Resolved
- That the recommendations set out in the report to the Cabinet Member for Highways and Transport be noted and that no additional comments or suggested alternative recommendations be made.
Executive Scrutiny Committee noted this item on Tuesday 7 March 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
- That the recommendations set out in the report to the Cabinet Member for Highways and Transport be noted and that no additional comments or suggested alternative recommendations be made.
Having completed the GRIP 1- 2 stage in assessing the technical feasibility of constructing a rail link between the Wigan to Kirkby line and Skelmersdale, this report is requesting approval to commission Network Rail to undertake the GRIP2 refresh and 3A feasibility study.
This is deemed to be a Key Decision and the requirements of Standing Order 25 have been complied with.
The Cabinet Member for Highways and Transport is requested to;
(i) Approve that Network Rail is commissioned to carry out the GRIP 2 refresh and the GRIP 3A feasibility study into the Skelmersdale Rail Link project at an estimated cost of £5.1m with the costs met by the County Council, £4.335m and Merseytravel, £0.765m. (ii) Approve that the Director of Governance, Finance and Public Services be authorised on behalf of the County Council to enter into the 'Development Services Agreement (DSA)' between Lancashire County Council and Network Rail for the commissioning of the GRIP 2 refresh and the GRIP 3A feasibility study. (iii) Approve that the Director of Community Services and the Director of Governance, Finance and Public Services be authorised on behalf of the County Council to enter into a 'Funding Agreement' with Merseytravel. (iv) That the additional £0.955m required to be funded by LCC to be the first call on the 2018/19 Department for Transport (DfT) transport allocation; (v) Approve the addition to the capital programme of £0.765m funding from Merseytravel. Background and Advice
The West Lancashire Highways and Transportation Master Plan identified that a new rail link into Skelmersdale town centre would potentially be a catalyst for commercial, retail and housing developments. It would also provide significantly improved public transport connectivity into the Greater Manchester and Liverpool City Regions providing enhanced links to employment and educational opportunities.
Following publication of the Master Plan, Network Rail was commissioned by Merseytravel, in partnership with the County Council, to undertake a GRIP 1- 2 (Guide to Rail Investment Process) technical feasibility study to identify a possible alignment for the rail link from the existing Wigan to Kirkby line into Skelmersdale town centre. The study was completed in December 2014 and identified an alignment for the line as well as two potential locations for the new station. Following this a further study was commissioned from Network Rail to undertake a comparative assessment of the two potential locations for the new Skelmersdale station using a SWOT (strengths, weaknesses, opportunities and threats) analysis against a set of agreed criteria. The study was completed in December 2016 and on 23 January, 2017, the Cabinet Member for Highways and Transport approved the proposal that the new station should be constructed on the former Glenburn High School and Westbank Campus site.
At the same time Jacobs was commissioned to carry out the development of an outline business case for the project. This found that a new station at Skelmersdale could attract between 0.600m and 1.3m passengers per annum and that the overall project could have a BCR (benefit cost ratio) of between 1.5 and 2, which is regarded as good by the DfT.
As mentioned above, the GRIP 1 - 2 report identified a potential route for the rail link into Skelmersdale. However, this was a high level, mainly desk top study and it recommended that the feasibility of the identified route would need to be investigated in more detail at the GRIP 3 stage of the project.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix AAppendix A | 468 KB | Download |
PDF |
Skelmersdale Rail Link Grip 3 studyReport | 119 KB | DownloadRead as text |
PDF |
View item 4g as DOC 168 KBReport | 5 pages | Download |
Follow Executive Scrutiny Committee at Lancashire & Rossendale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 Apr 2017 | Minutes of the meeting held on 7 March 2017- That the minutes of the meeting held on 7 March 2017 be confirmed and signed by the Chair | Decided | Open |
| 4 Apr 2017 | Procurement Report - Request for Approval to Commence Procurement Exercises- That the recommendations set out in the report to the Deputy Leader of the County Council and the Cabinet Member fo... | Noted | Open |
| 4 Apr 2017 | Capital Strategy for Schools – Condition Led Capital Investment Programme, 2016/17 and part 2017/18- That the recommendations set out in the report to T he Cabinet Member for Children, Young People and Schools be not... | Noted | Open |
| 4 Apr 2017 | Exclusion of Press and Public- That under Section 100A(4) of the Local Government Act, 1972, the press and public should be excluded from the meet... | Decided | Open |
| 7 Mar 2017 | Minutes of the meeting held on 31 January 2017- That the minutes of the meeting held on 31 January 2017 be confirmed and signed by the Chair. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.