Resolved
That The amended 2025/26 Revenue Budget, be approved; The amended 2025/26 Capital Programme, be approved; and The expenditure commitments made to date against these budgets, be noted.
Lancashire Combined County Authority approved this item on Tuesday 17 June 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
That The amended 2025/26 Revenue Budget, be approved; The amended 2025/26 Capital Programme, be approved; and The expenditure commitments made to date against these budgets, be noted.
To provide an update on the LCCA 2025/26 Revenue budget and Capital Programme including new grant allocations and expenditure commitments.
The Lancashire Combined County Authority is asked to:
(i) Approve the amended 2025/26 Revenue Budget. (ii) Approve the amended 2025/26 Capital Programme; and (iii) Note the expenditure commitments made to date against these budgets.
Section 2 - Background
1. The Revenue Budget and Capital Programme for the Lancashire Combined County Authority (LCCA) was originally set at the inaugural meeting on 11th March 2025. This is the Approved Budget. 2. Since March there have been significant changes to some of the assumptions made, both in terms of monies to be received by LCCA and expenditure needed to be incurred. These now necessitate changes to be made to the Approved budget as included in the report below.
Income
3. At the meeting of the LCCA on 24th April 2025 the following grants were approved to be received by the LCCA: a. Bus Service Improvement Plan - Revenue £19,127,824 and Capital £17,470,799 b. Combined Active Travel Fund – Revenue £1,286,455 and Capital £4,073,774 c. Integrated Transport Grant - Capital £9,269,000 d. Local Transport Grant – Revenue £1,349,000 and Capital £ 34,945,000 e. Rural Prosperity Fund – Capital £653,065
4. These grants are currently only awarded for one year and are not annual recurring amounts at this stage.
5. There has also been an award of £100,000 received by LCCA from the Department for Education (DfE) as a capacity fund to allow the Lancashire Skills Hub to prepare the Get Lancashire Working plan. This was accepted by officers due to the timescales to undertake the work on the plan.
Expenditure
6. Expenditure commitments made since the LCCA Budget was approved are detailed below: a. £28,620 for insurance premiums required by the LCCA. b. £25,000 for Careers Hub Match funding - the Skills Hub requested this to replace funding previously provided by the Lancashire enterprise Partnership and which adds to funding provided by LCC Blackpool and Blackburn councils. c. £10,000 for Employment Consultants to support the LCCA Chief Operating Officer Recruitment process. d. The Chief Operating Officer has been appointed on a seconded basis to start on 16th June 2025. e. £31,025 for expenditure at UKREiiF. There will be £14,000 of contributions to offset this so the ask of the LCCA budget is the net expenditure of £ 17,025. f. £20,103 for consultants working on developing the Lancashire Growth Plan and prioritising the pipeline of investment projects contained within the Growth Plan.
7. It is also thought necessary to increase the budget provision for the Governance review from the £50k already approved to £75k in accordance with revised resources estimates.
8. In addition a proposal for £50,000 to support the Lancashire Business Board connect with the business community, is included for approval elsewhere on this agenda. Virements
9. The expenditure committed above along with other expected costs has been reviewed along with the assumptions contained in the original budget proposals in March 2025. Considering this some budget headings need to be increased and the contribution to reserves reduced by £75,000 to accommodate this.
Revenue
10. The new Revenue Budget for 2025/26 being proposed by function and activity are as below:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Finance/Funding Update: June 2025Report | 110 KB | DownloadRead as text |
PDF |
View item 9. as DOC 148 KBReport | 3 pages | Download |
Follow Lancashire Combined County Authority at Lancashire & Rossendale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | Minutes of the meeting held on 23 June 2026That the minutes of the meeting held on 23 June 2026 be confirmed as a correct record and signed by the Chair. | Decided | Open |
| 8 Sep 2026 | Governance Review/Future DevolutionThat the update be noted. | Noted | Open |
| 8 Sep 2026 | Employment Matters - Appointment of the Chief Finance OfficerThat Gary Fielding be appointed as the Chief Finance Officer (Section 73 Officer) of the LCCA. | Decided | Open |
| 8 Sep 2026 | Transport Delivery Plan and Implementation UpdateThat i. The Local Transport Delivery Plan be submitted to the Department for Transport covering the period 2026/27 to... | Noted | Open |
| 8 Sep 2026 | Lancashire Spatial Development Strategy UpdateThat, following consideration of the Lancashire Spatial Development Strategy, the updates on preparatory and enabling... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.