Capital Strategy for Schools – Condition Led Capital Investment Programme 2025/26

Approved Executive 2 papers

Cabinet approved this item on Thursday 16 January 2025. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

That i. The proposed list of maintenance schemes in Lancashire schools, as detailed at Appendix 'A' of the report, totalling £13.999m, be approved as a further phase of high priority school repairs, subject to the grant settlement for 2025/26 being £14m; and ii. The Director of Finance and Commerce be authorised, in consultation with the Executive Director for Education and Children's Services and the Cabinet Member for Education and Skills, to approve any necessary adjustments to the programme once the final funding settlement is announced.
Word for word from the decision Lancashire & Rossendale published for this meeting. Source: council.lancashire.gov.uk

Follow this further

Built from Lancashire & Rossendale's papers

What the report saysPro

Report to Cabinet

Summary

Purpose of the report

This report sets out the proposals for the allocation of schools capital funding to address a further phase of high priority building condition repairs on Community, Voluntary Controlled and Maintained Schools in Lancashire.

The condition programme is funded by a grant from the Department for Education. Allocations are usually announced in April, and previous year's allocations indicate that approximately £14m should be received in 2025/26.

The programme, set out at Appendix 'A', has been developed to utilise this grant funding allocation. Once the amount is announced, the programme will be adjusted accordingly.

This is deemed to be a Key Decision and the requirements of the council's Cabinet procedure rules (Standing Order C18, Consideration of Key Decisions) have been complied with.

Recommendation

Cabinet is asked to approve:

(i) The proposed list of maintenance schemes in Lancashire schools, detailed at Appendix 'A', totalling £13.999m, as a further phase of high priority school repairs, subject to the grant settlement for 2025/26 being £14m.

(ii) That the Director of Finance and Commerce, in consultation with the Executive Director for Education and Children's Services and the Cabinet Member for Education and Skills, be authorised to approve any necessary adjustments to the programme once the final funding settlement is announced.

Background

1. The Schools Condition Led Programme began in 2011. Using Department for Education grant monies, each round of the programme has addressed the worst condition issues that have been identified. Reviewing the asset management building condition data held by the county council, officers have prepared a programme of highest priority works, which are set out at Appendix 'A'.

2. The aim of the programme is to address the highest priority building condition repairs, compliance, and health and safety issues on Community, Voluntary Controlled and Maintained Schools in Lancashire.

3. The programme has been formulated using the most current information available. From experience on earlier programmes and the complexities of assessing the condition of existing buildings, there could be a risk that further Priority 1 works may become apparent. A contingency is recommended, which will be available to cover any further justifiable Priority 1 projects which become known during the delivery of programme.

4. Variations to the programme will be approved in accordance with the Scheme of Delegation to Officers, Capital Sub-Group and Cabinet in accordance with the financial regulations and any authorisations in place.

5. The criteria for schools being included in the programme is based on the Department for Education Schools Asset Management Guidance which defines Schools highest Priority 1 works as:

6. Priority 1. Urgent work that will prevent immediate closure of premises and/or address an immediate high risk to the health and safety of occupants and/or remedy a serious breach of legislation.

7. The Department for Education provides annual funding for Schools Condition. This is based on a set methodology for county council controlled schools. Due to the finite budget, it would not be possible to address all high priority works in all schools. The remaining high priority works will be reviewed and considered for any future condition led programmes.

Specialist surveys and investigations

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Strategy for Schools: Condition Led Capital Investment Programme 2025/26Report 157 KB DownloadRead as text
PDF
View item 7. as DOC 194 KBReport 6 pages Download

At this meeting

Whole meeting

Who was there

10 of 21 attended
CP
CC P Williamson Leader of the County CouncilChair, present
CA
CC A Vincent Cabinet Member for Resources, HR and Property (Deputy Leader)Deputy Chair, present
CP
CC P Buckley Cabinet Member for Community and Cultural ServicesCommittee Member, present
CG
CC G Gooch Cabinet Member for Adult Social CareCommittee Member, present
CM
CC M Green Cabinet Member for Health and WellbeingCommittee Member, present
CJ
CC J Rear Cabinet Member for Education and SkillsCommittee Member, present
CA
CC A Riggott Cabinet Member for Economic Development and GrowthCommittee Member, present
CR
CC R Swarbrick Cabinet Member for Highways and TransportCommittee Member, present
CC
CC C Towneley Cabinet Member for Children and FamiliesCommittee Member, present
CS
CC S Turner Cabinet Member for Environment and Climate ChangeCommittee Member, present
CC
County Councillor Matthew TomlinsonCounty Councillor In Attendance, in attendance
CJ
CC J MeinCounty Councillor In Attendance, in attendance

All 21 on the meeting page

On this subject at Lancashire & Rossendale

Search all
  1. Capital Strategy for Schools – Condition Led Capital Investment Programme 2025/26This decision
  2. Capital Strategy for Schools – Condition Led Investment Programme 2026/27Approved
  3. Education Capital StrategyApproved
  4. Capital Strategy for Schools – Condition Led Capital Investment Programme 2024/25Approved
  5. Capital Strategy for Schools – Condition Led Capital Investment Programme 2023/24Approved
  6. Capital Strategy for Schools - Condition Led Capital Investment Programme 2022/23Approved

More from Lancashire & Rossendale Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 Minutes of the Meeting held on 2 July 2026That the minutes of the meeting held on 2 July 2026 be confirmed as a correct record and signed by the Chair. Decided Open
3 Sep 2026 Quarter 1 2026/27 Corporate Performance ReportThat, following consideration of the performance of the Council in Quarter 1 of 2026/27 against the ambitions set out... Noted Open
3 Sep 2026 2026/27 Quarter 1 Financial Monitoring ReportThat i. The current forecast Revenue Budget overspend at Quarter 1 of £15.655m (1.18%), as detailed in Appendix 'A' o... Noted Open
3 Sep 2026 Ofsted Inspection of Lancashire Children's ServicesThat, following consideration of the outcome of the inspection, which confirmed that Lancashire's Children's Services... Approved Open
3 Sep 2026 SEND Capital ProjectThat i. Following consideration of the positive consultation responses, the prior approval of those projects through ... Approved Open