Item8
Resolved
Following a discussion, the Board agreed to: (i) Note the progress made by local partners in restructuring the funding profile of the LEP's Priority 1 scheme, Northlight , and agreed to include the scheme as part of the LEP's Growth Deal 1 programme; (ii) Redirect £1.7M in additional Growth Deal funding which was previously assigned to the Fleetwood Fish Park in support of Northlight ; (iii) Provide an additional £2M in Growth Deal funding by 1 April 2016, through the active management and value engineering of the LEP's overarching £251.2M Growth Deal funded delivery programme; and (iv) With the above subject to a Growth Deal funding agreement with the Northlight scheme sponsor, which, inter alia, confirms all other identified funding contributions have been successfully secured.
Word for word from the decision Lancashire & Rossendale published for this meeting.
Source: council.lancashire.gov.uk