CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Lancashire County Council / Rossendale Borough Council
Lancashire Combined County Authority, Tuesday 14 April 2026 at 4.00pm

UK Shared Prosperity Fund - Programme Update

Noted Committee 2 papers

AI summaryLancashire Combined County Authority notes UK Shared Prosperity Fund progress, with £11.8m of £22.4m spent by December 2025. The programme now ends 30 September 2026 with no direct replacement, and council leaders plan to raise the gap with Government.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedThree items noted on progress, impact, and lobbying
Money£11.8m spent of £22.4m54% of 2025/26 allocation used by end December 2025
What happens nextProgramme ends 30 September 2026Six month extension, no extra funding
Who it affectsLancashire local authorities and partners188 projects, business, skills, VCFSE groups affected

What was decided

The LCCA noted programme progress to 31 December 2025 and the extension of the UKSPF end date from 31 March 2026 to 30 September 2026. Report P3, P10

The LCCA noted ongoing activity, with reporting to the Economy and Skills Advisory Boards, to assess and mitigate the impact of UKSPF ending in Lancashire, including dialogue with all Lancashire local authorities. Report P4, P21, P22

The LCCA noted that Constituent Council Leaders intend to raise the absence of a UKSPF successor with Government as part of upcoming devolution discussions. Report P4, P11

Why

UKSPF is the Government's domestic replacement for the European Structural and Investment Programme, with three priority areas: Communities and Place, Support for Local Business, and People and Skills. Report P6

The LCCA, as a Foundation Strategic Authority with no Mayor, will not get a direct replacement programme for UKSPF, which puts local growth investment at risk after September 2026. Report P11, P17, P18

Programme spend to 31 December 2025 was £11.8m (Capital £2.2m, Revenue £9.6m), equal to 54% of the total £22.4m 2025/26 allocation, with 53 of 188 projects expected to use the extension. Report P12

What happens next

Officers will continue dialogue with all Lancashire local authorities to map what provision will end, which groups will be affected, and how gaps can be offset. Report P19, P20, P22

A People and Skills paper will go to the LCCA Skills Advisory Board on 26 March, and a business support focus to the Economy Advisory Board on 27 March. Report P21

Constituent Council Leaders will raise the absence of a UKSPF successor with Government in upcoming devolution discussions for Lancashire. Report P4, P11

The money

  • c£55m Core UKSPF funding for Lancashire over 2022 to 2025 Report P7
  • £22.4m UKSPF allocation awarded to the LCCA for 2025/26 Report P9, P12
  • £0.65m Ringfenced REPF capital for rural projects in 2025/26 Report P9
  • £11.8m Total UKSPF spend to end of December 2025 (Capital £2.2m; Revenue £9.6m), 54% of allocation Report P12
  • £3.5m Allocation across 23 separate People and Skills projects Report P21
  • £5.3m Allocation across 33 projects supporting local business Report P21
  • c£370k p/a Core Growth Hub grant over a 3 year settlement Report P30

Options considered

  • Chosen: Note programme progress, extension to 30 September 2026, mitigation activity, and lobbying intention. Recommended to enable awareness and continued officer work on impact and successor discussions Report P2, P3, P4

Implications

  • Financial: No direct continuation funding from Government to replace UKSPF for the LCCA after September 2026, with ongoing discussion about future devolution arrangements. Report P11, P35
  • Risk: Loss of UKSPF creates unprecedented risk and uncertainty for local authorities, business organisations, skills providers and VCFSE organisations, and may disadvantage Lancashire's residents and businesses. Report P18, P38
  • Equalities: Specific projects and programmes are responsible for ensuring appropriate Equality and Diversity requirements are met. Report P37
  • Legal: Blackpool Council provides administrative and assurance oversight for UKSPF under a Joint Support Services Agreement, with Blackpool's legal team preparing funding agreements and LCC legal sealing grant agreements for the LCCA. Report P33

Who and where

  • Lancashire's 2 Unitary and 12 District Councils delivering 188 UKSPF projects Report P9, P12
  • Local businesses and business support providers, including Growth Lancashire Report P29, P30
  • VCFSE organisations commissioned using UKSPF, whose long-term sustainability may be at risk Report P27
  • Young people aged 16 to 18, particularly NEETs, where local support may reduce Report P28
  • Residents needing additional support to stay in or gain employment, especially older residents with musculoskeletal and mental health needs Report P28

Timeline

  • 2022 to 2025: Initial UKSPF period; core Lancashire funding totalled c£55m paid to Unitary and District Councils Report P6, P7
  • 21 January 2025: Shadow LCCA agreed apportionment of 2025/26 UKSPF allocation and appointed Blackpool as monitoring lead Report P9
  • February 2025: LCCA created and awarded £22.4m for 2025/26 as lead authority Report P9
  • December 2025: MHCLG announced six month extension of UKSPF/REPF delivery and expenditure deadline, with no extra funding Report P10
  • 31st December 2025: Latest monitoring period: £11.8m spent, 54% of allocation Report P3, P12
  • 26 March 2026: People and Skills report to LCCA Skills Advisory Board Report P21
  • 27 March 2026: Business support focus to LCCA Economy Advisory Board Report P21
  • 30th September 2026: New end date for UKSPF delivery and expenditure, with no direct replacement for the LCCA Report P3, P10, P11

Plain English for the jargon

  • UKSPF: UK Shared Prosperity Fund, the Government's domestic replacement for the European Structural and Investment Programme, with three priority areas: Communities and Place; Support for Local Business; and People and Skills.
  • REPF: Rural England Prosperity Fund, ringfenced capital for rural projects within UKSPF.
  • LCCA: Lancashire Combined County Authority, a Foundation Strategic Authority (non-Mayoral).
  • PMO: Programme Monitoring Office, provided by Blackpool Council to monitor and report on UKSPF on behalf of the LCCA.
  • Multiply: Adult numeracy programme funded through the County Council's UKSPF allocation.
  • VCFSE: Voluntary, Community, Faith and Social Enterprise organisations.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

That, the following be noted: The programme progress to the 31st December 2025 (the latest monitoring period) as set out in tables 1 and 2 of the report, along with the extension to the end date of the programme to 30th September 2026; The ongoing activity, with reporting to the LCCA Economy and Skills Advisory Boards, to assess and mitigate against the impact of the end of UKSPF in Lancashire, including dialogue with all Lancashire Local Authorities; and The intention of Constituent Council Leaders to raise the issue of no successor programme to UKSPF for the LCCA as a Foundation Strategic Authority, as part of upcoming dialogue with Government regarding future devolution in Lancashire.
Word for word from the decision Lancashire & Rossendale published for this meeting. Source: council.lancashire.gov.uk

Follow this further

Built from Lancashire & Rossendale's papers

What the report saysPro

Report to Lancashire Combined County Authority

Purpose of the report

The purpose of the report is to provide the Lancashire Combined County Authority (LCCA) with an update on the UK Shared Prosperity Fund (UKSPF) in Lancashire. This includes a programme update covering the period to 31st December 2025 and an overview of the ongoing activity to assess and mitigate against the implications arising from the end of UKSPF in September 2026.

Recommendation

The LCCA is asked to:

(i) Note programme progress to the 31st December 2025 (the latest monitoring period) as set out in tables 1 and 2, along with the extension to the end date of the programme to 30th September 2026.

(ii) Note the ongoing activity, with reporting to the LCCA Economy and Skills Advisory Boards, to assess and mitigate against the impact of the end of UKSPF in Lancashire, including dialogue with all Lancashire Local Authorities. (iii) Note the intention of Constituent Council Leaders to raise the issue of no successor programme to UKSPF for the LCCA as a Foundation Strategic Authority, as part of upcoming dialogue with Government regarding future devolution in Lancashire.

Section 2 - Background

1. First launched in 2022, the UK Shared Prosperity Fund (UKSPF) is the Government’s domestic replacement for the European Structural and Investment Programme. UKSPF has three priority areas: Communities and Place; Support for Local Business; and People and Skills.

2. Initially covering the period 2022 to 2025, funding for Lancashire was paid directly to Unitary and District Councils in advance of the creation of the LCCA. The County Council received an allocation specifically for the adult numeracy programme, Multiply. Core UKSPF funding for Lancashire over the period 2022 to 2025 totalled c£55m, with individual Local Authorities able to use this as a flexible resource to drive local growth priorities with greater emphasis on revenue rather than capital funding.

3. Following the initial 2022 to 2025 period, Government has continued UKSPF as a one-year extension covering 2025/26. This was framed as a transitional arrangement allowing local authorities to invest in local growth, in advance of wider funding reforms.

4. Further to the creation of the LCCA in February 2025, Government awarded the LCCA (as lead authority) £22.4m for 2025/26, including £0.65m ringfenced for capital rural projects under the Rural England Prosperity Fund (REPF). The apportionment of the 25/26 allocation amongst Lancashire’s 2 Unitary and 12 District Councils was agreed at the meeting of the Shadow LCCA on the 21st January 2025, whilst also appointing Blackpool, through its established Programme Monitoring Office, to undertake the monitoring and reporting role for the UKSPF funds on behalf of the LCCA.

5. After the launch of the 2025/26 programme, MHCLG announced in December 2025 that the delivery and expenditure deadline for UKSPF/REPF would be extended for a further six months from 31st March 2026 to 30th September 2026, although no additional funding would be made available.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
UK Shared Prosperity Fund: Programme UpdateReport 166 KB DownloadRead as text
PDF
View item 8. as DOCX 119 KBReport 6 pages Download

At this meeting

Whole meeting

Who was there

8 of 8 attended
CC
County Councillor Stephen Atkinson Leader, Lancashire County CouncilChair, present
PR
Councillor Phil Riley Leader, Blackburn with Darwen Borough CouncilDeputy Chair, present
CC
County Councillor Simon Evans Deputy Leader, Lancashire County CouncilCommittee Member, present
NB
Councillor Neal BrookesCommittee Member, present
AB
Councillor Alistair BradleyCo-optee Non-voting, present
SH
Councillor Simon HoreCo-optee Non-voting, present
MI
Mo Isap Lancashire Business BoardCo-optee Non-voting, present
CG
Clive Grunshaw Police and Crime CommissionerObserver, present

On this subject at Lancashire & Rossendale

Search all
  1. UK Shared Prosperity Fund - Programme UpdateThis decision
  2. UK Rural Prosperity Funding 2025/26 and UK Shared Prosperity FundingApproved

More from Lancashire & Rossendale Lancashire Combined County Authority

All decisions
MeetingDecisionOutcome
8 Sep 2026 Minutes of the meeting held on 23 June 2026That the minutes of the meeting held on 23 June 2026 be confirmed as a correct record and signed by the Chair. Decided Open
8 Sep 2026 Governance Review/Future DevolutionThat the update be noted. Noted Open
8 Sep 2026 Employment Matters - Appointment of the Chief Finance OfficerThat Gary Fielding be appointed as the Chief Finance Officer (Section 73 Officer) of the LCCA. Decided Open
8 Sep 2026 Transport Delivery Plan and Implementation UpdateThat i. The Local Transport Delivery Plan be submitted to the Department for Transport covering the period 2026/27 to... Noted Open
8 Sep 2026 Lancashire Spatial Development Strategy UpdateThat, following consideration of the Lancashire Spatial Development Strategy, the updates on preparatory and enabling... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies