That: i. the proposed revisions to the approved apportionment of the 2019/20 New Start Highway Maintenance programme as detailed in the report be approved. ii. the proposed 2019/20 New Start Highway Maintenance programmes set out as projects in the repot be approved; iii. approval be given for additional schemes to be identified for funding from the ABC, Urban Unclassified, Rural Unclassified, and footways allocations up to the value of the approved allocation, subject to consultation with the Cabinet Member for Highways and Transport. iv. a further report be brought forward in relation to the Moss Roads programme. v. the detailed apportionment of the £2.774m allocation for 'Other Transport Schemes as detailed in the report be approved. vi. the proposed 2019/20 New Start Public Rights of Way programme set out in the report be approved. vii. a further report be brought forward in relation to the 2019/20 New Start Road Safety and Cycling safety programmes viii. the thanks of Cabinet be given to officers who have developed the programme.
Word for word from the decision Lancashire & Rossendale published for this meeting.Source: council.lancashire.gov.uk
On 14 February 2019 Full Council approved the high level apportionment of anticipated 2019/20 highway maintenance and transport grant funding from the Department for Transport (DfT). Subsequently, this report recommends approval of a more detailed apportionment and approval of a number of detailed programmes of work relating to this funding as set out at Appendices 'B' to 'H'.
This is deemed to be a Key Decision and the provisions of Standing Order C19 have been complied with.
Recommendation
Cabinet is asked to:
(i) Approve the proposed revisions to the approved apportionment of the 2019/20 New Start Highway Maintenance programme as detailed in the report. (ii) Approve the proposed 2019/20 New Start Highway Maintenance programmes set out as projects at Appendices 'B' to 'G'; (iii) Give approval for additional schemes to be identified for funding from the ABC, Urban Unclassified, Rural Unclassified, and footways allocations up to the value of the approved allocation, subject to consultation with the Cabinet Member for Highways and Transport. (iv) Approve that a further report be brought forward in relation to the Moss Roads programme. (v) Approve the detailed apportionment of the £2.774m allocation for 'Other Transport Schemes as detailed in the report. (vi) Subject to the approval of (v) above, approve the proposed 2019/20 New Start Public Rights of Way programme set out at Appendix 'H'. (vii) Approve that a further report be brought forward in relation to the 2019/20 New Start Road Safety and Cycling safety programmes.
Background and Advice
Proposed 2019/20 New Start Highway Maintenance Capital Projects
On 14 February 2019 Full Council approved the apportionment of anticipated 2019/20 highway maintenance grant funding from the Department for Transport (DfT). This specifically included;
The indicative Highways Maintenance Needs allocation of £18.567 million. The Local Highways Maintenance Incentive Fund anticipated to be £3.867 million. Additional Local Highways Maintenance funding of £10.229 million less £1.5 million already allocated to the 2018/19 programme.
The total value of the 2019/20 New Start programme is therefore £31.163 million.
As a result of a number of recently identified pressures the following changes are required to the approved apportionment;
Table 1
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.