Transport for Lancashire - Proposed Amendments to the LEP Assurance Framework
ApprovedCommittee4 papers
LEP - Transport for Lancashire Committee approved this item on Wednesday 10 January 2018. Below is the council's own wording, with the papers it was decided on.
That: (i) The proposed changes to the Committee's Terms of Reference in respect of the Accountability Framework for Transport schemes as set out at Appendix A be approved; and (ii) The proposed changes be included with the LEP's Assurance Framework to be presented to the Lancashire Enterprise Partnership Board on 30 January 2018 for consideration and approval.
Word for word from the decision Lancashire & Rossendale published for this meeting.Source: council.lancashire.gov.uk
Report to LEP - Transport for Lancashire Committee
Executive summary
This report requests that Transport for Lancashire (TfL) considers proposed amendments to the Accountability Framework for Transport schemes as set out in the LEP's Assurance Framework.
Should the Committee approve the proposed changes, these will be reflected in the LEP's Assurance Framework which is currently being reviewed and updated by officers. The revised Assurance Framework will be presented to the LEP Board on 30 January for consideration and approval.
Recommendation
The Transport for Lancashire Committee is asked to:
(i) Consider the contents of this report;
(ii) Approve the proposed changes to the Accountability Framework for Transport schemes as set out in the LEP's Assurance Framework; and
(iii) Recommend the proposed changes are included with the LEP's Assurance Framework which is currently being reviewed and updated by officers and will be presented to the LEP Board on 30 January 2018 for consideration and approval. Background and Advice
Transport for Lancashire's current Terms of Reference, part of the LEP's Assurance Framework that came into force in February 2017, state that the LEP will not fund scheme development and preparation costs nor any post scheme monitoring and evaluation. This is inconsistent with the other two themes of the Growth Deal programme covering skills and economic projects, where scheme preparation costs are permissible as part of the local contribution.
It is therefore proposed to amend the Terms of Reference to allow scheme sponsors to use a proportion of Growth Deal funding to support scheme preparation and development. It is further proposed that the minimum 10% local contribution scheme sponsors are required to provide can also include scheme preparation and development costs in addition to capital costs as currently approved. The proposed changes in respect of transport schemes will bring the management and delivery of the Growth Deal programme and scheme delivery into alignment. Local contributions will continue to be considered on a scheme by scheme basis to ensure that value for money is achieved.
Should the Committee approve the proposed changes, they will be reflected in an update of the LEP's Assurance Framework, which is currently under review by officers. The revised Assurance Framework will be presented to the LEP Board at its meeting on 30th January 2018 for consideration and approval.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow LEP - Transport for Lancashire Committee at Lancashire & Rossendale and we tell you when its next papers are published, before the meeting rather than after it.
South East Blackburn Funding ApplicationThat the Lancashire Enterprise Partnership Board be recommended to grant the scheme a maximum of £9.05m Growth Deal f...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.