CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Lancashire County Council / Rossendale Borough Council
Lancashire Enterprise Partnership, Tuesday 10 February 2015 at 6.00pm

Blackburn to Manchester Rail Corridor Improvement Scheme

Approved Committee 6 papers

Lancashire Enterprise Partnership approved this item on Tuesday 10 February 2015. Below is the council's own wording, with the papers it was decided on.

Item11

Resolved

That the Board: (i) Approved the granting of Conditional Approval for the ; and (ii) Requested that officers advise the scheme promoter that the six conditions set out in the Jacobs report need to be addressed in the Full Business Case submission.
Word for word from the decision Lancashire & Rossendale published for this meeting. Source: council.lancashire.gov.uk

Follow this further

Built from Lancashire & Rossendale's papers

What the report saysPro

Report to Lancashire Enterprise Partnership

Executive summary

The Blackburn to Bolton Rail Corridor Improvement Scheme is included in Lancashire's transport investment programme as a scheme due to commence works in 2015/16. In accordance with the Lancashire Enterprise Partnership's Assurance Framework, the scheme is therefore subject to a two stage approvals process, the first stage of which is a Conditional Approval decision by the Board.

Independent scrutiny of the Outline Business Case has been undertaken by Jacobs UK Limited on behalf of the Transport for Lancashire Committee. It is the consultant's view that the Blackburn to Manchester Rail Corridor Improvement Scheme be granted Conditional Approval to enable it to progress to Full Business Case submission, subject to a number of conditions that the scheme promoter will need to address as part of that submission.

Recommendation

The Board is asked to:

(i) Approve the granting of Conditional Approval for the Blackburn to Manchester Rail Corridor Improvement Scheme; and

(ii) Advise the scheme promoter that the six conditions set out in the Jacobs report (attached as an appendix) to the Transport for Lancashire Committee need to be addressed in the Full Business Case submission.

Background

1.1The Blackburn to Bolton Rail Corridor Improvement Scheme is included in Lancashire's transport investment programme as a scheme due to commence works in 2015/16. The scheme's funding profile includes a maximum £12.4m contribution in 2015/16 from the Local Growth Fund through the Lancashire Growth Deal. In accordance with the Lancashire Enterprise Partnership's Assurance Framework, the scheme is therefore subject to a two stage approvals process, the first stage of which is a Conditional Approval decision by the Board.

1.2Conditional Approval indicates the Lancashire Enterprise Partnership's acceptance of an Outline Business Case demonstrating high value for money, ie a benefit to cost (BCR) ratio of greater than 2. Conditional Approval is granted on the basis that there will be no material changes to the scheme's scope, cost, design, expected benefits and value for money. The granting of Conditional Approval may be subject to a small and limited number of conditions.

1.3Lancashire County Council commissioned its framework consultants Jacobs UK Limited on behalf of the Transport for Lancashire Committee to undertake an independent, comprehensive review of the Outline Business Case submitted by Blackburn with Darwen Borough Council, and to recommend whether or not the scheme should be granted Conditional Approval. Jacobs presented their findings to Transport for Lancashire at its meeting held on 3rd February 2015; the consultant's report is attached as Appendix 'A'.

1.4It is the consultant's view that the Blackburn to Manchester Rail Corridor Improvement Scheme be granted Conditional Approval to enable it to progress to Full Business Case submission, subject to a number of conditions that the scheme promoter will need to address as part of that submission.

1.5Having considered Jacobs' report, the Transport for Lancashire Committee agreed to recommend to the Lancashire Enterprise Partnership that it grant the Blackburn to Bolton Rail Corridor Improvement Scheme Conditional Approval, with Full Approval subject to the following six conditions as set out in the Jacobs report being addressed in the Full Business Case submission:

1. Confirmation is received (when the Invitation to Tender for the new Northern Franchise is publically available) that the Manchester to Blackburn service is to be included as part of the baseline specification for the next Northern Franchise.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Blackburn to Manchester Rail Corridor Improvement SchemeReport 68 KB DownloadRead as text
PDF
Blackburn to Manchester Rail Report: Annex 1Appendix 103 KB Download
PDF
Blackburn to Manchester Rail Report: Annex 1: Appendix AAppendix 186 KB Download
PDF
Blackburn to Manchester Rail Report: Annex 1: Appendix BAppendix 267 KB Download
PDF
View as DOC (11./2) 209 KBAppendix 4 pages Download
PDF
View item 11. as DOCX 41 KBReport 2 pages Download

At this meeting

Whole meeting

Who was there

18 of 26 attended
EB
Mr E Booth (Chair)Chair, present
MB
Cllr M BatesonDirector, present
SB
Cllr S BlackburnDirector, present
MB
Mr M BlackburnDirector, apologies
JC
Mr J CarterDirector, present
GC
Mr G CowleyDirector, present
MD
Mr M DammsDirector, present
RE
Mr R EvansDirector, present
SH
Cllr S HirstDirector, apologies
MM
Dr M McVicarDirector, present
DM
Mr D MendorosDirector, apologies
CJ
CC J MeinDirector, present

All 26 on the meeting page

On this subject at Lancashire & Rossendale

Search all
  1. Blackburn to Manchester Rail Corridor Improvement SchemeThis decision
  2. Blackburn to Manchester Rail Corridor Improvement Scheme Full Approval ApplicationApproved
  3. Blackburn to Manchester Rail Corridor Improvement Scheme - Conditional Approval ApplicationApproved

More from Lancashire & Rossendale Lancashire Enterprise Partnership

All decisions
MeetingDecisionOutcome
20 Sep 2023 Minutes of the meeting held on 21 June 2023Following this amendment, the minutes were approved as an accurate recor d. Approved Open
20 Sep 2023 23/24 mid-year Business Plan Delivery UpdateResolved : The Lancashire Enterprise Partnership Board noted the report as presented. Noted Open
20 Sep 2023 LEP Governance and Committees Report - September 2023The Lancashire Enterprise Partnership Board noted the report as set out. Noted Open
20 Sep 2023 Establishment of a Business Board for Lancashire - UpdateResolved : The Lancashire Enterprise Partnership Board noted the update as provided and gave the above comments for c... Noted Open
20 Sep 2023 Energy and Low Carbon Implementation PlanResolved : The Lancashire Enterprise Partnership Board noted the update. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies