CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Lancashire County Council / Rossendale Borough Council
LEP - Growth Deal Management Board, Wednesday 13 April 2016 at 1.30pm

Social Value

Decided Committee 2 papers

LEP - Growth Deal Management Board decided this item on Wednesday 13 April 2016. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

That Officers continue to work with [name removed] and [name removed] to develop a process for achieving social value outcomes in relation to Growth Deal projects in Lancashire. 2. That [name removed] be requested to provide case studies regarding Balfour Beatty projects which have resulted in social value outcomes which can be used as part of the Toolkit for Wider Economic and Social Benefits for Growth Deal Projects in Lancashire. [name removed] and [name removed] left the meeting at this point.
Word for word from the decision Lancashire & Rossendale published for this meeting. Source: council.lancashire.gov.uk

Follow this further

Built from Lancashire & Rossendale's papers

What the report saysPro

Report to LEP - Growth Deal Management Board

Executive summary

The purpose of this report is to provide a summary of progress made since the last meeting of the Growth Deal Management Board

Recommendation

The Board are invited to receive, consider and comment on the update.

Background and Advice

The Growth Deal Management Board are committed to maximising the Social Value benefits of the individual projects that form part of the Growth Deal Programme, and the Social Value benefits across the Growth Deal Programme.

In order to progress towards realising this aspiration the Growth Deal Management Board, on 21 October 2015, agreed to produce a “Toolkit for Wider Economic and Social Benefits for Growth Deal Projects in Lancashire. The Board also decided to establish a small working group to include: Graham Cowley, [name removed], Richard Hothersall, Alison Moore and Martine Winder.

Activity since 9 March 2016

Since the last meeting of the Growth Deal Management Board blank copies of the social value template have continued to be provided to projects for consideration and completion.

A number of projects have submitted responses that can easily be included on the social value metrics template. However, the very diverse and often qualitative information that has been submitted means that some information cannot be captured in this way. Training 2000 have been unable to identify any social value outcomes that can be directly attributed to their projects. This is not to say that there has been a lack of co-operation. Instead it reflects that owing to the diverse nature of the suite of projects that form the Growth Deal programme some just don't naturally lend themselves to achieving social value.

Discussions, during project monitoring, will ensure that any social value outcomes that do emerge will be captured and attributed.

Proposed Way Forward

It is proposed that progress/realisation of social value outcomes is considered during project monitoring rather than being linked to the reporting/claims process.

This allows for the distinction between what projects are legally obliged to undertake (as per their individual Growth Fund Agreement/Memorandum of Understanding). It also allows for the rich narrative that is likely to emerge in terms of social value outcomes to be fully captured and celebrated.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Social ValueReport 73 KB DownloadRead as text
PDF
View item 6. as DOCX 35 KBReport 1 pages Download

At this meeting

Whole meeting

Who was there

12 of 19 attended
GC
Mr G CowleyChairman, present
BB
Mr B BaileyCommittee Member, apologies
AB
Andrew BondCommittee Member, present
AC
Mr A CavillCommittee Member, present
L
Ms Lawty-JonesCommittee Member, present
SP
Mrs S ProcterCommittee Member, present
GS
Mr G SmithCommittee Member, present
PR
Professor R WalshCommittee Member, present
JW
Ms J WhittakerCommittee Member, present
JA
Joanne AinsworthOfficer, present
AP
Anne-Marie ParkinsonOfficer, present
BJ
Beckie JoyceOfficer, expected

All 19 on the meeting page

On this subject at Lancashire & Rossendale

Search all
  1. Social ValueThis decision
  2. Social Value Policy and FrameworkApproved
  3. Social Value Update.Noted
  4. Social Value Policy and FrameworkNoted
  5. Growth Deal Skills Capital - Round 1 Update, Round 2 Overview and Social Value UpdateNoted
  6. Public Services (Social Value) Act 2012Decided

More from Lancashire & Rossendale LEP - Growth Deal Management Board

All decisions
MeetingDecisionOutcome
4 Mar 2020 Minutes of the meeting held on 13 November 2019that the minutes of the meeting held on 13 November 2019 be approved as an accurate record and signed by the Chair. Approved Open
4 Mar 2020 Reporting to Lancashire Enterprise Partnership Boardthat at the next meeting of the Lancashire Enterprise Partnership Board it should be reported that: 1. Officers are c... Decided Open
4 Mar 2020 Growth Deal Programme and Project Update ReportThat the Grant Funding ... view the full minutes text for item 9. Decided Open
4 Mar 2020 Growth Deal Finance Reportthe Growth Deal Management Board agreed: 1. To note the spend and forecast as presented 2. That the current project f... Agreed Open
5 Jun 2019 Declaration of InterestsIt was agreed that conflicted members could remain in the room during discussion but, should decisions be made about ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies