That The Department for Transport 2023/24 Integrated Transport grant of £6.101 million be added to the Transport Block of the Capital Programme; The proposed apportionment of the 2023/24 Department for Transport Integrated Transport Grant as detailed in the report and at Appendix 'A' of the report, be approved; and The proposed 2023/24 New Starts Road Safety, Cycle Safety and Public Rights of Way programmes set out as projects at Appendices 'B' to 'D' of the report, be approved.
Word for word from the decision Lancashire & Rossendale published for this meeting.Source: council.lancashire.gov.uk
(i) Approve that the Department for Transport 2023/24 Integrated Transport grant of £6.101 million be added to the Transport Block of the Capital Programme.
(ii) Subject to approval at (i) above, approve the proposed apportionment of the 2023/24 Department for Transport Integrated Transport Grant as detailed in the report and at Appendix 'A'.
(iii) Subject to such approval of apportionments in (ii) approve the proposed 2023/24 New Starts Road Safety, Cycle Safety and Public Rights of Way programmes set out as projects at Appendices 'B' to 'D'. Detail
In March 2022 the Department for Transport confirmed that the Integrated Transport annual capital allocation would be £6.101m per annum until 2024/25. It is proposed that the 2023/24 funding is allocated as detailed at Appendix 'A'.
The proposed 2023/24 New Start Road Safety, Cycle Safety and Public Rights of Way programmes set out as projects are detailed at Appendices 'B', 'C' and 'D' respectively.
Consultations
N/A
Implications:
This item has the following implications, as indicated:
Risk management
It should also be noted that the delivery of the proposed programmes/projects is dependent on the 2022/23 transport programme outturn position which will not be known until spring 2023. The programmes may be subject to change after this date when the revised delivery programme is reported to Cabinet. It is anticipated that the delivery of the schemes in the attached appendices may not be delivered in full in 2023/24 due to timescales for design and consultations where required and this will again be reported in revised delivery programme.
Furthermore, there is a risk that some of the detailed projects set out at Appendices 'B' to 'D' may not be delivered or could be delayed due to changes to estimated costs, other priorities emerging within year because of bad weather or other unforeseen circumstances. Any changes required to the programmes will be reported as above in the revised delivery programme.
The annual contributions in this programme reflect the individual approvals to City Deal and South Lancaster growth catalyst and the use of the funds within those programmes are the subject of separate programme reporting reflecting the different maturity stages of those programmes and the different funding regimes with in them.
Financial
It is proposed that the programmes detailed at Appendices 'B' to 'D' be funded from the 2023/24 Integrated Transport grant funding from the Department for Transport with a value of £6.101 million and the schemes within the programme will be reduced accordingly to fit within the grant available, therefore there is no commitment to additional borrowing required for this programme. List of Background Papers
Paper Date Contact/Tel
None
Reason for inclusion in Part II, if appropriate
N/A
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.