4.6 of this report; and,

(c) Note the treasury management prudential indicators as presented in section 6 of this report.

4. CAPITAL PROGRAMME: 2025/26 OUTTURN POSITION

4.1The Capital Programme in 2025/26 invested in a wide range of schemes including:-

• creating 246 new school places across mainstream and special schools (£4.6m); • providing disabled facilities and adaptations to residents’ properties (£3.8m); • improvements to the Borough’s highways including the M57 and Tarbock Island works (£18.6m); • purchase of vehicles and food caddies to enable the food waste service to commence early April 2026 (£1.2m); • continued progress on the Halewood Levelling Up Fund scheme including improvements to the walking and cycling links, as well as works commencing on the Decarbonisation of Halewood Leisure Centre (£1.9m); • improvements to Town Centres including the demolition of Prescot Shopping Centre and Phase 1 of the Huyton Village Centre Development (£5.5m); and, • providing support to residents to avoid them becoming homeless through the purchase of six properties and providing grants to Registered Housing Providers to purchase properties (£1.2m).

4.2The forecast at the quarter three stage was that total spending would be £56.482m. The actual level of expenditure at the end of the year was £47.380m, which was £9.102m (16%) less than the forecast. The main reasons for this were slower than expected progress on the Huyton Active Travel Corridor and Tarbock Island and Halewood Levelling Up schemes.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme: 2025/26 Final Outturn (*)Report 11 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Knowsley

Search all
  1. Capital Programme: 2025/26 Final Outturn (*)This decision
  2. Capital Programme: 2026/27 Monitoring (*)Approved
  3. Highways Capital Delivery Programme for 2027/28 and Highway Maintenance Revenue Programme for 2026/27Approved
  4. Capital Programme - 2025/26 and Future YearsApproved
  5. Capital Programme - 2025/26 and Future Years (*)Approved
  6. Capital Programme - 2024/25 and Future YearsApproved

More from Knowsley Cabinet

All decisions
MeetingDecisionOutcome
15 Jul 2026 Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App... Agreed Open
15 Jul 2026 2026/27 Revenue Budget - Quarter 1 Monitoring Update (*)RESOLVED – That:- (i) the key issues affecting 2026/27 budget monitoring as set out in this report be noted; and, (ii... Noted Open
15 Jul 2026 Capital Programme: 2026/27 Monitoring (*)RESOLVED – That the revised three-year Capital Programme of £118.011m in total as set out in section 4 and detailed i... Approved Open
15 Jul 2026 Local Government Association (Corporate Peer Challenge) - Progress Update on Delivery of Action PlanRESOLVED – That the draft Action Plan (attached at Appendix A) which sets out progress made to address the recommenda... Agreed Open
4 Jun 2026 2025/26 Revenue Budget Monitoring - Final Outturn Position (*)RESOLVED - That:- (i) the final 2025/26 budget monitoring position for the Council as set out in this report be noted... Noted Open