Lancashire County Council / Rossendale Borough Council
Cabinet, Thursday 6 February 2025 at 2.00pm

2024/25 Quarter 3 Financial Monitoring Report

Approved Executive 6 papers

Cabinet approved this item on Thursday 6 February 2025. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

That, following consideration of the current forecast overspend of £12.737m on the revenue budget in 2024/25 and the forecast revenue expenditure of £1,124.490m, the current forecast of capital expenditure of £200.697m for 2024/25 and the changes described in Appendix 'B' of the report, be approved.
Word for word from the decision Lancashire & Rossendale published for this meeting. Source: council.lancashire.gov.uk

Follow this further

Built from Lancashire & Rossendale's papers

What the report saysPro

Report to Cabinet

Summary

Purpose of the report

This report provides an update to Cabinet on the county council's 2024/25 revenue and capital financial position, as at the end of Quarter 3.

The forecast outturn position is an overspend of £12.737m which is a reduction of £4.338m from the position predicted at Quarter 2 following further mitigating actions. Actions are continuing throughout Quarter 4 to try to further improve the position.

The forecast outturn for capital delivery programme for 2024/25 is £200.697m which is an underspend of £2.542m (1.25%) on the planned programme.

Recommendation

Cabinet is asked to:

(i) Consider the current forecast overspend of £12.737m on the revenue budget in 2024/25 and the forecast revenue expenditure of £1,124.490m.

(ii) Approve the current forecast of capital expenditure £200.697m for 2024/25 and the changes described in Appendix B. Background

2024/25 Revenue Position as at 30 November 2024 (Appendix 'A')

1. The county council, like other local authorities, continues to face unprecedented financial challenges. Whilst there is a strong track record of delivering savings and managing budgets, the 2024/25 in-year position is particularly challenging. The main pressures are across demand led budgets, where we continue to see growth and inflationary increases in addition to the requirement to deliver significant savings.

2. At Quarter 3, the revenue budget for 2024/25 is predicted to overspend by £12.737m, a reduction of £4.38m compared to the position at Quarter 2. The major factor for this improved position is because of changes to the Adult Services position. Whilst the underlying cost pressures and challenges to delivering the significant savings remain, positive actions have reduced the forecast by £5.277m.

3. A summary of the forecast position at Quarter 3 is shown in Table 1 below. Detailed analysis of each area is presented in Appendix 'A'.

Table 1 – Forecast Q3 Outturn Position for 2024/25

Quarter 3 Quarter 3 Quarter 3 Q2 Net Net Net Change Service Area Net Budget Forecast Forecast Forecast Forecast from Q2 Variance Outturn Variance Variance £m £m £m % £m £m Adult Services 469.835 491.643 21.808 4.64% 27.085 -5.277 Education and Children's 256.090 257.506 1.416 0.55% 2.133 -0.717 Services Growth, Environment, 194.948 194.982 0.034 0.02% -1.568 1.602 Transport & Health

Resources & Chief Executive 138.832 128.939 -9.893 -7.12% -10.651 0.758 Services

Corporate 52.049 51.421 -0.628 1.21% 0.076 -0.704 Budgets

Grand Total 1,111.754 1,124.490 12.737 1.15% 17.076 -4.338

4. The Executive Leadership Team has focussed on the overall financial position throughout the year. Mitigation and recovery plans were introduced and continued to be monitored. Given the budget position that is forecast for 2024/25 (and the potential impact on the 2025/26 budget and beyond) there have been detailed "special" meetings of the Executive Leadership Team to both review the in-year forecast and progress against delivery of savings. In addition, all Directorates have reviewed their expenditure forecasts and commitments and have revised forecasts, accordingly, reflecting the financial pressures that are faced in the 2024/25 financial year.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2024/25 Quarter 3 Financial Monitoring ReportReport 226 KB DownloadRead as text
PDF
Appendix AAppendix A 411 KB Download
PDF
Appendix BAppendix B 317 KB Download
PDF
View as DOCX (6./2) 463 KBAppendix 10 pages Download
PDF
View as DOCX (6./3) 1 MBAppendix 10 pages Download
PDF
View item 6. as DOC 210 KBReport 7 pages Download

At this meeting

Whole meeting

Who was there

10 of 16 attended
CP
CC P Williamson Leader of the County CouncilChair, present
CA
CC A Vincent Cabinet Member for Resources, HR and Property (Deputy Leader)Deputy Chair, present
CP
CC P Buckley Cabinet Member for Community and Cultural ServicesCommittee Member, present
CG
CC G Gooch Cabinet Member for Adult Social CareCommittee Member, present
CM
CC M Green Cabinet Member for Health and WellbeingCommittee Member, present
CJ
CC J Rear Cabinet Member for Education and SkillsCommittee Member, present
CA
CC A Riggott Cabinet Member for Economic Development and GrowthCommittee Member, present
CR
CC R Swarbrick Cabinet Member for Highways and TransportCommittee Member, present
CC
CC C Towneley Cabinet Member for Children and FamiliesCommittee Member, present
CS
CC S Turner Cabinet Member for Environment and Climate ChangeCommittee Member, present
CC
County Councillor Matthew TomlinsonCounty Councillor In Attendance, in attendance
CJ
CC J MeinCounty Councillor In Attendance, in attendance

All 16 on the meeting page

On this subject at Lancashire & Rossendale

Search all
  1. 2024/25 Quarter 3 Financial Monitoring ReportThis decision
  2. 2026/27 Quarter 1 Financial Monitoring ReportNoted
  3. 2026/27 Quarter 1 Financial Monitoring Report (Including Capital Review)Decided
  4. 2025/26 Quarter 3 Financial Monitoring ReportNoted
  5. 2025/26 Quarter 1 Financial Monitoring ReportNoted
  6. 2024/25 Quarter 3 – Financial Monitoring ReportNoted

More from Lancashire & Rossendale Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 Minutes of the Meeting held on 2 July 2026That the minutes of the meeting held on 2 July 2026 be confirmed as a correct record and signed by the Chair. Decided Open
3 Sep 2026 Quarter 1 2026/27 Corporate Performance ReportThat, following consideration of the performance of the Council in Quarter 1 of 2026/27 against the ambitions set out... Noted Open
3 Sep 2026 2026/27 Quarter 1 Financial Monitoring ReportThat i. The current forecast Revenue Budget overspend at Quarter 1 of £15.655m (1.18%), as detailed in Appendix 'A' o... Noted Open
3 Sep 2026 Ofsted Inspection of Lancashire Children's ServicesThat, following consideration of the outcome of the inspection, which confirmed that Lancashire's Children's Services... Approved Open
3 Sep 2026 SEND Capital ProjectThat i. Following consideration of the positive consultation responses, the prior approval of those projects through ... Approved Open