Resolved
That the proposed provision of three cycle track lengths with right of way on foot and the implementation of No Waiting At Any Time Restrictions as set out in the report be approved.
Cabinet approved this item on Thursday 11 April 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
That the proposed provision of three cycle track lengths with right of way on foot and the implementation of No Waiting At Any Time Restrictions as set out in the report be approved.
This report outlines proposals to provide a cycle track with right of way on foot along lengths of St Crispin Way, Flip Road and Grane Road Haslingden, which is part of National Cycle Route 6. Proposals for waiting restrictions required in conjunction with the cycle track are also described.
Consultation and formal advertising of the proposals has been undertaken with one objection being received.
Cabinet is asked to approve the proposed provision of three cycle track lengths with right of way on foot and the implementation of No Waiting At Any Time Restrictions as shown in Appendices 'A' and 'B'.
Background and Advice
The East Lancashire Highways and Transport Masterplan includes creation of an East Lancashire Strategic Cycleway Network. National Cycle Route 6 forms part of this network, providing a cycle route between Accrington to the north and the Lancashire boundary near Stubbins to the south.
As part of the scheme, it is proposed that St Crispin Way, Flip Road and Grane Road, Haslingden, require the following measures as shown in Appendices 'A' and 'B', in order to provide an improved route for cyclists; (a) Cycle Track Length A - An existing footway will be widened into the carriageway and then removed and cycletrack constructed being the old footway width and this cycle track will be for cycles with right of way on foot. The minimum width of this cycle track will be 3.0 m, this is considered wide enough to be safely shared by pedestrians and cyclists. The change to carriageway width is not considered to impact on carriageway use or safety
(b) Cycle Track Length B – That subject to the dedication of extra highway width from Highways England, remove the verge and construct a cycle track over which the public have a right of way on foot. The minimum width of this cycle track will be 3.0 m, this is considered wide enough to be safely shared by pedestrians and cyclists.
(c) Cycle Track Length C – An existing footway will be removed and cycletrack constructed being the old footway width. This will be a cycle track with right of way on foot, the minimum width of this cycle track will be 3.0 m, and this is considered wide enough to be safely shared by pedestrians and cyclists.
(d) Cycle Track Length D – An existing footway will be widened into the carriageway then removed and cycletrack constructed being the old footway width and this cycletrack will be for cycles with right of way on foot. The minimum width of this cycle track will be 2.8 m, this is considered wide enough to be safely shared by pedestrians and cyclists. The change to carriageway width is not considered to impact on carriageway use or safety.
(e) No Waiting at Any Time Restrictions - Various lengths of 'No Waiting at Any Time' parking restrictions are required to prohibit motor vehicles from restricting use of the cycle track to its intended users. This will also improve visibility to and of cyclists crossing and joining the carriageway.
Consultations
Formal advertising of the proposed waiting restrictions was undertaken during December 2018 resulting in one objection regarding the loss of on street parking.
Insufficient parking currently available for local business in St Crispin Way with no alternatives available together with inadequate transport connections, there is a potential threat of a loss of jobs if the proposal is enforced.
In response:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix AAppendix A | 410 KB | Download |
PDF |
Appendix BAppendix B | 176 KB | Download |
PDF |
St Crispin Way, Flip Road and Grane Road, Haslingden Cycle Track and Waiting RestrictionsReport | 104 KB | DownloadRead as text |
PDF |
View item 8. as DOC 156 KBReport | 3 pages | Download |
Follow Cabinet at Lancashire & Rossendale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Sep 2026 | Minutes of the Meeting held on 2 July 2026That the minutes of the meeting held on 2 July 2026 be confirmed as a correct record and signed by the Chair. | Decided | Open |
| 3 Sep 2026 | Quarter 1 2026/27 Corporate Performance ReportThat, following consideration of the performance of the Council in Quarter 1 of 2026/27 against the ambitions set out... | Noted | Open |
| 3 Sep 2026 | 2026/27 Quarter 1 Financial Monitoring ReportThat i. The current forecast Revenue Budget overspend at Quarter 1 of £15.655m (1.18%), as detailed in Appendix 'A' o... | Noted | Open |
| 3 Sep 2026 | Ofsted Inspection of Lancashire Children's ServicesThat, following consideration of the outcome of the inspection, which confirmed that Lancashire's Children's Services... | Approved | Open |
| 3 Sep 2026 | SEND Capital ProjectThat i. Following consideration of the positive consultation responses, the prior approval of those projects through ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.