That: i The procurement of a contract for the treatment of residual waste in Lancashire from 2025 on the basis outlined in the report be approved. ii The Head of Service for Waste, in liaison with Procurement and Legal services, be authorised to make any appropriate amendments to the proposed contract during the procurement process to ensure that the council achieves the best financial and environmental outcome from the procurement exercise insofar that the basic principles of what is to be procured as outlined in the report are not significantly changed. iii The Chief Executive and Director of Resources be requested to arrange for county councillors to be provided with 'bite size' briefings on the subject matter as appropriate.
Word for word from the decision Lancashire & Rossendale published for this meeting.Source: council.lancashire.gov.uk
The council is currently reliant on landfill for the disposal of a significant quantity of the residual waste collected from households in Lancashire. Our existing landfill contract ends in 2025.
The Waste service is seeking approval to procure a 15 year contract for the thermal treatment of Lancashire's residual waste from 2025, providing a better environmental solution for the county and potentially reducing costs. The contract would commence in April 2025 and may result in the private sector development of new waste treatment infrastructure within or outside of Lancashire, the utilisation of existing infrastructure nationally, or both.
The estimated value of the contract is in the region of £40m per annum.
This is deemed to be a Key Decision and the provisions of Standing Order No. C19 have been complied with.
Recommendation
Cabinet is asked to:
(i) Approve the procurement of a contract for the treatment of residual waste in Lancashire from 2025 on the basis outlined in the report ;and
(ii) Authorise the Head of Service for Waste, in liaison with Procurement and Legal services, to make any appropriate amendments to the proposed contract during the procurement process to ensure that the council achieves the best financial and environmental outcome from the procurement exercise. Insofar that the basic principles of what is to be procured as outlined in the report are not significantly changed. Background and Advice
Lancashire produces around 400,000 tonnes of household residual waste (grey bin rubbish) a year. Around a half of this residual waste is processed into Refuse Derived Fuel (RDF) through the waste recovery parks at Farington and Thornton and used to produce electricity through thermal treatment (often referred to as 'Energy from Waste') or is used in the cement industry. The remainder is landfilled.
The county council's existing landfill contract was procured in 2006 in order to provide a disposal solution for the east of Lancashire, which had no identified alternative treatment option at that time, and to dispose of residues from the processes at Farington and Thornton. The contract ends in 2025.
The end of the landfill contract provides the opportunity for Lancashire to move away from landfill for all but the wastes that cannot be dealt with in any other way. Industry engagement has demonstrated that alternative treatment processes are available, or can be delivered, for the long term treatment of the county's residual waste in a more sustainable and environmentally responsible manner.
On this basis, the Waste service is seeking to procure a contract (or contracts) for the thermal treatment of residual waste from 2025. Thermal treatment can take a number of forms, but it is intended that we seek a technology which is proven in terms of both its operational and environmental performance. As a minimum requirement, the treatment process will need to demonstrate additional beneficial outcomes such as energy production, combined heat and power schemes or industrial benefit such as use in manufacturing.
Key elements of the procurement are outlined in the following table:
Contract Initial period of 15 years commencing 1st April 2025 with options duration to extend the contract, beyond the initial term for further periods of 5 years, commencing: 1st April 2040 and ending 31st March 2045; and 1st April 2045 and ending 31st March 2050.
Location The location of any final treatment process will not be prescribed but transport costs to any delivery point will be included in the evaluation.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.