That: i. the proposed apportionment of the additional £5 million of capital funding approved by Full Council on 13th February 2020 for highway maintenance be approved. ii. the detailed programmes of work relating to the Footways, ABC and Urban unclassified programmes be approved, in conjunction with the Cabinet Member for Highways and Transport and that those schemes next in priority that did not make the 'draw the line' for inclusion in the 2020/21 Capital Programme that are deliverable in light of the Covid-19 pandemic restrictions be included.
Word for word from the decision Lancashire & Rossendale published for this meeting.Source: council.lancashire.gov.uk
This report requests approval of the proposed apportionment of the additional £5 million of capital funding approved by Full Council on 13 February 2020 for highway maintenance.
This is deemed to be a Key Decision and the provisions of Standing Order C19 have been complied with.
Recommendation
Cabinet is asked to:
(i) Approve the proposed apportionment of the additional £5 million of capital funding approved by Full Council on 13th February 2020 for highway maintenance.
(ii) Approve that the detailed programmes of work relating to the Footways, ABC and Urban unclassified programmes be agreed, in conjunction with the Cabinet Member for Highways and Transport and include those schemes next in priority that did not make the 'draw the line' for inclusion in the 2020/21 Capital Programme that are deliverable in light of the Covid-19 pandemic restrictions.
Background and Advice
In February 2020 Full Council approved an additional £5m of capital funding for highway maintenance. The proposed apportionment detailed below supports the Transport Asset Management Plan principles to manage the highway assets, using a risk based preventative maintenance approach that will help reduce further deterioration of the highway network.
In February 2020, the severe weather, including Storms Ciara and Dennis, caused significant damage to highway assets in Lancashire. The total estimated cost of repairs required due to the above storms has been estimated at £4,709,385 (including £4,461,857 capital and £247,528 revenue costs).
Of this, £1,636,808 is required to fund urgent work to prevent further deterioration, road closures and community severance. On 14 May 2020 Cabinet gave approval for the urgent work to be funded from the additional £5m approved by Full Council for highway maintenance in February 2020.
It is proposed that non urgent work totalling £3,363,192 is funded from any underspends resulting from efficiencies in the previously approved 2020/21 approved capital programme and/or inclusion in the 2021/22 Capital programme.
Localised Deterioration It is proposed that the Localised Deterioration allocation be used to address smaller areas of deterioration that tend not to qualify for inclusion in resurfacing or surface dressing programmes but are too big to be addressed by the structural maintenance allocation. The sites will be identified by the Highway Maintenance Service and prioritised by Asset Management in line with Transport Asset Management Plan principles.
Spray Injection patching
Spray injection patching works will be focused on the rural unclassified network in areas not prioritised by the existing capital programme. The sites will be identified by the Highway Maintenance Service and prioritised by Asset Management in line with Transport Asset Management Plan principles. ABC & Urban Unclassified roads
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.