LEP - Transport for Lancashire Committee, Monday 13 April 2015 at 2.00pm

Blackburn to Manchester Rail Corridor Improvement Scheme Full Approval Application

Approved Committee 2 papers

LEP - Transport for Lancashire Committee approved this item on Monday 13 April 2015. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

The Committee endorsed Jacobs' recommendation that the Blackburn to Manchester Rail Corridor Improvement Scheme should be granted Full Approval status, thus enabling the scheme to draw down Growth Deal funds and proceed to implementation.
Word for word from the decision Lancashire & Rossendale published for this meeting. Source: council.lancashire.gov.uk

Follow this further

Built from Lancashire & Rossendale's papers

What the report saysPro

Report to LEP - Transport for Lancashire Committee

Date 13th April 2015

To Transport for Lancashire (TfL)

From Jacobs

Subject Blackburn to Manchester Rail Corridor Improvement Scheme

Introduction

The purpose of the review is to inform TfL’s recommendation on whether the Blackburn to Manchester Rail Corridor Improvement Scheme should be granted Full Approval status at the LEP Board meeting on the 21st April 2015. This would subsequently enable the scheme to draw down Growth Deal funds and proceed to implementation.

Scheme Description

The Blackburn to Manchester Rail Corridor Improvements Scheme will deliver a half- hourly service between Blackburn and Manchester throughout the day through the addition of 7 journeys between these stations each day Monday – Saturday. This increased service level will cater for the current demand and improve the economic relationship between East Lancashire and Greater Manchester.

In order to deliver a robust half hourly service throughout the day an extension to the passing loop (double track) at Darwen is required. The project, as identified by Network Rail as the preferred solution through the GRIP process, is to extend the double track section known as the Darwen loop on the Bolton to Blackburn Line, with associated works at structures along that part of the route. In addition, the scheme includes enhancement works at selected stations on the line (including stations north of Blackburn).

Scheme Milestones

Table 1 summarises the key milestones in the approval process for the scheme.

Date Task December 2014 BwDBC completed the Outline Business Case for the scheme. February 2015 Jacobs undertook a comprehensive review of the scheme’s Outline Business Case. February 2015 Scheme granted Conditional Approval status at the LEP Board meeting on the 10th February 2015. February / March 2015 BwDBC updated the Outline Business Case to be a Full Business Case. March 2015 Jacobs reviewed the Full Business Case for the scheme. April 2015 Scheme Seeking Full Approval at the LEP Board meeting on the 21st April 2015. Table 1: Key Milestones

Jacobs U.K. Limited Jacobs_MemoA4.doc Methodology

The scheme’s Outline Business Case (December 2014) was previously reviewed and evaluated against the Department for Transport’s (DfT) guidance on The Transport Business Cases (January 2013). The business case was also assessed to ensure consistency with the Lancashire Enterprise Partnership’s Accountability Framework.

Jacobs have subsequently reviewed the scheme’s Full Business Case (March 2015) to ensure that each of the conditions that were placed on the scheme, when it was granted Conditional Approval status, have been met.

The review has also ensured that each of the recommendations that were previously suggested have been incorporated into the Full Business Case update.

As part of the review process, Jacobs have actively engaged with the scheme promoter (BwDBC) in order to agree on viable and proportionate solutions to any key issues.

Conclusions

The Blackburn to Manchester Rail Corridor Improvement Scheme should be granted Full Approval status and subsequently enable the scheme to proceed to implementation.

The table below summarises how each of the six conditions previously placed on the scheme have been resolved.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Blackburn to Manchester Rail Corridor Improvement Scheme Full Approval ApplicationReport 193 KB DownloadRead as text
PDF
View item 5. as DOC 324 KBReport 3 pages Download

At this meeting

Whole meeting

Who was there

15 of 25 attended
CC
County Councillor Jennifer Mein (Chair)Chair, present
MB
Councillor Maureen BatesonCommittee Member, present
JJ
Councillor John JonesCommittee Member, present
GC
Graham CowleyCommittee Member, present
BP
Bruce ParkerObserver, apologies
MS
Mike SinnottObserver, present
RP
Richard PerryObserver, present
TC
Tom CarberyObserver, apologies
MK
Mike KirbyOfficer, present
AC
Alan CavillOfficer, present
DC
Dave ColbertOfficer, present
MK
Martin KellyOfficer, apologies

All 25 on the meeting page

On this subject at Lancashire & Rossendale

Search all
  1. Blackburn to Manchester Rail Corridor Improvement Scheme Full Approval ApplicationThis decision
  2. Blackburn to Manchester Rail Corridor Improvement SchemeApproved
  3. Blackburn to Manchester Rail Corridor Improvement Scheme - Conditional Approval ApplicationApproved

More from Lancashire & Rossendale LEP - Transport for Lancashire Committee

All decisions
MeetingDecisionOutcome
30 Jan 2020 South East Blackburn Funding ApplicationThat the Lancashire Enterprise Partnership Board be recommended to grant the scheme a maximum of £9.05m Growth Deal f... Decided Open
5 Jun 2019 Matters ArisingThat the update be noted . Noted Open
5 Jun 2019 Preston Western Distributor Funding ApplicationThat the Lancashire Enterprise Partnership be recommended to grant the scheme a maximum £58m Growth Deal funding, sub... Approved Open
5 Jun 2019 Preston Rail Station HS2 Hub - Assessment of Wider Economic benefitsThat the contents of the report be noted. Noted Open
5 Jun 2019 Exclusion of Press and Public- That the press and members of the public be excluded from the meeting during consideration of the following item of... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies