CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Lancashire County Council / Rossendale Borough Council
Cabinet, Thursday 8 March 2018 at 2.00pm

Street Lighting - LED Lantern Replacement Scheme

Approved Executive 2 papers

Cabinet approved this item on Thursday 8 March 2018. Below is the council's own wording, with the papers it was decided on.

Item13

Resolved

That: i. the application for Salix funding as set out in the report be approved; ii. the proposal as set out in the report be included within the Capital Programme 2018-2021.
Word for word from the decision Lancashire & Rossendale published for this meeting. Source: council.lancashire.gov.uk

Follow this further

Built from Lancashire & Rossendale's papers

What the report saysPro

Report to Cabinet

Executive summary

The Department for Transport (DfT) Challenge Fund and the £5m county council Invest to Save schemes are nearing completion and collectively have enabled 87,000 light emitting diode (LED) lanterns to be installed and approximately £3.4m saved from the street lighting energy revenue budget since 2014/15.

Following discussions with Salix Finance Ltd, a government funded body that provides interest-free funding to the public sector to improve energy efficiency, reduce carbon emissions and lower energy bills, a proposal has now been developed to enable the street lighting energy efficiency programme to be completed. The proposal as detailed in the report meets Salix funding requirements and would enable a further 38,000 street lighting lanterns to be replaced with LED equivalents. It is anticipated the proposal will cost in the region of £9.200m, which would be funded by an interest free loan and enable a further £1.843m to be saved recurrently from the street lighting energy revenue budget per year when complete.

This is deemed to be a Key Decision and the provisions of Standing Order No. 26 have been complied with.

Recommendation

That Cabinet is recommended to approve:

(i) The application for Salix funding as set out in the report; (ii) That the proposal as set out in the report be included within the Capital Programme 2018-2021. Background and Advice

The first phase of the street lighting energy efficiency programme started in 2008 and ran until 2012. As a result of a successful bid to the Department for Transport (DfT) Challenge Fund in January 2015 the county council has been able to replace 67,000 LED lanterns, replace up to 4,000 lighting columns between June 2015 and March 2018 and establish a scheme to install 150 electric car charging points in the coming months. In 2017/18 the county council made a capital allocation of £5m to enable a further 20,000 LEDs to be installed and extend the scope of the DfT works.

By the end of March 2018 it is anticipated that following this three year investment period approximately 87,000 energy inefficient street lighting lanterns will have been replaced with LED equivalents and our energy consumption will have reduced by just over 37% between 2014/15 and 2017/18. Had this work not been carried out the 2017/18 street light energy revenue budget outturn would have been in the region of £8.2m instead of the current forecast to March 2018 of just over £5.1m.

Following discussions with Salix Finance Ltd, a government funded body that provides interest-free funding to the public sector to improve energy efficiency, reduce carbon emissions and lower energy bills, a further phase of the programme has now been developed to enable the street lighting energy efficiency programme to be completed. This proposal involves converting to LEDs, the remaining 38,000 non-LED street lights which mainly comprise of 150w and 250w high pressure sodium lamps and are of a higher wattage than the works undertaken as part of the DfT scheme. All installation works will be undertaken by the county council's highways service and the opportunity will be taken to revise lighting levels where appropriate which will involve changing some 250w lighting to 150w, using LED equivalents.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Street Lighting: LED Lantern Replacement SchemeReport 106 KB DownloadRead as text
PDF
View item 13. as DOC 186 KBReport 4 pages Download

At this meeting

Whole meeting
1The Leader proposed that permission to speak at the meetingDecided 3Minutes of the Meeting held on 1 February 2018Agreed 4Premises Use PolicyApproved 5Procurement Report - Request Approval to Commence Procurement ExercisesApproved 6Proposed Changes to the Highways and Transport Capital ProgrammesApproved 7Conversion of Footway to shared use Footway/Cycle Track and Adoption of Land - Westgate/Railway Road, SkelmersdaleApproved 8Lancashire County Council (Sir Frederick Page Way, Samlesbury, Ribble Valley and South Ribble Boroughs) (Prohibition of Stopping) and (30MPH Speed Limit) Orders 201*Approved 9Lancashire County Council (Various Roads, Rossendale Borough Area) (Revocation and Introduction of Parking Places) Order 201* and Lancashire County Council (Parramatta Street and Queen Street, Rossendale Borough Area) (Amendment to Parking Provisions) Order 201*Approved 10Department for Transport Consultation: Proposals for the Creation of a Major Road NetworkApproved 11Proposed 2018/19 Highway Maintenance and Road Safety, Cycling Safety and Public Rights of Way New Starts Capital ProgrammesApproved 12A682 Gisburn Road, Blacko contained within Lancashire County Council (Various Roads, Chorley, Fylde, Pendle, Preston, Rossendale, South Ribble, West Lancashire and Wyre Boroughs) (Revocation, 30mph, 40mph, 50mph and De-Restricted Road (August No 1) Speed Limits) Order 201*Approved
13Street Lighting - LED Lantern Replacement SchemeThis decision
14Proposed Expansion of Barrow Primary School, ClitheroeApproved 15The Future of Baines School's Post 16 ProvisionNoted 16The Future of Carr Hill High School and Sixth Form Centre's Post 16 ProvisionNoted 17Awarding of Small Grants to Third Sector Groups which are Registered with the Children and Family Wellbeing Service, including Grants to Individual Young PeopleApproved 18Special Educational Needs and Disabilities (SEND) School Placement Sufficiency and Suitability Plan 2018-21Approved 19Library Opening Hours Review 2018Approved 24Exclusion of Press and PublicDecided 25Programme of Works to Operational BuildingsPrivate 26Community Asset Transfers - Approval for TransferPrivate 27Contract extension for the Health Visitors/School Nurses contractsPrivate 28Long Term Options for Service Provision at Walton-Le-Dale Park and RidePrivate 29Billington & Langho St. Leonards CE School Expansion to 1.5 Form Entry Project - Further Additional Funding RequirementPrivate 30Children Looked After (CLA) Residential Strategy - Capital SchemesPrivate 31Cuerden Strategic Site - Land Sale ProposalsPrivate 32Transfer of Fleetwood Maritime MuseumPrivate 33Proposals Relating to Libraries - EarbyPrivate

Who was there

8 of 8 attended
CG
CC G Driver Leader of the CouncilChair, present
CA
CC A AtkinsonDeputy Chair, present
CM
CC M GreenCommittee Member, present
CS
CC S CharlesCommittee Member, present
CK
CC K IddonCommittee Member, present
CP
CC P BuckleyCommittee Member, present
CG
CC G GoochCommittee Member, present
CS
CC S TurnerCommittee Member, present

On this subject at Lancashire & Rossendale

Search all
  1. Street Lighting - LED Lantern Replacement SchemeThis decision
  2. Hyndburn Borough: LCC/2024/0039 Public realm improvements including soft landscaping, resurfacing, street furniture and cycle stands, wayfinding signage, lighting, drainage swale and public artwork. Nuttall Street Civic Space, Land at junction of Nuttall Street and Royds Street, AccringtonDecided
  3. Rossendale Borough: LCC/2024/0040 Formation of green space including landscaping, footpath, play equipment, street furniture and lighting, Land between Fallbarn Crescent and Hardman Avenue, RawtenstallDecided
  4. Street Lighting Budget ConsultationApproved
  5. Hyndburn Borough: Application 11/13/0013 Proposed bus station for Accrington town centre, including a new pedestrian arcade link and the provision of new lighting columns on land at Crawshaw Street Car Park, AccringtonDecided

More from Lancashire & Rossendale Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 Minutes of the Meeting held on 2 July 2026That the minutes of the meeting held on 2 July 2026 be confirmed as a correct record and signed by the Chair. Decided Open
3 Sep 2026 Quarter 1 2026/27 Corporate Performance ReportThat, following consideration of the performance of the Council in Quarter 1 of 2026/27 against the ambitions set out... Noted Open
3 Sep 2026 2026/27 Quarter 1 Financial Monitoring ReportThat i. The current forecast Revenue Budget overspend at Quarter 1 of £15.655m (1.18%), as detailed in Appendix 'A' o... Noted Open
3 Sep 2026 Ofsted Inspection of Lancashire Children's ServicesThat, following consideration of the outcome of the inspection, which confirmed that Lancashire's Children's Services... Approved Open
3 Sep 2026 SEND Capital ProjectThat i. Following consideration of the positive consultation responses, the prior approval of those projects through ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies