That: (i) The progress made to ensure the City Deal can be implemented from 2014/15, as set out in the report, no presented, be noted; (ii) The draft City Deal Infrastructure Delivery Plan which will be considered by the City Deal Executive in April 2014, as set out in the report, now presented, be endorsed; (iii) The principles of the Stewardship Board Agreement which will be considered by the City Deal Stewardship Board in May 2014, as set out in the report, now presented, be approved; (iv) The principles of the Memorandum of Understanding (MoU) which deals with the HCA asset uplift and which will be signed by the County Council, Department for Communities and Local Government (DCLG) and HCA, as set out in the report, now presented, be endorsed and authority be delegated to the County Treasurer and the County Secretary and Solicitor, in consultation with the Leader of the County Council, to approve and execute the final MoU and subsequent loan agreements; (v) The operating principles for the establishment of the City Deal Infrastructure Delivery Fund and Heads of Terms regarding fund flow between the 3 Councils, as set out in the report, now presented, be approved and authority be delegated to the County Secretary and Solicitor and the County Treasurer, in consultation with the Leader of the County Council as Portfolio Holder for Economic Development, to finalise and execute the Heads of Terms and thereafter the formal Legal Agreement; (vi) The County Treasurer be authorised to incorporate expenditure commitments and funding arising from City Deal projects approved through the City Deal Governance Structures within the County Council's Capital Investment Programme on an ongoing basis; (vii) That all those involved in bringing the City Deal to fruition be thanked.
Word for word from the decision Lancashire & Rossendale published for this meeting.Source: council.lancashire.gov.uk
The Preston, South Ribble and Lancashire City Deal (City Deal) was signed by the Lancashire Enterprise Partnership, Preston City Council, South Ribble Borough Council, Lancashire County Council and Central Government in September 2013.
The City Deal agreed with Government, builds on the strong economic performance of the area over the last ten years and will help to ensure that the City Deal area continues to grow by addressing strategic transport infrastructure and development challenges to delivering new jobs and housing across the City Deal area.
The signed City Deal document sets out a number of commitments for each of the City Deal partners, including the LEP, 3 local authorities and Central Government departments and agencies, including the Homes and Communities Agency (HCA). It incorporates these in a Delivery and Implementation Plan, which sets out the actions that partners need to undertake to ensure that the City Deal is implemented successfully from 2014/15. Since September 2013 a significant amount of work has been undertaken to complete those actions in readiness for the City Deal to begin in 2014/15.
The City Deal Executive and City Deal Stewardship Board have both been established and appropriate technical and operational delivery mechanisms have been put in place.
Lancashire County Council is the accountable body for the City Deal and is now in a position to establish the City Deal Infrastructure Delivery Fund. The financial principles relating to the flow of funds into the fund have been agreed between the partners.
An Infrastructure Delivery Plan for 2014/15 has been drafted by the partners and will be presented for approval to the City Deal Executive in April 2014. A Stewardship Board Agreement and a Business and Disposal Plan for 2014/15 has been drafted by the HCA and will be presented to the City Deal Stewardship Board in May 2014 for approval.
This is deemed to be a Key Decision and Standing Order 27 has been complied with.
Recommendation
Cabinet is recommended to:
(i) Note the progress made to ensure the City Deal can be implemented from 2014/15; (ii) Endorse the draft City Deal Infrastructure Delivery Plan which will be considered by the City Deal Executive in April 2014; (iii) Approve the principles of the Stewardship Board Agreement which will be considered by the City Deal Stewardship Board in May 2014; (iv) Endorse the principles of the Memorandum of Understanding (MoU) which deals with the HCA asset uplift and which will be signed by the County Council, Department for Communities and Local Government (DCLG) and HCA and delegate authority to the County Treasurer and the County Secretary and Solicitor, in consultation with the Leader of the County Council, to approve and execute the final MoU and subsequent loan agreements. (v) Approve the operating principles for the establishment of the City Deal Infrastructure Delivery Fund and Heads of Terms regarding fund flow between the 3 Councils and delegate authority to the County Secretary and Solicitor and the County Treasurer, in consultation with the Leader of the County Council as Portfolio Holder for Economic Development, to finalise and execute the Heads of Terms and thereafter the formal Legal Agreement; (vi) Authorise the County Treasurer to incorporate expenditure commitments and funding arising from City Deal projects approved through the City Deal Governance Structures within the County Council's Capital Investment Programme on an ongoing basis.
Background and Advice
1. Introduction
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.