Resolved
That: i. the application for Salix funding as set out in the report be approved; ii. the proposal as set out in the report be included within the Capital Programme 2018-2021.
Cabinet approved this item on Thursday 8 March 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
That: i. the application for Salix funding as set out in the report be approved; ii. the proposal as set out in the report be included within the Capital Programme 2018-2021.
The Department for Transport (DfT) Challenge Fund and the £5m county council Invest to Save schemes are nearing completion and collectively have enabled 87,000 light emitting diode (LED) lanterns to be installed and approximately £3.4m saved from the street lighting energy revenue budget since 2014/15.
Following discussions with Salix Finance Ltd, a government funded body that provides interest-free funding to the public sector to improve energy efficiency, reduce carbon emissions and lower energy bills, a proposal has now been developed to enable the street lighting energy efficiency programme to be completed. The proposal as detailed in the report meets Salix funding requirements and would enable a further 38,000 street lighting lanterns to be replaced with LED equivalents. It is anticipated the proposal will cost in the region of £9.200m, which would be funded by an interest free loan and enable a further £1.843m to be saved recurrently from the street lighting energy revenue budget per year when complete.
This is deemed to be a Key Decision and the provisions of Standing Order No. 26 have been complied with.
That Cabinet is recommended to approve:
(i) The application for Salix funding as set out in the report; (ii) That the proposal as set out in the report be included within the Capital Programme 2018-2021. Background and Advice
The first phase of the street lighting energy efficiency programme started in 2008 and ran until 2012. As a result of a successful bid to the Department for Transport (DfT) Challenge Fund in January 2015 the county council has been able to replace 67,000 LED lanterns, replace up to 4,000 lighting columns between June 2015 and March 2018 and establish a scheme to install 150 electric car charging points in the coming months. In 2017/18 the county council made a capital allocation of £5m to enable a further 20,000 LEDs to be installed and extend the scope of the DfT works.
By the end of March 2018 it is anticipated that following this three year investment period approximately 87,000 energy inefficient street lighting lanterns will have been replaced with LED equivalents and our energy consumption will have reduced by just over 37% between 2014/15 and 2017/18. Had this work not been carried out the 2017/18 street light energy revenue budget outturn would have been in the region of £8.2m instead of the current forecast to March 2018 of just over £5.1m.
Following discussions with Salix Finance Ltd, a government funded body that provides interest-free funding to the public sector to improve energy efficiency, reduce carbon emissions and lower energy bills, a further phase of the programme has now been developed to enable the street lighting energy efficiency programme to be completed. This proposal involves converting to LEDs, the remaining 38,000 non-LED street lights which mainly comprise of 150w and 250w high pressure sodium lamps and are of a higher wattage than the works undertaken as part of the DfT scheme. All installation works will be undertaken by the county council's highways service and the opportunity will be taken to revise lighting levels where appropriate which will involve changing some 250w lighting to 150w, using LED equivalents.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Street Lighting: LED Lantern Replacement SchemeReport | 106 KB | DownloadRead as text |
PDF |
View item 13. as DOC 186 KBReport | 4 pages | Download |
Follow Cabinet at Lancashire & Rossendale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Sep 2026 | Minutes of the Meeting held on 2 July 2026That the minutes of the meeting held on 2 July 2026 be confirmed as a correct record and signed by the Chair. | Decided | Open |
| 3 Sep 2026 | Quarter 1 2026/27 Corporate Performance ReportThat, following consideration of the performance of the Council in Quarter 1 of 2026/27 against the ambitions set out... | Noted | Open |
| 3 Sep 2026 | 2026/27 Quarter 1 Financial Monitoring ReportThat i. The current forecast Revenue Budget overspend at Quarter 1 of £15.655m (1.18%), as detailed in Appendix 'A' o... | Noted | Open |
| 3 Sep 2026 | Ofsted Inspection of Lancashire Children's ServicesThat, following consideration of the outcome of the inspection, which confirmed that Lancashire's Children's Services... | Approved | Open |
| 3 Sep 2026 | SEND Capital ProjectThat i. Following consideration of the positive consultation responses, the prior approval of those projects through ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.