That: (i) The allocation of additional Transport Infrastructure Investment Fund money of £15,891,000 to the 2020/21 Capital Programme as described in the report, be approved. (ii) The funding of the A601( M) bridge and highway maintenance scheme be approved. (iii) The funding of the storm damage schemes detailed in Appendix 'A' be approved. (iv) The apportionment of funding to preventative maintenance schemes detailed in Appendix 'B' be approved. (v) The Moss Roads programme for 2020/21, detailed in Appendix 'C', which included the schemes funded from the approved Capital Programme agreed by Cabinet in March 2020 and those funded from the Transport Infrastructure Investment Fund, be approved.
Word for word from the decision Lancashire & Rossendale published for this meeting.Source: council.lancashire.gov.uk
The Department for Transport has announced funding under the heading Transport Infrastructure Investment Fund that pulls together a number of previously announced funding streams including the 2020/21 Challenge Fund and the Pothole Action Fund. The allocation for Lancashire is £15,891,000. It has been confirmed that it is not ring-fenced and that authorities can spend on capital projects such as preventative maintenance and storm damage as a result of the severe weather events earlier in the year. The additional funding announcement gives us a number of opportunities. This is deemed to be a Key Decision and the provisions of Standing Order C19 have been complied with.
Recommendation
Cabinet is asked to approve:
(i) The additional Transport Infrastructure Investment Fund money of £15,891,000 be allocated to the 2020/21 Capital Programme as described in the report.
(ii) The funding of the A601(M) bridge and highway maintenance scheme.
(iii) The funding of the storm damage schemes detailed in Appendix 'A'. (iv) The apportionment of funding to preventative maintenance schemes detailed in Appendix 'B'.
(v) The Moss Roads Programme for 2020/21, detailed in Appendix 'C', which included the schemes funded from the approved Capital Programme agreed by Cabinet in March 2020 and those funded from the Transport Infrastructure Investment Fund.
Background and Advice
The Department for Transport has announced £15,891,000 under the heading Transport Infrastructure Investment Fund that pulls together a number of previously announced funding streams including the 2020/21 Challenge Fund and the Pothole Action Fund. The Department for Transport has confirmed that that due to the ongoing coronavirus issues and pressures on authorities that the competition for 2020/21 Challenge Fund funding (£100mn) will now be allocated by formula. They also confirmed that the funding allocated can use used to undertake the schemes proposed in the Expression of Interest if deemed a priority by the local authority and that the fund is not ring-fenced; confirming that authorities can spend on preventative maintenance capital schemes and storm damage as a result of the severe weather events earlier in the year.
In October 2019 Cabinet approved the submission of an Expression of Interest to the Challenge Fund for the A601(M) scheme detailed below. This report proposes that the scheme should be funded from the Transport Infrastructure Investment Fund as it is the lowest cost option for maintenance spend over 30 years and if not approved an additional £1.6m will required to be spent in 2021/22 which is not budgeted for. This report also proposes that fund also be used to address the urgent storm damage works, as a result of storms Ciara and Dennis in February 2020, identified following underwater and confined space inspections and the priority works previously identified to prevent further deterioration. The additional funding announcement also allows deliver the Transport Asset Management Plan preventative maintenance approach, prioritising schemes in line with the approach approved at the March 2020 Cabinet.
Proposals for apportioning the additional Department for Transport allocation of £15,891,000 from the Transport Infrastructure Investment Fund It is proposed to apportion the £15,891,000 as per table 1 and described in detail below and in Appendix 'A'. Table 1: Proposed Apportionment
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.