Resolved
That; The minutes of the meeting held on the 3 April 2017 be confirmed and signed by the Chair. A report on BTLS payroll processing be presented to a future meeting of the Committee
Audit, Risk and Governance Committee decided this item on Monday 26 June 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
That; The minutes of the meeting held on the 3 April 2017 be confirmed and signed by the Chair. A report on BTLS payroll processing be presented to a future meeting of the Committee
Lancashire County Council
Audit and Governance Committee
Minutes of the Meeting held on Monday, 3rd April, 2017 at 2.00 pm in Cabinet Room 'B' - The Diamond Jubilee Room, County Hall, Preston
Present:
County Councillors
K Brown A Schofield D Clifford V Taylor C Dereli B Winlow G Driver
1. Apologies
Deputy Chair (County Councillor Darren Clifford) welcomed members and apologies were noted from County Councillor Terry Brown.
2. Disclosure of Pecuniary and Non-Pecuniary Interests
There were no declarations of interest at this time.
3. Minutes of the Meeting held on 30 January 2017
Item 3 Minutes of the Meeting held on 26 September 2016
The following update on the Liquid Logic system from Lisa Kitto, Director of Corporate Services was reported to members:
'The initial scoping work for Project Accuracy for Adults is underway and being supported by Newton Europe. Two initial workshops have been held involving a number of key services including adult's social care, core systems, care navigation, procurement, finance and learning and development. A steering group has been established and will be chaired by the deputy Chief Executive, the first meeting of which will take place in April. A number of workstreams will report to the group including; social care practice and processes, design of 'to be' processes, data cleaning, system changes, training and commissioning. All of these will have detailed workplans and timescales against which the project will be monitored'.
Members were assured that a full update would be provided at the next meeting of the Committee.
1 Item 4 Update on Treasury Management Activity
Members were advised that the transitional arrangements that had been in place since the establishment of LPP had now been terminated and an agreement for the provision of Treasury Management Services by LPP to the Council was now in place. It was intended that detailed requirements would be finalised in the next two weeks and it was confirmed that a full report would be presented to the next meeting of the Committee.
Item 8 Internal Audit progress report
It was confirmed that the Corporate Director for Operations and Delivery attended the February meeting of the Scrutiny Committee (minutes from this meeting was circulated to members) to provide an update on the issues in adult services highlighted in the audit progress report. At this meeting, it was confirmed that the number of team managers had increased and would have responsibility for a maximum of 10 social workers to ensure sufficient oversight of social work practice. In addition, weekly case progression meetings had been introduced. Members were assured that the Scrutiny Committee was satisfied that the situation was being addressed and had requested a further report in six months.
It was confirmed that both the Scrutiny Committee and the Audit and Governance Committee would be kept informed.
Resolved: That the minutes of the meeting held on the 30 January 2017 be confirmed and signed by the Deputy Chair.
4. Risk and Opportunity Register - Quarter 4
Paul Bond, Head of Legal and Democratic Services, presented the Quarter 4 report of the Risk and Opportunity Register to the Committee.
It was reported that additional information had been included in CR1 to reflect the additional funding for social care over the next three years. It was confirmed that for Lancashire, this would equate to a total of £48m - £25m in 2017/18, £15m in 2018/19 and £8m in 2019/20.
CR24 Troubled Families – the risk score has increased due to the inability to achieve the National Troubled Families Unit targets. It was reported that this was as a result of a six month delay to the service commencing.
CR27 Homecare Framework – the procurement process was reported to be underway and at the evaluation stage. It was confirmed that the transition would be over a 12 month period to minimise disruption to service users.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes of the Meeting held on 3 April 2017Minutes | 73 KB | DownloadRead as text |
PDF |
View item 4. as DOC 66 KBMinutes | 4 pages | Download |
Follow Audit, Risk and Governance Committee at Lancashire & Rossendale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Jul 2026 | Constitution, Membership and Terms of ReferenceThat the following be noted: i) The appointment of County Councillor G Mirfin as Chair and County Councillor R Edward... | Noted | Open |
| 27 Jul 2026 | Minutes of the Meeting held on 27 April 2026That the minutes of the Audit, Risk and Governance Committee meeting held on 27 April 2026 be confirmed as an accurat... | Decided | Open |
| 27 Jul 2026 | Statement of Accounts 2025/26That the 2025/26 statement of accounts for Lancashire County Council be noted. | Noted | Open |
| 27 Jul 2026 | External Audit: Lancashire County Council External Audit Plan 2025/26That the Lancashire County Council External Audit Plan 2025/26 be noted. | Noted | Open |
| 27 Jul 2026 | External Audit: Lancashire County Pension Fund External Audit Plan 2025/26That the Lancashire County Pension Fund External Audit Plan 2025/26 be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.