Resolved
- That: (i) The report, now presented, be noted; (ii) The Assistant Chief Executive and the Project Team be thanked for the progress made to date.
Cabinet noted this item on Thursday 21 March 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
- That: (i) The report, now presented, be noted; (ii) The Assistant Chief Executive and the Project Team be thanked for the progress made to date.
This report provides an update on the progress made to date and forward plans for the Lancashire SFBB Project.
The Cabinet are asked to note the contents of this Report.
Background and Advice
1. Overview
The Lancashire SFFB Project is a County wide programme designed to ensure that 97% of the County can receive SFBB by 2015. At a base level, SFBB refers to broadband access in excess of 24Mbps delivered to business and residential users. Broadband speed is measured in megabits per second, commonly written as Mb or Mbps (as in 24Mb, or 24Mbps).
Current broadband provision in Lancashire delivers speeds ranging from 2 - 10Mbps dependent upon a user's location to the distributing infrastructure.
The Lancashire SFBB Project will provide a step change in this performance and will provide speeds ranging from 50 - 330Mbps. Access to SFBB requires an upgrade to the existing telecoms network via a combination of civil engineering works (laying new pipes, cables and street furniture) and an upgrade of existing street cabinets (typically green boxes located at the end of streets).
The Lancashire SFBB Project has started with mobilisation and initial planning stages now complete. Survey and detailed planning has also now commenced. The 'big build' begins in early April with the first live services expected later in the spring.
State aid approval has been received and external grant funding of £27.3m is in place. 2. Network rollout
The roll out of SFBB in Lancashire Project is in two parts.
A) Existing commercial plans from BT
A total of 36 exchanges are to be upgraded under the BT and Openreach commercial rollout, a £2.5bn UK-wide investment. This will provide coverage to around 400,000 premises in Lancashire by the end of 2013 of which around 200,000 premises currently have access to the services. A significant amount of activity within the commercial rollout is happening during this year.
Commercial exchange areas which are now live are: Accrington, Ashton-On-Ribble, Broughton, Chorley, Cleveleys, Clitheroe, Fleetwood, Fulwood, Hesketh Bank, Lancaster, Leyland, Longton, Morecambe, Ormskirk, Penwortham, Preston, Lancashire, Rossendale, Skelmersdale, Upholland.
Commercial exchange areas in plan for 2013 are: Aughton Green, Bacup, Bamber Bridge, Blackburn, Blackpool, Burnley, Burscough, Darwen, Garstang, Kirkham, Longridge, Lytham, Nelson, Poulton, Ribbleton Preston, South Shore, St Anne's.
B) Intervention via funding provided through LCC
Network Planning is now underway for the first phase of the intervention area. This involves assessing the network in each of the exchange areas, looking for routes for the fibre spine network (connecting the fibre broadband cabinets to the network), planning any exchange upgrade work required and surveying the locations for new fibre broadband cabinets.
Sub-contractor Carillion-Telent conduct the cabinet surveys on behalf of BT and they are fully briefed on the requirements of the Lancashire SFBB Project. The Lancashire SFBB Project Team have also been working with LCC Highways Team to smooth processes for work under the programme.
Equipment orders have been placed for the key serving exchanges that require upgrade. Overall, network planning can take up to six months, and is then followed by deployment / build activity which takes 3-6 months depending on the amount of work required in an area.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Lancashire Superfast Broadband Project UpdateReport | 252 KB | DownloadRead as text |
PDF |
View item 4. as DOCX 1 MBReport | 3 pages | Download |
Follow Cabinet at Lancashire & Rossendale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Sep 2026 | Minutes of the Meeting held on 2 July 2026That the minutes of the meeting held on 2 July 2026 be confirmed as a correct record and signed by the Chair. | Decided | Open |
| 3 Sep 2026 | Quarter 1 2026/27 Corporate Performance ReportThat, following consideration of the performance of the Council in Quarter 1 of 2026/27 against the ambitions set out... | Noted | Open |
| 3 Sep 2026 | 2026/27 Quarter 1 Financial Monitoring ReportThat i. The current forecast Revenue Budget overspend at Quarter 1 of £15.655m (1.18%), as detailed in Appendix 'A' o... | Noted | Open |
| 3 Sep 2026 | Ofsted Inspection of Lancashire Children's ServicesThat, following consideration of the outcome of the inspection, which confirmed that Lancashire's Children's Services... | Approved | Open |
| 3 Sep 2026 | SEND Capital ProjectThat i. Following consideration of the positive consultation responses, the prior approval of those projects through ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.