Bus Service Improvement Plan and Enhanced Partnership Arrangements
ApprovedCommittee6 papers
AI summaryLancashire Combined County Authority approved its draft bus improvement plan and enhanced partnership documents, paving the way for publication and to access bus services funding from 1 April 2026.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedBoth documents to proceed to stakeholder consultation
MoneyNot stated
What happens nextConsultation then publicationFinal documents to be published after consultation
Who it affectsBus users across Lancashire areaCovering Blackburn, Blackpool and Lancashire
What was decided
Members approved the draft Bus Service Improvement Plan at Appendix A, which sets out the vision, investment plans and targets for bus services in the area. Report P4, P8
Members approved the draft Enhanced Partnership Plan and Scheme at Appendix B, a legal agreement between the authority, bus operators and other parties. Report P4, P9
Authority was delegated to the Head of Paid Service, working with named directors at the three constituent councils, to give final approval and publish the documents after consultation. Report P5
Why
As the sole Local Transport Authority from 1 April 2026, the Combined County Authority needs a single Bus Service Improvement Plan and Enhanced Partnership to receive the Bus Services Fund under the new Local Transport Consolidated Funding Settlement. Report P2, P7
An Enhanced Partnership is required under sections 138A to 138S of the Transport Act 2000, with statutory duties to consult operators, user representatives, neighbouring authorities, the Traffic Commissioner and the Police. Report P21, P22
The new arrangements build on the existing shared plan covering Lancashire and Blackburn with Darwen, plus Blackpool's standalone plan, to reduce disruption and risk. Report P15, P30
What happens next
Formal stakeholder consultation on both documents will run for 28 days starting the week commencing 23 February 2026. Report P11, P12
The Bus Service Improvement Plan is due to be published the week commencing 6 April 2026, subject to feedback and approval. Report P11
The Enhanced Partnership is scheduled to go live on 1 April 2026, with a notice of intent to make it issued the week commencing 23 March 2026. Report P12
Options considered
Chosen: Approve the draft BSIP and Enhanced Partnership and delegate authority for final publication. Required to access Bus Services Fund and meet statutory duties from 1 April 2026 Report P7, P14, P21
Implications
Legal: The Enhanced Partnership carries statutory duties under sections 138A-S of the Transport Act 2000, including the operator objection mechanism in the 2018 Regulations. Report P21, P22, P23
Financial: Approving the documents creates no direct financial obligations; funding allocations are set out elsewhere on the agenda for 2026/27. Report P27
Equalities: The Department for Transport has stressed that accessibility and inclusion should be a key consideration in scheme design and implementation across the area. Report P29
Risk: Plans will be reviewed iteratively to take account of new Department for Transport guidance expected in Spring 2026, which will require updates to the Enhanced Partnership. Report P30
Other: Where the Bus Service Improvement Plan is delivered through the Enhanced Partnership, parts of it become legally binding, including on service standards, infrastructure and ticketing. Report P25
Who and where
Bus passengers across the Lancashire Combined County Authority area Report P8, P25
The three constituent councils: Lancashire County Council, Blackburn with Darwen Borough Council and Blackpool Council Report P2, P9
Highways authorities, with highways functions remaining with the constituent councils Report P9
Neighbouring local authorities, the Traffic Commissioner and the Police as statutory consultees Report P22
Timeline
26 November 2025: Request for stakeholder input and notice of intent to prepare Enhanced Partnership issued Report P11, P12
10 December 2025: Request for bus operator data issued Report P11, P12
18 December 2025: Informal engagement with bus operators opened Report P12
26 January 2026: Notice that the Enhanced Partnership has been prepared issued Report P12
26 January to 22 February 2026: Operator objections period for the Enhanced Partnership Report P12
w/c 23 February 2026: Wider formal stakeholder consultation begins, running for 28 days Report P11, P12
w/c 23 March 2026: Notice of intent to make the Enhanced Partnership to be issued Report P12
1 April 2026: Enhanced Partnership scheduled to go live, subject to feedback and approval Report P12
w/c 6 April 2026: Final Bus Service Improvement Plan scheduled for publication Report P11
before 14 April 2026: Notice that the Enhanced Partnership has been made to be issued Report P12
Plain English for the jargon
LCCA: Lancashire Combined County Authority
BSIP: Bus Service Improvement Plan, a strategy document sitting under the Local Transport Plan
EP: Enhanced Partnership, a legal agreement between the authority and bus operators
LTA: Local Transport Authority
DfT: Department for Transport
LTP: Local Transport Plan
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6
Resolved
That The draft Bus Service Improvement Plan at Appendix 'A' of the report, be approved; The draft Enhanced Partnership Plan and Scheme at Appendix 'B' of the report, be approved; and The Head of Paid Service be authorised in consultation with the Director of Highways and Transport (Lancashire County Council); Deputy Chief Executive (Blackburn with Darwen Borough Council); and Director of Communications and Regeneration (Blackpool Council) for final approval and publication of the Bus Service Improvement Plan and Enhanced Partnership and Scheme following stakeholder consultation.
Word for word from the decision Lancashire & Rossendale published for this meeting.Source: council.lancashire.gov.uk
The purpose of the report is to present the Lancashire Combined County Authority's (LCCA) draft Bus Service Improvement Plan and Enhanced Partnership documents, and to secure delegated authority to publish the documents following a period of stakeholder consultation.
This area of work is part of wider activity to establish the LCCA as the sole Local Transport Authority (LTA) for the Blackburn with Darwen Borough Council, Blackpool Council and Lancashire County Council area from 1st April 2026 as covered under previous reports to the LCCA.
Recommendation
The Lancashire Combined County Authority is asked to:
(i) Approve the draft Bus Service Improvement Plan at Appendix 'A'. (ii) Approve the draft Enhanced Partnership Plan and Scheme at Appendix 'B'.
(iii) Delegate authority to the Head of Paid Service in consultation with the Director of Highways and Transport (Lancashire County Council); Deputy Chief Executive (Blackburn with Darwen Borough Council); and Director of Communications and Regeneration (Blackpool Council) for final approval and publication of the Bus Service Improvement Plan and Enhanced Partnership and Scheme following stakeholder consultation.
Section 2 - Background
1. As the sole Local Transport Authority (LTA) from 1st April 2026, Lancashire Combined County Authority (LCCA) is required to have a single Bus Service Improvement Plan (BSIP) and Enhanced Partnership (EP) in order to receive the Bus Services Fund as part of a Local Transport Consolidated Funding Settlement. The BSIP is a strategy document developed in partnership with bus operators and other stakeholders which sits under the Local Transport Plan. It sets out:
i. The aims and vision of the LTA in relation to bus services ii. The current state of the bus market in the LTA area iii. Investment plans using Bus Services Fund and other funding iv. Future targets for bus services including patronage growth, passenger satisfaction and performance v. The LTA's long-term ambitions for the bus network
2. The Enhanced Partnership is a legal agreement between LCCA, local bus operators and other third parties such as the Highways Authorities (with highways functions remaining the responsibility of the Constituent Councils of the LCCA). Arrangements are set out in an EP Plan and Scheme; the Plan provides a summary of the BSIP, whilst the Scheme sets out the obligations on each party alongside the governance process for the Enhanced Partnership.
BSIP and Enhanced Partnership Timeline
3. The timeline for the LCCA’s BSIP is as follows: i. Request for stakeholder input – issued 26 November 2025 ii. Request for bus operator data – issued 10 December 2025 iii. Formal stakeholder consultation – w/c 23rd February 2026 for 28 days iv. Publish final BSIP – w/c 6th April subject to stakeholder feedback and approval by the LCCA as set out in the recommendations in section 1
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Lancashire Combined County Authority at Lancashire & Rossendale and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.