AI summaryLancashire County Council Cabinet noted the Quarter 1 2026/27 Corporate Performance Report, with 20 of 36 rated indicators on track, five off target, and recovery plans in place for underperforming areas.
Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted Q1 2026/27 performance and improvement actions
MoneyNo direct financial implications
What happens nextQ2 2026/27 performance reportContinued monitoring and recovery activity for off-target areas
Who it affectsLancashire residents and businessesAcross four Council Plan ambitions
What was decided
Cabinet noted Quarter 1 2026/27 performance against the Council Plan 2025-2030 and the annual priorities in Moving the Dial, along with areas of strong performance and key actions for indicators not meeting target. Report P2, P3
Why
Section 3 of the Local Government Act 1999 places a best value duty on the council, and monitoring key performance indicators supports informed decision-making and oversight of statutory functions. Report P31, P32, P33
What happens next
Focused recovery plans are in place for indicators below target, with enhanced performance oversight and governance to accelerate progress through the rest of 2026/27. Report P22
New corporate key performance indicators that could not be reported in Quarter 1 will be developed so that data can be collected and performance reported in future quarters. Report P24, P25
Options considered
Chosen: Note the Quarter 1 2026/27 Corporate Performance Report. First quarterly report against the performance framework agreed by Cabinet on 2 July 2026. Report P2, P3, P27
Implications
Legal: Monitoring supports the best value duty under the Local Government Act 1999 and the balanced budget duty under the Local Government Finance Act 1992. Report P31, P34
Financial: No direct financial implications, though several indicators link to the council's overall financial position. Report P36
Equalities: Where relevant, actions to improve performance consider the impact on equality and diversity. Report P40
Risk: Each key performance indicator has commentary proportionate to current performance, including risks to achieving targets. Report P41
Other: Performance is reported alongside planning for Local Government Reorganisation, with statutory responsibility retained until Vesting Day in April 2028. Report P38
Who and where
Children and young people, including those with Education, Health and Care Plans Report P13, P20
Adults needing social care, reablement or safeguarding support Report P13, P25
Carers of adults receiving social care Report P25
Lancashire businesses and residents using highways services Report P14
Households using Household Waste Recycling Centres Report P15
Council service users and customers accessing council services Report P17
Timeline
April - June 2026: Period covered by Quarter 1 2026/27 performance report Report P1
2 July 2026: Cabinet agreed the key performance indicators and performance framework Report P4, P27
3 September 2026: Cabinet considered the Quarter 1 2026/27 Corporate Performance Report
April 2028: Vesting Day for new Lancashire Authorities under Local Government Reorganisation Report P38
Plain English for the jargon
RAG rating: Red, Amber or Green rating used to show whether a key performance indicator is off track, within tolerance, or on target.
Key performance indicator (KPI): A measure agreed by Cabinet to track progress against Council Plan priorities.
Council Plan 2025-2030: The council's overall plan setting out its ambitions for the period.
Moving the Dial: The annual priorities document supporting the Council Plan, including the Local Government Reorganisation programme.
Education, Health and Care Plan (EHCP): A plan for children and young people with special educational needs and disabilities.
Vesting Day: The date in April 2028 when new Lancashire Authorities take on responsibility from the county council under Local Government Reorganisation.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5
Resolved
That, following consideration of the performance of the Council in Quarter 1 of 2026/27 against the ambitions set out in the Council Plan 2025-2030 and, specifically the annual priorities set out in Moving the Dial, the areas of strong performance and the key actions identified against indicators that are not achieving targets, be noted.
Word for word from the decision Lancashire & Rossendale published for this meeting.Source: council.lancashire.gov.uk
The report is the first Corporate Performance Report for 2026/27 (for the period April - June 2026) and provides an overview of performance of the key performance indicators, agreed by Cabinet on 2 July 2026, and the priorities set out in Moving the Dial, monitoring the delivery of the ambitions of the Council Plan 2025-2030.
Recommendation
Cabinet is asked to:
(i) Review the performance of the Council in Quarter 1 of 2026/27 against the ambitions set out in the Council Plan 2025-2030 and, specifically the annual priorities set out in Moving the Dial. (ii) Note areas of strong performance and the key actions identified against indicators that are not achieving targets.
Background
1. This is the quarter 1 corporate performance report for 2026/27, setting out performance highlights and areas of improvement against the priorities set out in the Council Plan 2025-2030. Key performance indicators were agreed by Cabinet on 2 July 2026 to enable the monitoring of progress and delivery. The corporate performance dashboard provides more detail for each key performance indicators including trend over time and supporting commentary.
Overview of Performance
2. Quarter 1 performance demonstrates positive momentum across the Council's priorities, with the majority of indicators improving or maintaining performance. Strong results are being delivered for residents and businesses, including better access to services, increased independence for adults, continued economic growth, and stronger, more connected communities.
3. Whilst the overall direction of travel is positive, pressures remain in a small number of demand-led services, where rising demand, increasing complexity and workforce challenges continue to impact performance. Targeted improvement activity is in place to address these areas and accelerate recovery. A detailed summary of quarter 1 key performance indicators performance and progress against the Council's Moving the Dial priorities is provided in Appendix 'B'.
Key Performance Indicators
4. A total of 45 key performance indicators currently make up the corporate performance report. Where possible targets have been set for each key performance indicator.
5. Performance monitoring against the suite of key performance indicators with data and targets shows 36 out of 45 key performance indicators were given a Red, Amber or Green rating (RAG). Of these, 55.5% (20) were on track and rated green, 30.5% (11) were within 5% tolerance of target and rated amber, and 14% (5) were off track and rated red.
6. Performance for quarter 1 of 2026/27 can be broken down across the Council Plan ambitions is summarised in the following diagram. A full list of quarter 1 performance for all key performance indicators under each of the council ambitions is included at Appendix 'A'. Areas of Strong Performance
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.