Resolved
- That the recommendations set out in the report to the Deputy Leader of the County Council be noted and that no additional comments or suggested alternative recommendations be made.
Executive Scrutiny Committee noted this item on Tuesday 7 March 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
- That the recommendations set out in the report to the Deputy Leader of the County Council be noted and that no additional comments or suggested alternative recommendations be made.
This report:
outlines several elements of works classified as in need of immediate attention due to a high risk of failure, or as a regulatory requirement of the redevelopment works currently underway to the County Hall Old Building as part of the ongoing redevelopment of the County Hall Complex; and how these works will be funded.
This is deemed to be a Key Decision and the provisions of Standing Order 25 have been complied with.
The Deputy Leader of the Council is recommended to approve:
(i) The investment of £1.586m in order to fund several elements of works classified as in need of immediate attention due to a high risk of failure, or as a regulatory requirement of the redevelopment works currently underway to the County Hall Old Building as part of the ongoing redevelopment of the County Hall Complex; and: (ii) The use of three funding sources as set out in the table in section 2 of the report to fund this investment.
1. Background and Advice
Over the past four years, two key refurbishment/remodelling projects of work have been undertaken across the county hall complex of buildings as part of the Preston property review. The projects enable the closure of 9 properties. -2-
The first phase of construction and refurbishment work was undertaken in Christ Church Precinct and Lancashire Point. The level of investment in County Hall Old Building (CHOB) was not as significant at that time, as the future utilisation of the building was expected to reduce as the organisation reduced in staffing numbers.
Phase one of the CHOB project was partially completed early in 2015, however it was temporarily paused in order to review the outstanding works in the context of the corporate property strategy and the wider organisational transformation. Part of the process in developing the property strategy proposals involved an assessment to identify the suitability and condition of the retained portfolio.
The remainder of the refurbishment works in CHOB was incorporated into a budget option proposal (BOP050 – closure of Woodlands, Alston Hall and Leyland Learning Centre), which sought to secure additional capital investment for CHOB. The increased investment proposal would enable greater utilisation of the space and enable the closure of these three facilities. The budget option proposal was subsequently approved, which committed £3.6m of capital to deliver the scheme.
It is important to note that at the time of preparing the budget option proposal, there was limited information known on any other essential or urgent repair and maintenance works required at CHOB.
As a consequence of the commitment to invest further capital into CHOB, the Design and Construction (D&C) service initiated a condition survey to ensure the sustainability of the building in line with the level of capital investment and future occupancy plans. The D&C service were concerned that the condition survey for CHOB was out of date and did not reflect up to date information to inform the current condition or future planned maintenance items that may be required.
As part of the feasibility stage, building control and the County Council's fire consultant highlighted the requirement for an additional emergency stairwell due to the change of use/occupancy figures to ensure compliance. The estimated budget for the stairwell was £0.155m and it was discussed by officers that this could be met from the revenue repair and maintenance budget and would not form part of the financial business case for BOP50. However, this allocation was not made from the revenue, repair and maintenance budget which was used to fund other repair and maintenance requirements.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
County Hall ComplexReport | 173 KB | DownloadRead as text |
PDF |
View item 4f as DOC 188 KBReport | 6 pages | Download |
Follow Executive Scrutiny Committee at Lancashire & Rossendale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 Apr 2017 | Minutes of the meeting held on 7 March 2017- That the minutes of the meeting held on 7 March 2017 be confirmed and signed by the Chair | Decided | Open |
| 4 Apr 2017 | Procurement Report - Request for Approval to Commence Procurement Exercises- That the recommendations set out in the report to the Deputy Leader of the County Council and the Cabinet Member fo... | Noted | Open |
| 4 Apr 2017 | Capital Strategy for Schools – Condition Led Capital Investment Programme, 2016/17 and part 2017/18- That the recommendations set out in the report to T he Cabinet Member for Children, Young People and Schools be not... | Noted | Open |
| 4 Apr 2017 | Exclusion of Press and Public- That under Section 100A(4) of the Local Government Act, 1972, the press and public should be excluded from the meet... | Decided | Open |
| 7 Mar 2017 | Minutes of the meeting held on 31 January 2017- That the minutes of the meeting held on 31 January 2017 be confirmed and signed by the Chair. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.