Supplementary Procurement Report

Approved Executive 4 papers

AI summaryLancashire County Council Cabinet approves starting six procurement exercises covering construction, lighting, water safety, security and vehicle parts.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedSix contracts to be put out to tender
MoneyNot stated in reportEstimated values are in Appendix A, not supplied
What happens nextTendering to beginAwards to be made by officers under delegated powers
Who it affectsPotential suppliers and biddersAcross property, highways, facilities and fleet

What was decided

Cabinet approved the start of procurement for six contracts: professional services for a condition-led programme, construction of the Samlesbury Enterprise Zone Innovation Hub, LED road lighting lanterns, legionella services, manned guarding and front-of-house security, and vehicle parts. Report P1, P2, P5, P6

Any contract award at the end of the process will be made under section 9.52 (49) of the county council's Scheme of Delegation to Officers, not by Cabinet. Report P3

The decision is treated as a Key Decision and the Cabinet procedure rules on Key Decisions have been complied with. Report P4

Why

The county council's procurement rules require Cabinet to approve the start of procurement exercises of this kind. Report P1

An earlier Procurement Pipeline 2025/26 report approved by Cabinet on 6 March 2025 allowed further procurement reports for processes not identified when that plan was drawn up; this is one such report. Report P7, P8

The report says the circumstances and information on these processes were not known when the earlier plan was drafted. Report P8

What happens next

Procurement exercises for the six workstreams are to be run, with detail set out in Appendix A of the report. Report P9, P10, P12

If actual contract values vary significantly from the estimates in Appendix A, a further report to Cabinet will be required. Report P19

Risk mitigation will rely on precise specifications and contracts, use of multiple suppliers where appropriate, and a rigorous evaluation process. Report P22, P23

Options considered

  • Chosen: Approve commencement of the six procurement exercises. Required by the county council's procurement rules and the prior Procurement Pipeline 2025/26 approval Report P1, P5, P6, P7

Implications

  • Legal: Legal implications are addressed within the appendices, which are not included in the supplied papers. Report P16, P17
  • Financial: The maximum estimated value of the contracts will be contained within existing funding arrangements, as set out in Appendix A; significant variations would need a further Cabinet report. Report P18, P19
  • Equalities: Equality and diversity implications are considered within Appendix A, not supplied. Report P20, P21
  • Risk: Risks include failing to find a suitable bidder, procurement law challenges, and selecting an unsuitable supplier; mitigated through robust procedures, clear specifications, use of multiple suppliers and a rigorous evaluation. Report P22, P23

Who and where

  • Bidders and suppliers in construction, professional services, LED lighting, water safety, security and vehicle parts Report P1, P2
  • Council services that draw on condition-led maintenance, street lighting, water hygiene, building security and vehicle maintenance Report P1, P2
  • Samlesbury Enterprise Zone, as the planned Innovation Hub construction is one of the procurements Report P2

Timeline

  • 6 March 2025: Cabinet approved the original Procurement Pipeline 2025/26 report, which allowed for further procurement reports on items not known at the time Report P7
  • 2026-01-22: Cabinet considered this supplementary procurement report and approved the start of six new procurement exercises Report P4

Plain English for the jargon

  • Key Decision: An executive decision which is significant in terms of its effect on communities or the council, subject to specific procedure rules.
  • Procurement Pipeline 2025/26 report: A forward plan of key procurement decisions approved by Cabinet in March 2025, with provision for additional supplementary reports.
  • Scheme of Delegation to Officers: The county council's rules setting out which decisions officers may take on the council's behalf, here section 9.52 (49).
  • Condition Led Programme: A programme of works driven by the condition of assets rather than a fixed schedule, used here for property maintenance professional services.
  • Legionella Services: Services to control the risk of Legionella bacteria in water systems within council buildings.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

That the commencement of the procurement exercises for the following be approved: Professional Services for Condition Led Programme Construction of Samlesbury Enterprise Zone Innovation Hub Supply of LED Road Lighting Lanterns Supply of Legionella Services Manned Guarding, Front of House & Security Concierge Services Supply of Vehicle Parts
Word for word from the decision Lancashire & Rossendale published for this meeting. Source: council.lancashire.gov.uk

Follow this further

Built from Lancashire & Rossendale's papers

What the report saysPro

Report to Cabinet, 2 pages

Purpose of the report

In line with the county council's procurement rules, this report sets out a recommendation to approve the commencement of the following procurement exercises:

Professional Services for Condition Led Programme Construction of Salmesbury Enterprise Zone Innovation Hub Supply of LED Road Lighting Lanterns Supply of Legionella Services Manned Guarding, Front of House & Security Concierge Services Supply of Vehicle Parts

At the conclusion of the procurement process, any award of contract will be made under Section 9.52 (49) of the county council's Scheme of Delegation to Officers.

This is deemed to be a Key Decision, and the requirements of the council's Cabinet procedure rules (Standing Order C18, Consideration of Key Decisions) have been complied with. DOCPROPERTY issuedescriptionplain \* MERGEFORMAT

Recommendation

Cabinet is asked to approve the commencement of the following procurement exercises:

Professional Services for Condition Led Programme Construction of Salmesbury Enterprise Zone Innovation Hub Supply of LED Road Lighting Lanterns Supply of Legionella Services Manned Guarding, Front of House & Security Concierge Services Supply of Vehicle Parts

Background

On 6 March 2025, Cabinet received recommendations and approved the commencement of the procurement exercises in 2025/26 based on the forward plan of key decision procurement processes (Procurement Pipeline 2025/26 report). That same report envisaged that there may be procurement processes not identified in the planning process that would be subject to a 'further procurement report', submitted to Cabinet.

This supplementary procurement report is a further example of such a report. It is the case that the circumstances and the necessary information concerning these processes were not known at the time that the earlier report was drafted.

Appendix 'A' sets out the detail of the procurement exercises and basis upon which it is proposed to carry out the process including:

The description of the services. The procurement route proposed. The estimated contract value. The proposed basis for the evaluation of the tender submissions.

Options and Proposals

The options concerning the procurement exercises are considered within Appendix 'A'.

Consultations

The relevant heads of service and key operational staff have been consulted in drawing up the proposals contained within this report.

Context and Implications

Legal (including Human Rights)

Legal implications are considered within the Appendices.

Financial

The maximum estimated value of the contracts will be contained within the funding arrangements as set out in Appendix 'A'. If significant variations should result from this position, a further report to Cabinet will be required.

Equality and Diversity

Equality and Diversity implications are considered within Appendix 'A'.

Risk management

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 162 KB Download
PDF
Supplementary Procurement ReportSupplementary 135 KB Download
PDF
View as DOCX (12./2) 69 KBAppendix 13 pages Download
PDF
View item 12. as DOCX 82 KBReport 2 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 18 attended
CS
CC S Atkinson Leader of the County CouncilChair, present
CS
CC S Evans Deputy Leader & Cabinet Member for Children and FamiliesDeputy Chair, apologies
CG
CC G Mirfin Cabinet Member for Resources, HR and PropertyCommittee Member, present
CG
CC G Dalton Cabinet Member for Adult Social CareCommittee Member, apologies
CD
CC D Matchett Cabinet Member for Health and WellbeingCommittee Member, present
CM
CC M Salter Cabinet Member for Education and SkillsCommittee Member, present
CB
CC B Moore Cabinet Member for Economic Development and GrowthCommittee Member, present
CW
CC W Goldsworthy Cabinet Member for Highways and TransportCommittee Member, present
CJ
CC J Roberts Cabinet Member for Rural Affairs, Environment and CommunitiesCommittee Member, present
CD
CC D Dwyer Cabinet Member for Data, Technology, Customer and EfficiencyCommittee Member, present
CA
CC A AliCounty Councillor In Attendance, in attendance
CG
CC G DowdingCounty Councillor In Attendance, in attendance

All 18 on the meeting page

On this subject at Lancashire & Rossendale

Search all
  1. Supplementary Procurement ReportThis decision
  2. Supplementary Procurement ReportApproved
  3. Supplementary Procurement ReportApproved

More from Lancashire & Rossendale Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 Minutes of the Meeting held on 2 July 2026That the minutes of the meeting held on 2 July 2026 be confirmed as a correct record and signed by the Chair. Decided Open
3 Sep 2026 Quarter 1 2026/27 Corporate Performance ReportThat, following consideration of the performance of the Council in Quarter 1 of 2026/27 against the ambitions set out... Noted Open
3 Sep 2026 2026/27 Quarter 1 Financial Monitoring ReportThat i. The current forecast Revenue Budget overspend at Quarter 1 of £15.655m (1.18%), as detailed in Appendix 'A' o... Noted Open
3 Sep 2026 Ofsted Inspection of Lancashire Children's ServicesThat, following consideration of the outcome of the inspection, which confirmed that Lancashire's Children's Services... Approved Open
3 Sep 2026 SEND Capital ProjectThat i. Following consideration of the positive consultation responses, the prior approval of those projects through ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies