That; i. The review of Burnley Campus, Phase 1 be approved; ii. The relocation of Reedley Hallows Nursery and Reedley Hallows Children and Family Wellbeing Service to part of the former Thomas Whitham accommodation, be approved; iii. The provision of additional places, for one year only in 2021, at Barden Primary School, through the addition of one classroom to the school be approved; iv. The provision of a Special Educational Needs unit for Barden Primary School, located within the former Thomas Whitham accommodation be approved; v. The provision of additional accommodation for Holly Grove Special School, increasing the building capacity by using the vacated Reedley Hallows nursery accommodation allowing the number of pupils to be increased in the future via a further Cabinet report be approved; and vi. The capital expenditure detailed in Appendix 'A' of the report to deliver phase 1, be approved.
Word for word from the decision Lancashire & Rossendale published for this meeting.Source: council.lancashire.gov.uk
Burnley Campus was built in 2008 under the Private Finance Initiative programme: Building Schools for the Future. It provides accommodation for Barden Primary School, Holly Grove Primary School (Special Educational Needs), Reedley Hallows Nursery School, Burnley Campus Library, Reedley Hallows Children and Family Wellbeing Service, The Faith Centre and The Exchange in Burnley.
Following the closure of Thomas Whitham Sixth Form, the vacated accommodation at Burnley Campus needs to be reviewed and alternate use identified. The School Planning Strategy has identified the need for 30 additional primary school places, which can be met by the addition of a temporary form of entry for September 2021 at Barden Primary School.
The Special Educational Needs and Disability sufficiency strategy under priority 3 aims to ensure that all pupils with Education Health and Care Plans have access to mainstream education within their local community. Barden Primary School expressed an interest in providing a special educational needs unit, within their mainstream school setting, and the vacant former Thomas Whitham accommodation provides opportunity to establish one.
The SEND sufficiency strategy also identifies the need for more special school places within Lancashire to meet rising demand for places and to meet various priorities under the strategy. Holly Grove Primary School is currently over- subscribed for pupils requiring places in the special school, and the opportunity to provide additional accommodation using former Thomas Whitham space will enable the school to increase the number of special school places it can provide. Following the phase one reorganisation of the educational partners on the campus and the Children and Family Wellbeing Service, a phase two review to address the impact on other services and to form a plan for the remaining accommodation is required.
Phase one of the Burnley Campus review sets out a reconfiguration of accommodation in order to meet these strategic requirements. An overview of the phase 1 reconfiguration and associated cost estimates is set out within the report.
This is deemed to be a Key Decision and the provisions of Standing Order C20 have been complied with. Compliance with Standing Order C19 was impractical as the project has expanded from that originally envisaged which, in turn, has impacted on the cost. The reason for this is that agreement needed to be reached with multiple stakeholders and further works are now required under phase 1 to future proof phase 2 works at the campus.
Recommendation
Cabinet is asked to:
(i) Approve the review of Burnley Campus, Phase 1.
(ii) Approve the relocation of Reedley Hallows Nursery and Reedley Hallows Children and Family Wellbeing Service to part of the former Thomas Whitham accommodation.
(iii) Approve the provision of additional places, for one year only in 2021, at Barden Primary School, through the addition of one classroom to the school.
(iv) Approve the provision of a Special Educational Needs unit for Barden Primary School, located within the former Thomas Whitham accommodation.
(v) Approve the provision of additional accommodation for Holly Grove Special School, increasing the building capacity by using the vacated Reedley Hallows nursery accommodation. This will allow the number of pupils to be increased in the future via further cabinet report.
(vi) Approve the capital expenditure detailed in Appendix 'A' to deliver phase 1.
Background and Advice
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies