AI summaryLancashire Combined County Authority endorses Spatial Development Strategy preparatory work, including a planning ecosystem diagram, indicative timelines and proposed new governance groups, ahead of an expected autumn 2026 statutory start.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedThree appendices endorsed by the LCCA
Money£765,071 plus £9,601.87MHCLG grant MoU and PropTech 6 award to LCCA
What happens nextFormal SDS timetable early 2027Due around 3 months after statutory commencement
Who it affectsLancashire councils, residents, developersAnd statutory and infrastructure stakeholders across the county
What was decided
The LCCA endorsed updates on SDS preparatory and enabling works, including the Planning Ecosystem diagram at Appendix A, indicative SDS and Local Plan timetables at Appendix B, and emerging governance arrangements at Appendix C. Report P3, P4, P5
Interim resource arrangements through the SDS Interim Joint Officer Working Group, currently around 1.2 Full Time Equivalent, are to continue rather than pausing work. Report P15, P16, P41
A resourcing plan to establish a permanent core Strategic Planning Team within the LCCA has been agreed and will be kept under review. Report P15, P16
Why
The Government announced a delay in May 2026 to the commencement of the new SDS provisions and associated regulations, now expected in autumn 2026, to allow consideration of the revised National Planning Policy Framework and consolidation of SDS regulations. Report P8, P9, P10
A pause in interim working was rejected because significant governance and scoping work is still required before publishing a formal timetable, and a temporary stop would risk missing the early 2027 timetable deadline. Report P41
A clear governance framework is needed given the complexity of the Lancashire planning ecosystem, which includes Local Plans, Minerals and Waste Local Plans, Neighbourhood Plans, new planning reforms and Local Government Reorganisation. Report P29, P32, P36
What happens next
Continue the four SDS preparatory workstreams: resourcing and governance, early engagement, evidence base, and digital and technical services. Report P13, P14, P18, P22, P25
Establish new governance groups, including an SDS Strategic Oversight Group, an LCCA Strategic Infrastructure Group, an SDS Advisory Board, an LCCA Data Observatory Group and a Citizens Panel, with terms of reference to be agreed. Report P38, P39
Produce a Risks, Assumptions, Issues and Decisions log and await the Government's full SDS funding package announcement, expected in autumn 2026 alongside commencement. Report P12, P54
The money
£765,071 MHCLG grant Memorandum of Understanding authorised by the LCCA Section 73 Officer for SDS preparation Report P49
£9,601.87 PropTech 6 consortium award to the LCCA for the digital end-to-end SDS Hub project Report P27, P49
Options considered
Chosen: Continue existing interim resource and preparatory workstreams. A pause would risk meeting the early 2027 timetable deadline, and significant governance and scoping work is still required Report P41
Rejected: Temporarily pause SDS preparatory and enabling works. Would risk meeting the Government timetable expected in early 2027 Report P41
Implications
Legal: The statutory duty on the LCCA to prepare an SDS becomes operative only when the relevant commencement provisions and SDS Regulations come into force, expected in autumn 2026; the Secretary of State has reserve intervention powers. Report P46, P47
Financial: Current funding is interim only; a full funding package to support SDS preparation up to the end of March 2029 is expected to be announced in autumn 2026, with a future report to set out expected costs and a timeline of spend. Report P12, P49, P50
Staffing: An agreed resourcing plan will establish a permanent core Strategic Planning Team within the LCCA, to be kept under review in light of Local Government Reorganisation and further devolved powers. Report P15, P16
Risk: A Risks, Assumptions, Issues and Decisions log will be produced and updated, with risks recorded and monitored under the LCCA risk management framework and potentially escalated to the corporate risk register. Report P54
Equalities: No equality and diversity implications have been identified for the recommendations, with further consideration to be built into an integrated sustainability appraisal as the SDS develops. Report P52, P53
Other: Local Government Reorganisation will create four new unitary authorities in Lancashire from 1 April 2028, replacing the existing 15 districts and unitaries, requiring new Local Plans for the new unitary footprints. Report P32, P34
Who and where
Lancashire Combined County Authority, as the future strategic planning authority Report P46
The 15 existing Lancashire district and unitary councils, due to be replaced by four new unitary authorities from 1 April 2028 Report P32
Neighbouring strategic planning authorities and statutory and infrastructure stakeholders Report P21
Residents and other interested parties, through the new SDS webpage and forthcoming Citizens Panel Report P21, P38
Developers and applicants, since Local Plans must conform with the adopted SDS Report P56
Timeline
26 March 2026: Town and Country Planning (Local Planning) (England) Regulations 2026 came into force Report P32
Autumn 2026: Expected commencement of SDS provisions and related regulations, and announcement of the full SDS funding package Report P8, P12
Early 2027: Government expected to require submission of the LCCA's formal SDS timetable, around 3 months after commencement Report P11, P41
Early 2027: End of the PropTech 6 digital end-to-end SDS Hub project Report P27
17 August 2026: Revised National Planning Policy Framework published Report P10
1 April 2028: Local Government Reorganisation vesting day for four new Lancashire unitary authorities Report P32, P34
End of March 2029: End of the period expected to be covered by the full Government SDS funding package Report P12
Plain English for the jargon
SDS: Spatial Development Strategy, the strategic planning document the LCCA will prepare
LCCA: Lancashire Combined County Authority
JOWG: SDS Interim Joint Officer Working Group of officers from the three constituent authorities
FTE: Full Time Equivalent, a measure of staffing capacity
LGR: Local Government Reorganisation creating four new Lancashire unitary authorities
NPPF: National Planning Policy Framework
MHCLG: Ministry of Housing, Communities and Local Government
PropTech 6: Sixth round of the Government's PropTech Innovation Fund, supporting digital planning tools
RAID: Risks, Assumptions, Issues and Decisions project management log
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7
Resolved
That, following consideration of the Lancashire Spatial Development Strategy, the updates on preparatory and enabling works for Lancashire's Spatial Development Strategy be endorsed, including: i. The Spatial Development Strategy planning ecosystem diagram as set out at Appendix 'A' of the report; ii. The indicative Spatial development Strategy and Local Plan timetables as set out at Appendix 'B' of the report; and iii. The emerging governance arrangements as set out at Appendix 'C' of the report.
Word for word from the decision Lancashire & Rossendale published for this meeting.Source: council.lancashire.gov.uk
This report provides an update on matters relevant to Lancashire's Spatial Development Strategy (SDS) preparation, including:
• key policy and legislative changes; • progress on SDS preparatory and enabling workstreams; • details on the SDS planning ecosystem, current indicative SDS/Local Plan timelines, and proposed SDS governance;
Recommendation
The Lancashire Combined County Authority is asked to consider and endorse the updates on preparatory and enabling works for Lancashire's Spatial Development Strategy, including: (i) The Spatial Development Strategy planning ecosystem diagram as set out at Appendix 'A';
(ii) The indicative Spatial development Strategy and Local Plan timetables as set out at Appendix 'B';
(iii) The emerging governance arrangements as set out at Appendix 'C'.
Section 2 - Background
Spatial Development Strategy Policy and Legislative Updates
1. In May 2026 the Government announced a delay to the commencement of the new Spatial Development Strategy (SDS) provisions (set out in the Planning and Compulsory Purchase Act 2004 and summarised in the report on the SDS inception to April’s LCCA meeting (available to view here) , and the laying of associated SDS regulations. These are now expected in autumn 2026.
2. The delay allows for:
i. consideration of the revised National Planning Policy Framework (NPPF) which was published on 17 August 2026. This will allow for relevant impacts to be considered in the preparation and publication of SDS guidance (currently being drafted by Government); ii. adequate time for consolidation of all SDS provisions into a single set of regulations. Additional provisions have been added during the final passage of the English Devolution and Community Empowerment Act 2026; and iii. clarification/decisions on SDS geographies nationally, and for these to be concluded at the point of formal commencement of the system.
3. The statutory duty for the LCCA to prepare an SDS will formally commence once the relevant SDS regulations come into force. The first formal output required by the LCCA, the submission of an SDS timetable, is expected to be due around 3 months after commencement of the duty. As such it will now be early in 2027 before a clear timeframe for the preparation, submission and adoption of the SDS will be confirmed.
4. Alongside commencement of the SDS duty, it is expected that a full funding package for the LCCA to support SDS preparations up to the end of March 2029 will also be announced. The work underway with the preparation and enabling workstreams set out in April’s report is not currently impacted by these government delays. Spatial Development Strategy Preparatory and Enabling Works
5. April’s SDS Inception Report to the LCCA set out four key workstreams necessary to establish the right foundations for production of an SDS for Lancashire. An update on key progress against each is set out below.
Workstream 1 – resourcing/governance
6. Interim resource arrangements are continuing, via an SDS Interim Joint Officer Working Group (JOWG) comprising officers from the three constituent authorities. Currently, this equates to around 1.2 Full Time Equivalent (FTE). A resourcing plan has been agreed to establish a permanent, core Strategic Planning Team within the LCCA.
7. The resourcing plan will be kept under review, to take account of the need to ensure a flexible and responsive planning service given substantial impacts of Local Government Reorganisation and the prospect of further devolved powers.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Lancashire Combined County Authority at Lancashire & Rossendale and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.