Severe Weather Funding for Damage following Storms Ciara and Dennis

Approved Executive 4 papers

Cabinet approved this item on Thursday 14 May 2020. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

That i. £1,636,808 be allocated to the urgent works, as detailed at Appendix 'A', from the £5m additional capital funding approved by Full Council, as part of the county council's budget, for highway maintenance in February 2020. ii. the decision be implemented immediately for the purposes of Standing Order C29 as any delay would have an adverse effect on the operations of the county council in delivering this urgent maintenance work.
Word for word from the decision Lancashire & Rossendale published for this meeting. Source: council.lancashire.gov.uk

Follow this further

Built from Lancashire & Rossendale's papers

What the report saysPro

Report to Cabinet

Executive summary

Following severe weather events in February 2020 the Highways Asset Management Team has been working to collate the damages caused by Storm Ciara and subsequently Storm Dennis. The damages have been categorised as:  urgent (work required to prevent further deterioration that could cause road closures or community severance),  priority (Works to be programmed in the next 6-12 months),  work required (Remedial works to be programmed in the next 12-24 months) The total estimated cost of repairs required due to the above storms is estimated at £4,709,385 (including £4,461,857 capital and £247,528 revenue costs). Funding is required to undertake the urgent work that is required in the next 6 months with a value of £1,636,808. Recommendation

The Leader of the Council and the Deputy Leader of the Council and Cabinet Member for Highways and Transport are asked to approve that £1,636,808 be allocated to the urgent works, as detailed at Appendix 'A', from the £5m additional capital funding approved by Full Council, as part of the county council's budget, for highway maintenance in February 2020.

This decision should be implemented immediately for the purposes of Standing Order C29 as any delay could adversely affect the execution of the county council's responsibilities. The reason for this is that the decision has been designated as business critical by the relevant Executive Director, and any delay in its implementation would have an adverse effect on the operations of the county council.

Background and Advice

Following severe weather events in February 2020 the Highways Asset Management Team have been working to collate the damages caused by Storm Ciara and subsequently Storm Dennis. The damages have been categorised as:  urgent (work required to prevent further deterioration that could cause road closures or community severance),  priority (Works to be programmed in the next 6-12 months),  work required (Remedial works to be programmed in the next 12-24 months)

The total estimated cost of repairs required due to the above storms is estimated at £4,709,385 (including £4,461,857 capital and £247,528 revenue costs).

Capital Board has considered the damages and it is proposed that the non-urgent works be considered as first call in the preparation for the 21/22 capital programme and where possible will be advanced to 20/21 if underspends are identified within the works already approved in this year's capital programme.

Funding is required to undertake the urgent work that is required in the next 6 months with a value of £1,636,808, as detailed at Appendix 'A', to prevent further deterioration, road closures and community severance. It is recommended that: £1,636,808 be allocated to the urgent works, as detailed at Appendix 'A', from the £5m additional capital approved by Full Council in February 2020 for highway maintenance. A further report will be presented to Cabinet in due course proposing the apportionment of the remaining additional funding of £3,363,192.

Consultations

N/A

Implications:

This item has the following implications, as indicated: Risk management

Failure to approve funding for the schemes detailed at Appendix 'A' may result in further deterioration, road closures or community severance.

Financial

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 242 KB Download
PDF
Severe Weather Funding for Damage following Storms Ciara and DennisReport 122 KB DownloadRead as text
PDF
View as DOCX (4./2) 14 KBAppendix 1 pages Download
PDF
View item 4. as DOC 150 KBReport 2 pages Download

At this meeting

Whole meeting

Who was there

8 of 8 attended
CG
CC G Driver Leader of the CouncilChair, present
CK
CC K IddonDeputy Chair, present
CA
CC A AtkinsonCommittee Member, present
CM
CC M GreenCommittee Member, present
CP
CC P WilliamsonCommittee Member, present
CP
CC P BuckleyCommittee Member, present
CG
CC G GoochCommittee Member, present
CS
CC S TurnerCommittee Member, present

More from Lancashire & Rossendale Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 Minutes of the Meeting held on 2 July 2026That the minutes of the meeting held on 2 July 2026 be confirmed as a correct record and signed by the Chair. Decided Open
3 Sep 2026 Quarter 1 2026/27 Corporate Performance ReportThat, following consideration of the performance of the Council in Quarter 1 of 2026/27 against the ambitions set out... Noted Open
3 Sep 2026 2026/27 Quarter 1 Financial Monitoring ReportThat i. The current forecast Revenue Budget overspend at Quarter 1 of £15.655m (1.18%), as detailed in Appendix 'A' o... Noted Open
3 Sep 2026 Ofsted Inspection of Lancashire Children's ServicesThat, following consideration of the outcome of the inspection, which confirmed that Lancashire's Children's Services... Approved Open
3 Sep 2026 SEND Capital ProjectThat i. Following consideration of the positive consultation responses, the prior approval of those projects through ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies