AI summaryLancashire Cabinet approves expanding existing Preston secondary schools to address a projected shortfall, while keeping two new school sites under review for the longer term.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedInterim expansion of existing Preston secondary schools to proceed
MoneyUp to £41,000,000 estimatedEstimated costs in Table 7; current Basic Need grant insufficient
What happens nextFurther Cabinet reportDetailed and costed project plan to future Cabinet
Who it affectsPreston secondary school placesTen existing secondary schools and prospective new sites
What was decided
Cabinet approved progressing interim expansion options in existing Preston secondary schools to maintain the council's statutory sufficiency duty. Report P4
Cabinet agreed that due diligence should continue on the two previously named new school sites, the former Tulketh High School and Maxy Lane Farm. Report P5
Cabinet agreed that a further report with a detailed and costed project plan will be brought to a future Cabinet meeting. Report P6
Why
Forecast shows a shortfall of 2 forms of entry by 2026, rising to 3.5 by 2027 and 5 by 2031, and up to 8 to 9.5 forms of entry by the end of the draft Central Lancashire Local Plan period. Report P12, P13, P32, P34
Designing and delivering a new secondary school takes at least three years, so the council needed an interim solution to meet its statutory duty to provide sufficient places. Report P14, P62
Several existing schools rated Good or Outstanding have both the site capacity and willingness to expand by up to 3.5 forms of entry by 2027, making expansion more cost effective than a new build. Report P45, P53
What happens next
Officers will develop a feasibility and high-level cost plan for expanding existing secondary schools, with the Capital Programme for 2026 to 2029 to be agreed by Full Council. Report P55
Further statutory consultations on enlarging existing schools will be carried out under the Department for Education's Making Significant Changes guidance. Report P59, P63
A future Cabinet will decide whether to proceed with the expansions and whether to retain Tulketh for a future school or dispose of it, and whether to pursue Maxy Lane Farm for a school from 2031 onwards. Report P57
The money
£200,000 Housing developer contributions secured for the former Tulketh High School site Report P48
£3.8 million Section 106 funding secured in relation to the Maxy Lane Farm site Report P50
£32,000,000 Estimated cost for a new school at the former Tulketh High School Report P69
£41,000,000 Estimated cost for a new school at Maxy Lane Farm Report P69
£13,000,000 Estimated cost for potential expansions of up to four existing schools Report P69
Options considered
Chosen: Expand existing secondary schools to deliver up to 3.5 forms of entry by 2027. More cost effective, faster to deliver, several schools rated Good or Outstanding have capacity and willingness to expand; addresses short-term statutory duty. Report P45, P53
Rejected: Build a new secondary school at the former Tulketh High School. Site is council owned, cleared and ready, with £200,000 of developer contributions secured, but residents and nearby schools have raised concerns and the new school is not yet needed at scale. Report P48, P49
Rejected: Build a new secondary school at Maxy Lane Farm. Aligns with Northwest Preston Masterplan growth and £3.8 million Section 106 funding is secured, but the land is not yet in the council's ownership and there are unknown ground and access conditions. Report P50, P51
Implications
Legal: The county council has a statutory duty under section 14 of the Education Act 1996 to provide sufficient school places; any enlargement of a maintained school must follow the statutory process under section 18 of the Education and Inspections Act 2006. Report P62, P63
Financial: Current Department for Education Basic Need Grant is not enough to fully fund a new school without borrowing; borrowing has been approved from February 2025 to augment the Schools Block of the Capital Programme, with the final level to be set once all projects are costed. Report P65, P66
Risk: Not proceeding risks insufficient school places, potential failure of statutory duty and reputational damage; relying only on expansion could exhaust remaining headroom and leave a future shortfall. Report P46, P72
Equalities: The proposal affects the age (young people) protected characteristic group and may affect other groups under the Equality Act 2010, with the aim of advancing equality of opportunity through increased provision. Report P74
Who and where
Secondary school age pupils and their families in the Preston planning area Report P20, P74
The ten existing secondary schools in Preston, including the two community schools, Broughton High School and Ashton Community Science College Report P20
Residents near the former Tulketh High School and Maxy Lane Farm sites, who have raised highways, transport and other concerns Report P16, P49
The existing sports facility tenant at the Tulketh site, We Play Football, who would require compensation Report P49
Headteachers, governing bodies, academy trusts and diocesan authorities of the schools being considered for expansion Report P45, P56
Timeline
2018: Shortfall of secondary school places identified in Preston and expressions of interest sought from local schools Report P7
September 2020/2021: Bulge year delivered at Ashton Community Science College and Preston Muslim Girls School increased its Published Admission Number by 20 places Report P7
October 2022: Cabinet approved the Basic Need Delivery Plan 2023 to 2025, identifying a need for up to 5 forms of entry by 2025/2026 Report P8
12 December 2022 to 22 January 2023: Statutory Stage 1 consultation on a new secondary school at the former Tulketh High School site Report P59
December 2023: Legal agreement for the Maxy Lane Farm secondary school site was finalised Report P17
2026/2027: Projected shortfall of 2 forms of entry in Preston secondary places Report P34
By September 2027: Interim expansions aim to deliver 3.5 forms of entry, and temporary accommodation could potentially be available at the Tulketh site subject to planning and modular unit availability Report P43, P48
2031/2032: Projected shortfall rises to 5 forms of entry in Preston Report P34
By 2035: Draft Central Lancashire Local Plan projections indicate a need for 8 forms of entry, rising to 9.5 by the end of the plan period Report P13
Plain English for the jargon
Form of entry (FE): A measure of school capacity equal to 30 pupils per year group, used to compare school size.
Published Admission Number (PAN): The number of pupils a school intends to admit in each year group, set under the School Admissions Code.
Basic Need Grant: Department for Education funding provided to local authorities to help create new school places where they are needed.
Section 106 agreement: A planning obligation under which a developer provides funding or land for local infrastructure, such as schools, to mitigate the impact of a development.
Bulge year: A temporary increase in a school's pupil capacity to meet a one-off rise in applications, rather than ongoing growth.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11
Resolved
That The progression of the interim expansion options in existing secondary schools to address the present shortfall in secondary school places in Preston to ensure statutory sufficiency duties were maintained, be approved. Due diligence on the two previously named secondary school sites, the former Tulketh High School and Maxy Lane Farm, be continued to be progressed; and A further report be submitted to a future Cabinet meeting with a detailed and costed project plan.
Word for word from the decision Lancashire & Rossendale published for this meeting.Source: council.lancashire.gov.uk
This report provides an update to the delivery of secondary school places in Preston in response to a projected shortfall.
This is deemed to be a Key Decision and the requirements of the council's Cabinet procedure rules (Standing Order C18, Consideration of Key Decisions) have been complied with.
Recommendation
Cabinet is asked to:
(i) To approve the progression of the interim expansion options in existing secondary schools to address the present shortfall in secondary school places in Preston to ensure statutory sufficiency duties are maintained.
(ii) To continue to progress the due diligence on the two previously named secondary school sites, the former Tulketh High School and Maxy Lane Farm.
(iii) Subject to recommendation (i) above, agree that a further report will be submitted to a future Cabinet meeting with a detailed and costed project plan. Background
1. In 2018 a shortfall of secondary school places was identified in Preston. Officers met with the local schools, and, at the time, the preferred solution was to expand existing provision. Expressions of interest were sought from the local secondary schools. Whilst seeking to mitigate the deficit, and following an update of the 2020/2021 forecasts, it was decided that the shortfall could be accommodated through a bulge year, where existing secondary schools are asked to temporarily expand their pupil capacity to meet increased pupil numbers applying to a group of schools (not based on growth due to popularity). This was delivered at Ashton Community Science College, for the academic year September 2020/2021. In addition, Preston Muslim Girls school increased their Published Admission Number by 20 places, providing 120 Year 7 places for 2020/2021. This ensured sufficient provision of secondary school places across Preston.
2. In October 2022, Cabinet approved the Basic Need Delivery Plan 2023-2025, which indicated a requirement for up to an additional 5 forms of entry (equivalent to 750 secondary school places) in Preston by 2025/2026.
3. In response, the county council commenced a statutory proposal to establish a new secondary school at the former Tulketh High School site. The county council were also progressing a secondary school site option at Maxy Lane Farm, as part of the Northwest Masterplan.
4. In the interim period, between 2023 and 2025, additional places were provided at existing schools to address the projected 5 forms of entry shortfall. These additional places were provided in Preston, with 2.5 forms of entry at Archbishop Temple CE High School and Christ the King Catholic High School, and in the neighbouring planning area of Longridge, where a 1.5 form of entry expansion was delivered at Longridge High School and a 0.5 form of entry at St Cecilia's RC High School; in total providing a further 715 additional secondary school places.
5. In addition to these expansion projects additional places were also provided in South Ribble secondary schools. Although adjoining planning areas have been used as a solution to the provision of secondary school places for Preston children, the scale of projected demand means that this approach is not a long-term solution to school place sufficiency.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.