- That, (i) the additional responsibilities in relation to former Social Fund payments the County Council will assume from 1 April 2013 and in particular the scale of activity be noted, (ii) the work required and the timetable for achieving a successful launch of the new service be noted, and (iii) the release of £50,000 from the service transformation reserve to support the development of the scheme and service design be approved, to be repaid back to reserves in the event of resources becoming available from the government via the DWP.
Word for word from the decision Lancashire & Rossendale published for this meeting.Source: council.lancashire.gov.uk
This report provides an initial high level assessment of the work required to prepare the County Council to take on the new responsibilities from 1 April 2013. These relate to payments which currently form part of the Social Fund administered by the Department of Work and Pensions (DWP).
The County Council will become responsible for payments which generated approximately 50,000 applications in Lancashire in 2010/11, resulting in payments of over £5m. Creating the policy framework for dealing with these applications and the service and infrastructure to administer the scheme will require considerable work in a relatively compressed timescale.
In order to facilitate this it is recommended that the Cabinet approves the use of £50,000 from the service transformation reserve to fund a project manager for a maximum period of 12 months, in order that work can be progressed on an appropriate timescale prior to the resources being made available by the government for such set up costs being announced.
Recommendations
Cabinet is recommended to:
(i) Note the additional responsibilities in relation to former Social Fund payments the County Council will assume from 1 April 2013 and in particular the scale of activity; (ii) Note the work required and the timetable for achieving a successful launch of the new service; (iii) Approve the release of £50,000 from the service transformation reserve to support the development of the scheme and service design, to be repaid back to reserves in the event of resources becoming available from the government via the DWP. Background and Advice
See Appendix 'A'
Consultations
The report at Appendix 'A' sets out the need to consult with a wide range of stakeholders both on the principles of the new scheme and the detailed proposals prior to a decision by members on the final scheme. These consultations will inform the required equality analysis.
Implications:
This item has the following implications, as indicated:
Risk management
These new responsibilities will create a number of new risks for the County Council which will need to be managed within the design of the policy and delivery framework. These include risks around managing an entirely new type of demand led budget, a range of potential fraud risks and the usual risks which exist in the design and delivery of any new service within a fixed timescale.
Financial
Indications from the DWP are that initially both the costs of payments under the scheme and the costs of administering the scheme will be met through specific grant, with some reassessment of distribution at an early stage. In line with the Government's overall approach it is intended that these specific grants will be moved into the new equivalent of formula grant at an early opportunity. Allocations for benefit spend are to be made with reference to 2012/13 spending levels, although with spending of this sort there may be local factors which cause demand to swing widely from year to year, thus while reasonable this approach does contain some risk for all councils. It is not clear what basis will be used to allocate funding for administering the scheme but the working assumption is that, in total, it will be significantly less than is spent by DWP.
DWP has indicated that funding for set up costs will be available, but this seems likely only to be announced in the autumn. However, in order to meet the challenging timescales work must begin now and authority is being sought to fund activity in advance of any DWP resources being announced.
Any representations made to the Cabinet prior to the issue being considered in accordance with the Public Notice of Forward Plans
Name: Organisation: Comments:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.