That the report is noted and a further more detailed report, including details of the indicative commitments made by individual projects, be presented to the next meeting. 2. That a representative from Balfour Beatty be invited to attend the next meeting to give a presentation about social value in respect to a growth deal project. Councillor Rankin left the meeting at this point
Word for word from the decision Lancashire & Rossendale published for this meeting.Source: council.lancashire.gov.uk
The purpose of this report is to provide a summary of progress made since the last meeting of the Growth Deal Management Board
Recommendation
The Board are invited to receive, consider and comment on the update.
Background and Advice
The Growth Deal Management Board are committed to maximising the Social Value benefits of the individual projects that form part of the Growth Deal Programme, and the Social Value benefits across the Growth Deal Programme.
In order to progress towards realising this aspiration the Growth Deal Management Board, on 21 October 2015, agreed to produce a “Toolkit for Wider Economic and Social Benefits for Growth Deal Projects in Lancashire. In order to do this the Board decided to establish a small working group to include: Graham Cowley, [name removed], Richard Hothersall, Alison Moore and Martine Winder.
Update from the last Growth Deal Management Board Meeting (19 January 2016)
At the last meeting of the Growth Deal Management Board it was reported that the GDMB Social Value Working Group had met and were in the process of developing a template for capturing and monitoring social value outcomes across growth deal projects. [name removed] confirmed that the template would initially be trialled with two projects and that the findings will be reported to the next Committee. Progress since last meeting
As part of the scheduled monitoring meeting with the Blackburn-Bolton Rail Corridor project a conversation took place with the project sponsor about Social Value. The discussion was extremely positive, and the project sponsor was keen to complete appropriate sections of the template in order to capture the relevant aspects of social value.
Given the very positive nature of this conversation an opportunity has now been taken to have discussions with all project sponsors during monitoring meetings with them. To date the conversations have been, without fail, positive and all projects have agreed to seek to populate the parts of the template that are pertinent to their project with a view to getting some indicative commitment information by the end of February 2016 (note that this report represents the position on 24 February 2016).
Next Steps
A further, more detailed, report which will include details of the indicative commitments made by individual projects, will be presented to the April meeting of this Board.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow LEP - Growth Deal Management Board at Lancashire & Rossendale and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.