Resolved
The Board considered the Outline Business Case and agreed to grant the Blackpool Tramway Extension scheme conditional approval.
Lancashire Enterprise Partnership agreed this item on Tuesday 5 April 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
The Board considered the Outline Business Case and agreed to grant the Blackpool Tramway Extension scheme conditional approval.
Appendix A
Page 1 of 3
Date 24th March 2016
To Transport for Lancashire (TfL)
From Jacobs
Subject Blackpool and Fleetwood Tramway Extension to Blackpool North Station
Introduction
Jacobs have undertaken a comprehensive review of the Outline Business Case (March 2016) produced by Blackpool Council in support of the Blackpool and Fleetwood Tramway Extension to Blackpool North Station scheme.
The review findings should be used to inform a recommendation on whether the scheme should be granted Conditional Approval status at the LEP Board meeting on the 5th April 2016.
Scheme Description
The Blackpool North Tramway Extension will extend the current tramway from the North Pier tram stop on the Promenade to Blackpool North Station, approximately 600 metres inland on Talbot Road, as illustrated in Figure 1.
The scheme is promoted by Blackpool Council and Blackpool Transport Services (BTS).
Figure 1: Scheme Location
Jacobs U.K. Limited Jacobs_MemoA4.doc Memorandum (Continued)
Page 2 of 3
Methodology
The Outline Business Case has been reviewed and assessed against the Department for Transport’s (DfT) guidance on The Transport Business Cases (January 2013). This approach shows whether schemes:
• are supported by a robust case for change that fits with wider public policy objectives – the ‘strategic case’; • demonstrate value for money – the ‘economic case’; • are commercially viable – the ‘commercial case’; • are financially affordable – the ‘financial case’; and • are achievable – the ‘management case’.
A Red-Amber-Green (RAG) assessment has been undertaken on each of the five cases in order to:
a. Highlight any keys risks associated with the successful delivery of the project in accordance with the Lancashire Enterprise Partnership’s Accountability Framework. b. Identify areas of the Outline Business Case where there is insufficient evidence to demonstrate that the scheme has followed DfT best practice for the development of a major scheme. c. Ensure the scheme aligns positively with the LEP’s Strategic Economic Plan.
The completed RAG assessment has been appended to this document as Appendix A.
As part of the review process, Jacobs have actively engaged with the scheme promoter (Blackpool Council) and their specialist consultants (SDG) in order to seek clarification on any key issues associated with the Outline Business Case. The RAG assessment summarises the iterative process which has been adopted to update the Outline Business Case to ensure that it is compliant with the LEP’s Accountability Framework and DfT best practice guidance.
Key Points
Scheme Cost - The total investment cost for the scheme is £24.0m. The operator revenue generated over the scheme appraisal period is nearly 50% more than the operating costs, indicating a positive overall operating position.
Funding - A letter from Blackpool Council’s Section 151 Officer has been appended to this document as Appendix B. The letter confirms Blackpool Council’s support for the scheme and their commitment to provide a local contribution to fund the balance between the allocated Growth Deal funding (£16.4m) and the scheme cost (£24.0m).
Scheme BCR - The Economic Case for the scheme is strong, with the analysis presented showing that the scheme has a Benefit to Cost Ratio (BCR) of 2.86, which represents ‘High’ Value for Money.
GVA Benefits - The scheme is forecast to generate 6,000-11,000 induced trips annually which would generate £400,000 - £700,000 of GVA benefits per annum to Blackpool’s local economy.
Programme - It is intended that the tramway extension will be opened by the spring of 2019, with construction due to begin at the end of 2017. Jacobs U.K. Limited Jacobs_MemoA4.doc Memorandum (Continued)
Page 3 of 3
Conclusions
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Blackpool Tramway: Jacobs ReportReport | 570 KB | DownloadRead as text |
PDF |
Growth Deal: Transport Scheme: Blackpool Tramway: Conditional Approval ReportReport | 72 KB | Download |
PDF |
View item 9. as DOCX 35 KBReport | 2 pages | Download |
Follow Lancashire Enterprise Partnership at Lancashire & Rossendale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Sep 2023 | Minutes of the meeting held on 21 June 2023Following this amendment, the minutes were approved as an accurate recor d. | Approved | Open |
| 20 Sep 2023 | 23/24 mid-year Business Plan Delivery UpdateResolved : The Lancashire Enterprise Partnership Board noted the report as presented. | Noted | Open |
| 20 Sep 2023 | LEP Governance and Committees Report - September 2023The Lancashire Enterprise Partnership Board noted the report as set out. | Noted | Open |
| 20 Sep 2023 | Establishment of a Business Board for Lancashire - UpdateResolved : The Lancashire Enterprise Partnership Board noted the update as provided and gave the above comments for c... | Noted | Open |
| 20 Sep 2023 | Energy and Low Carbon Implementation PlanResolved : The Lancashire Enterprise Partnership Board noted the update. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.