That the proposal to proceed with the procurement process for the Preston Youth Zone Operator be approved on the basis that the county council's capital contribution is capped at £5.925m and all additional capital requirements, estimated at £2.605m, are met by the private/voluntary sector delivery partner.
Word for word from the decision Lancashire & Rossendale published for this meeting.Source: council.lancashire.gov.uk
The Cabinet approved a report on 10 August 2017, recommending the commencement of a procurement exercise to secure a Youth Zone Operator for the delivery of the Preston Youth Zone. A Prior Information Notice was issued on 12 October 2017 to prepare the market for the release of the tender documents.
In June 2016 the Cabinet received a report which provided a cost estimate of £6.925m for the design and construction of the Preston Youth Zone. The county council has committed a capital contribution of £5.925m to the scheme with the requirement that the Youth Zone operator provide the remaining £1m.
The estimate of £6.925m has been reviewed to take account of a recalculation of Tender Price Inflation, a revised design to accommodate the co-location of the Preston Youth Offending Team service and an enhanced specification of the external cladding. This has resulted in an increase in the cost estimate of £1.605m and a total capital cost of £8.53m.
Recommendation
The Cabinet is asked to approve the proposal to proceed with the procurement process for the Preston Youth Zone Operator on the basis that the county council's capital contribution is capped at £5.925m and all additional capital requirements, estimated at £2.605m, are met by the private/voluntary sector delivery partner.
Background and Advice
The Cabinet Member for Young People and the Leader received a report from the Executive Director for Children and Young People in July 2011 proposing the delivery of a Preston Youth Zone Plus. This report established a Council capital contribution of £3m towards the development of this facility on a site to be provided by the Council.
Following the transfer of the ownership of the Preston Bus Station to the Council, Cabinet agreed (6 November 2014) to locate the Preston Youth Zone Plus on the western apron of the bus station complex and to increase the Council's capital contribution to £5m.
Informed by a detailed design, and with the advice of the Council's construction framework partner Keepmoat, the cost estimate for the Preston Youth Zone was revised to £6.925m. The additional £925,000 was approved by Cabinet at its meeting on 9 June 2016.
Revised Cost Estimate for Preston Youth Zone
The period from Cabinet approval (June 2016) to the revised projected start on site (October 2018) has seen a number of factors place significant pressure on the Preston Youth Zone cost plan. These factors have been costed and represent an additional £1.605m taking the estimated outturn cost to £8.53m.
The first, and by far most significant factor, is construction Tender Price Inflation of just over £1.038m. An initial allowance for construction Tender Price Inflation was included to cover the period from Cabinet approval to the anticipated start on site. The initial inflation allowance was c.2% (taken from the Building Cost Information Service) of the construction cost for the scheme.
Actual construction Tender Price Inflation has exceeded all forecasts across the development and construction sectors over this period. The period from June 2016 to March 2017 saw Tender Price Inflation increase by 8% in comparison to the Building Cost Information Service allowance of 2%.
In addition to construction Tender Price Inflation further refinement of the design has resulted in additional costs. The Design Team, (advised by specialist Fire Engineering Consultants), has recommended an enhanced specification for the external cladding of the Youth Zone. This expenditure provides an element of future- proofing to the building in light of the likely changes to Building Regulations requirements.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.