Chorley Borough: Application 09/13/0181 Erection of two extensions to existing school building at Buckshaw Trinity C of E Methodist Primary, Unity Place, Chorley

Decided Planning 3 papers

Development Control Committee decided this item on Wednesday 17 April 2013. Below is the council's own wording, with the papers it was decided on.

Item15

Resolved

Resolved : That planning permission be granted subject to the following conditions: Time Limits 1. The development shall commence not later than 3 years from the date of this permission. Reason: Imposed pursuant to Section 91 (1) (a) of the Town and Country Planning Act 1990 . Working Programme 2. The development shall be carried out in accordance with the following documents: a) The Planning Application and Design and Access Statement received by the Director of Transport and Environment 13th February 2013. b) Submitted plans and documents: Drawing No. 8064-P01 Location Plan 8064-P02 Existing Site Plan 8064-P03 Existing Ground Floor Plan 8064-P04 Existing First Floor Plan 8064-P05 Existing Elevations 1 of 3 8064-P06 Existing Elevations 2 of 3 8064-P07 Existing Elevations 3 of 3 8064-P09 Proposed Ground Floor Plan Rev A 8064-P10 Proposed First Floor Plan Rev A 8064-P11 Proposed Elevations Rev B 1 of 2 8064-P12 Proposed Elevations Rev B 2 of 2 8064-P14 Proposed Site Plan Rev A 8064-P15 Proposed Fencing Alterations 1 of 2 8064-P16 Proposed Fencing Alterations 2 of 2 Reason: To minimise the impact of the development on the amenities of the area and to conform with Policies 1, 14, and 17 of the Central Lancashire Core Strategy . Notes The applicant's attention is drawn to the requirements of the Equality Act 2010 and the British Standards Institution Code of Practice for Design of Buildings and their approaches to meet the needs of Disabled People (BS8300:2009). The design of the building will also need to comply with Part M of the Building Regulations 2010. In the case of educational buildings, the applicant's attention is drawn to the Special Educational Needs and Disability Act 2001 and the guidance prepared by the Department of Education and Skills Building Bulletin 91 (Access for the Disabled to School Buildings) and Building Bulletin 94 (Inclusive School Design).
Word for word from the decision Lancashire & Rossendale published for this meeting. Source: council.lancashire.gov.uk

Follow this further

Built from Lancashire & Rossendale's papers

What the report saysPro

Report to Development Control Committee

Executive summary

Application - Erection of two extensions to existing school building at Buckshaw Trinity C of E Methodist Primary, Unity Place, Chorley.

Recommendation – Summary

That planning permission be granted subject to conditions controlling commencement and working programme.

Applicant’s Proposal

Planning permission is sought for extensions to the east and west wings of the existing primary school. The original two storey primary school building was conceived as a one-form entry to accommodate 210 pupils. However, it was purposely designed to allow for extensions to be constructed at a later date. The proposed extensions would allow the school to accommodate a two-form entry capable of accommodating 420 pupils.

The proposed extension to the east wing of the building would be single storey covering an area of approximately 87m². It would incorporate a mono-pitched aluminium curved standing seam roof, sloping from a height of 3m at the eaves to approximately 4.8m to tie in with the adjoining building. The elevations would be finished in buff facing brick incorporating areas of white render, pre-patinated copper cladding and a section of aluminium curtain walling.

The proposed extension to the west wing of the building would be two storey and would cover an area of approximately 330m². The extension would incorporate a curving mono-pitched aluminium standing seam roof, sloping from a height of 7.5m at the eaves to approximately 9.2m. The elevations would be finished in buff facing brick incorporating areas of white render, dark grey cladding panels, pre-patinated copper cladding, brise soleil aluminium louvre blades and sections of aluminium curtain walling. All materials to be used in the extensions would match materials used in the existing school building.

Description and Location of Site

The school site was originally retained specifically for the construction of a primary school in the Chorley Borough Council masterplan for the Buckshaw Village redevelopment, and forms part of the 'community core' of the Village. The school site is broadly rectangular in plan and has prominent frontages to both Buckshaw Avenue to the south and Village Way to the east. A Community Centre and Health Centre are located to the north on the opposite side of Unity Way with residential properties located to the west in Sharrock Street. Additional residential properties are located to the east in Aycliffe Drive. The site is generally flat, with swales boarding the east and south, with a footpath running north-south on the western boundary.

Background

The existing primary school was designed specifically to allow for future extension to accommodate a two-form entry. The school has infrastructure in place to accommodate the proposed number of additional staff and pupils.

Planning History

Outline permission for mixed use development was granted by Chorley Borough Council in 1999 (ref 97/00509/OUT).

Planning permission for a modification of conditions for mixed use development was granted by Chorley Borough Council in 2002 (ref 02/00748/OUT).

Planning permission was granted in May 2009 for the erection of a primary school with associated playing fields, 2.4m high boundary fence and car park was granted by Chorley Borough Council in May 2009 subject to a legal agreement safeguarding land for future extensions to the school. (09/00180/FULMAJ).

Planning Policy

National Planning Policy Framework (NPPF)

Paragraphs 11 – 14, 56 – 64, and 72 are relevant in terms of the presumption in favour of sustainable development, the need for high standards of design and promoting healthy communities respectively.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Chorley Borough: Application 09/13/0181 Erection of two extensions to existing school building at Buckshaw Trinity C of E Methodist Primary, Unity Place, ChorleyReport 88 KB DownloadRead as text
PDF
PlanReport 558 KB Download
PDF
View item 15. as DOC 157 KBReport 5 pages Download

At this meeting

Whole meeting
3Minutes of the last meeting held on 6 March 2013Noted 4Lancaster City: Application No. 01/12/1027 Change of use of land for processing of inert waste to produce a secondary aggregate including erection of new building and continuation of existing use as agricultural and civil engineering store and depot. Nans Nook Farm, Bay Horse Road, Ellel.Refused 5Wyre Borough : Application ref 02/09/0787 Construction of an anaerobic digestion facility processing commercial organic waste streams to provide renewable energy through CHP power plant. Unit CL5, West Road, Hillhouse International Business Park, Thornton CleveleysAgreed 6West Lancashire Borough: Application No. 08/13/0151 Variation of Condition 10 of planning permission 08/09/0494 to allow the exportation of 25,000 tonnes of sandstone per year for general sale Dalton Quarry, Lees Lane, Dalton.Agreed 7West Lancashire Borough: Application No. 08/13/0140Approved 8Chorley Borough: Application 09/13/0133Approved 9Hyndburn Borough: Application 11/13/0050 Change of use to vehicle depollution/recycling operation including erection of industrial building and provision of one office cabin and three storage containers. Yard (formerly UK Safe Storage), Heys Lane, Great Harwood.Approved 10Hyndburn Borough: Application ref 11/12/0482Decided 11Lancaster City: Application 01/13/0020 Single storey extension to the existing building and external works consisting of play areas, landscaping, and a new pedestrian access at Great Wood Primary, Beaufort Road, Morecambe.On the agenda 12Lancaster City: Application 01/13/0171 Variation of condition 6 of permission 01/10/0565 to extend the opening hours of the swimming pool to 0800 to 1900 Monday to Friday, 9.30 to 16.30 on Saturdays and Sundays with no opening at anytime on public holidays, The Loyne School, Sefton Drive, Lancaster.Decided 13Fylde Borough: Application 05/13/0122On the agenda 14Preston City: Application 06/13/0134 Construction of a patio area and cycle shelter and erection of a flag pole up to 4.8m high, Harris Primary School, Wychnor, Fulwood, Preston.Decided
15Chorley Borough: Application 09/13/0181 Erection of two extensions to existing school building at Buckshaw Trinity C of E Methodist Primary, Unity Place, ChorleyThis decision
16Planning Applications determined by the Executive Director for Environment in accordance with the County Council's Scheme of Delegation.Noted 17Lancaster City: Application Ref DCO Heysham 1 Submission of details to comply with the requirements of the Development Consent Order relating to the completion of the Heysham to M6 Link, Lancaster.Approved 18Lancaster City: Application 01/13/0179 Construction of a temporary compound including siting of eleven demountable units in association with the Heysham M6 Link, Halton Army Training Camp. Halton Road, LancasterDecided

Who was there

14 of 15 attended
CG
CC G AdamCommittee Member, apologies
CT
CC T AldridgeCommittee Member, present
CM
CC Mrs R BlowCommittee Member, present
CW
CC W CropperDeputy Chair, present
CM
CC M DevaneyChair, present
CK
CC K EllardCommittee Member, present
CP
CC P HayhurstCommittee Member, present
CH
CC H HenshawCommittee Member, present
CC
CC C HoltomCommittee Member, present
CJ
CC J JacksonCommittee Member, present
CP
CC P MalpasCommittee Member, present
CD
CC D O'TooleCommittee Member, present

All 15 on the meeting page

On this subject at Lancashire & Rossendale

Search all
  1. Chorley Borough: Application 09/13/0181 Erection of two extensions to existing school building at Buckshaw Trinity C of E Methodist Primary, Unity Place, ChorleyThis decision
  2. Chorley Borough: LCC/2026/0004. Land to the North of Myles Standish Way, Heath Charnock, Chorley, PR7 3FTDecided
  3. Chorley Borough: application number: LCC/2023/0019 Retention of the Waste Transfer Station, Leachate Plant, Gas Plant and related infrastructure at Clayton Hall Landfill Site, Dawson Lane, Whittle-Le-WoodsDecided
  4. Chorley Borough: application no LCC/2022/0002 Variation of condition 2 of planning permission LCC/2019/0054 to allow the golf course re-contouring operations and restoration operations to continue until 23 March 2023. The Laurels at Charnock, Preston Road, Charnock Richard.Decided
  5. Chorley Borough: Application number LCC/2020/0052 Erection of recycling wash plant to process selected wastes at Common Bank Works, Common Bank Lane, ChorleyDecided
  6. Highways Act 1980 - Section 119 Wildlife and Countryside Act 1981 - Section 53A Proposed Diversion of Part of Footpath Heapey 27 at Black Lion Farm, Wheelton, Chorley BoroughDecided

More from Lancashire & Rossendale Development Control Committee

All decisions
MeetingDecisionOutcome
15 Jul 2026 Minutes of the last meeting held on 10 June 2026That the minutes of the meeting held on 10 June 2026 be confirmed and signed by the Chair. Decided Open
15 Jul 2026 West Lancashire Borough: application number LCC/2025/0022. Ravenhead Quarry, Chequer Lane, Up Holland, WN8 0DDThat planning permission be granted , subject to the conditions detailed in Appendix 'A'. Decided Open
15 Jul 2026 West Lancashire Borough: application number LCC/2025/0023. Ravenhead Quarry, Chequer Lane, Up Holland, WN8 0DDThat planning permission be granted , subject to: (i) The conditions detailed within Appendix 'A'. (ii) An amendment ... Decided Open
15 Jul 2026 Decisions taken on development control matters by the Director of Environment and Planning in accordance with the County Council's Scheme of DelegationThat the report be noted. Noted Open
15 Jul 2026 Date of Next MeetingThat the next meeting of the Committee be held on Wednesday, 2 September 2026 at 10.00am in Committee Room B – The Di... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies