Preston Western Distributor Conditional Approval Application
NotedCommittee3 papers
LEP - Transport for Lancashire Committee noted this item on Wednesday 10 January 2018. Below is the council's own wording, with the papers it was decided on.
That: i) The Outline Business Case report as set out at Appendix A to the report be noted. ii) The Lancashire Enterprise Partnership Board be recommended to grant the scheme Conditional Approval at their meeting on 30 ... view the full minutes text for item 6.
Word for word from the decision Lancashire & Rossendale published for this meeting.Source: council.lancashire.gov.uk
Report to LEP - Transport for Lancashire Committee
Executive summary
The Preston Western Distributor comprises a new 4.3km dual carriageway road that will connect the A583 Preston to Blackpool road at Lea with the M55 at a new Junction 2 near Bartle. It is by far the largest transport project in the Lancashire Growth Deal programme and key to unlocking the North West Preston strategic housing location (circa 5,000 new homes). Lancashire County Council has submitted an Outline Business Case to the Lancashire Enterprise Partnership (LEP) for Conditional Approval. The consultants Atkins have undertaken an independent assessment of the Outline Business Case on behalf of the LEP. Atkins are satisfied that the project has been developed to the expected standard in most areas and recommend that Conditional Approval be granted to enable the scheme to progress to Full Business Case submission.
Recommendation
The Transport for Lancashire Committee is asked to consider the attached Outline Business Case report prepared by Atkins and recommend that the LEP Board grant the scheme Conditional Approval at its meeting to be held on Tuesday 30th January 2018.
Background and Advice
The Preston Western Distributor comprises a new 4.3km dual carriageway road that will connect the A583 Preston to Blackpool road at Lea with the M55 at a new Junction 2 near Bartle. It is by far the largest transport project in the Lancashire Growth Deal programme and a key project within the Preston, South Ribble and Lancashire City Deal agreed with the Government in September 2013.
The scheme will support delivery of the North West Preston strategic housing location (circa 5,000 new homes) and improve access between the Enterprise Zone site at Warton and the Strategic Road Network. It will also facilitate construction of a new 'parkway' station at Cottam on the Preston to Blackpool North railway line, taking advantage of ongoing electrification and route upgrade work to provide rail- based park and ride opportunities to Preston/Manchester/Liverpool and Blackpool. The additional capacity will help alleviate peak hour congestion in Preston City Centre affecting east-west routes and facilitate the introduction of bus priority measures, public realm enhancements and improvements to prioritise and promote walking and cycling along existing road corridors.
The scheme promoter, Lancashire County Council, has submitted an Outline Business Case to the Lancashire Enterprise Partnership (LEP) for Conditional Approval. The granting of Conditional Approval is intended to provide the expectation of funding necessary for the promoting authority to apply for any statutory powers that may be required to deliver a scheme, for example, Transport and Works Act powers, highways orders, planning consents and/or compulsory purchase orders.
Conditional Approval indicates the LEP's acceptance of an Outline Business Case demonstrating high value for money. In accordance with its Assurance Framework, the LEP will only grant Conditional Approval on the basis that there will be no material changes to the scheme's scope, cost, design, expected benefits and value for money. The granting of Conditional Approval may be subject to a small and limited number of conditions.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow LEP - Transport for Lancashire Committee at Lancashire & Rossendale and we tell you when its next papers are published, before the meeting rather than after it.
South East Blackburn Funding ApplicationThat the Lancashire Enterprise Partnership Board be recommended to grant the scheme a maximum of £9.05m Growth Deal f...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.