Fylde Borough: LCC/2026/0005. Land to the east of Graving Dock Road, Lytham
DecidedPlanning3 papers
AI summaryLancashire County Council's Development Control Committee has granted planning permission for a wastewater facility with three above ground tanks on land east of Graving Dock Road, Lytham, subject to conditions including an amended Construction Traffic Management Plan.
Written from the decision and the officer reportPDF Pro
OutcomeDecidedSubject to conditions in Appendix A and amended condition 7
MoneyNo cost to councilReport states no financial implications for county council
What happens nextDevelopment must begin within three yearsStandard planning condition under Section 91 Town and Country Planning Act 1990
Who it affectsWastewater infrastructure in LythamAims to reduce storm overflow spills at Lytham Pumping Station
What was decided
Planning permission was granted for a change of use of land to a wastewater facility, including three above ground tanks, fencing and associated infrastructure, at land east of Graving Dock Road, Lytham. Report P2, P9
The permission is subject to the conditions set out in Appendix A of the report, with condition 7 amended to require construction in line with the Construction Traffic Management Plan rev P04 dated 8/6/26. Report P93
Why
The facility is needed to help United Utilities meet a regulatory duty under the Environment Act 2021 to reduce storm overflow spills to no more than 10 per year, and to meet Bathing Water standards allowing no more than 3 spills in the May to September period. Report P11, P39
The site is over 120 metres from the nearest houses and adjacent to existing industrial and commercial uses, so the development is not considered incongruous and harm to residential amenity is unlikely. Report P46
What happens next
Construction must begin within three years of the permission date, and a Biodiversity Gain Plan must be submitted to and approved by Lancashire County Council before development begins. Report P77, P99, P100, P102
The applicant may need to make separate temporary diversion arrangements for the affected Public Right of Way footpath outside the planning process. Report P59
Options considered
Chosen: Grant planning permission subject to conditions in Appendix A and amended condition 7. Proposal complies with relevant Development Plan policies and NPPF, and is needed to meet regulatory duties on storm overflow spills and Bathing Water standards Report P61, P62
Implications
Legal: The county council considers that any interference with Human Rights under Article 1 of Protocol 1 would be lawful, proportionate and justified in the public interest. Report P65
Equalities: The Public Sector Equality Duty has been applied and no disproportionately adverse impact on any protected characteristic is anticipated. Report P70
Financial: There are no financial implications for the county council in granting the permission. Report P67
Risk: The decision must be based on the evidence and information in the report, supplementary reports and officers' presentation; significant risks from the decision-making process are unlikely. Report P71
Other: Biodiversity net gain must be secured through a Biodiversity Gain Plan approved by Lancashire County Council before development begins, with additional units met through purchase of biodiversity credits. Report P48, P99, P100, P102
Who and where
Residents living 120 metres north-west and 130 metres south of the site, who raised concerns about odour, noise, visual impact, traffic and environmental risk Report P6, P31
Users of Public Right of Way footpath FP0502006 on Graving Dock Road Report P6, P57
United Utilities as applicant, with regulatory duties under the Environment Act 2021 Report P11, P39
Timeline
First planting season after completion (1 October to 31 March): Landscaping works to be carried out under condition 5 Report P88
Within three years of permission: Development must commence under condition 1 Report P77
18 months construction period: Construction expected to generate 35 HGV movements and 12-15 staff vehicles per day Report P53
After construction (operational phase): Maintenance vehicle movements would reduce to 1 per month Report P53
Plain English for the jargon
Bathing Water standards: Standards limiting the existing infrastructure to no more than 3 spills in the May to September bathing water period.
Construction Environmental Management Plan (CEMP): A plan setting out measures to manage environmental impacts during construction, including ecology protection.
Biodiversity Net Gain: A requirement for development to deliver a measurable improvement in biodiversity, secured through a Biodiversity Gain Plan and potentially biodiversity credits.
HGV movements: Heavy goods vehicle trips to and from the site, estimated at 35 per day during construction.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9
Resolved
That planning permission be granted subject to: (i) The conditions set out in Appendix 'A' of the Committee report. (ii) The amendment to condition 7 as detailed on the Update Sheet as follows: " Construction development shall be carried out in accordance with the details set out in the document entitled 'Construction Traffic Management Plan' rev P04, dated 8/6/26. Reason: In the interests of the safe operation of the highway during the construction phases and to comply with Policy DM2 of the Joint Lancashire Minerals and Waste Local Plan."
Word for word from the decision Lancashire & Rossendale published for this meeting.Source: council.lancashire.gov.uk
To consider and determine the following planning application:
Fylde Borough Council: LCC/2026/0005 Change of use of land to a wastewater facility to include three above ground tanks, fencing and associated infrastructure – Land to the east of Graving Dock Road, Lytham.
Recommendation
The Development Control Committee is asked that planning permission be granted subject to the conditions set out in Appendix 'A'.
Background
Description and Location of the site
1. The site is located to the east of the existing Lytham Pumping Station on Graving Dock Road in Lytham and extends approximately 0.69 hectares. It is currently cleared of all vegetation for permitted development survey requirements.
2. The site is immediately surrounded by industrial and commercial uses to the north and north east, and green space and woodland to the south. The Main Drain watercourse runs to the south and east of the site, flowing towards the River Ribble which is approximately 1.2 kilometres to the south. 3. There are residential properties located 120 metres north-west and 130 metres to the south of the site. Public Right of Way footpath FP0502006 follows Graving Dock Road and to the south of the site.
4. All construction access would utilise the existing access from the Preston Road Industrial Estate to the east of the site. The permanent access when the site is operational would be on the northwest of the site, secured by a gate.
Applicant's Proposal
5. The proposal is for a change of use of land to a wastewater facility, which includes the construction of three above ground tanks and associated infrastructure.
6. Each of the proposed tanks would measure 26 metres in diameter and 9.3 metres in height. They would be constructed of steel and coloured green. The associated above ground pipework would connect the new tanks to the existing pumping station to the east. The proposed fencing would measure 2.4 metres in height and surround the entire site. This would include a gate, also 2.4 metres in height, on the northwest boundary of the site to allow access from the existing pumping station.
7. Lytham Pumping Station currently overflows into the Main Drain at approximately 45 spills per year. This is one of a number of stations across the northwest that United Utilities has a regulatory duty under the Environmental Act 2021 to make improvements to reduce storm overflow spills so that they do not discharge above 10 spills per year. This location is also subject to a Bathing Water standards, meaning that the existing infrastructure is not allowed to spill more than three times in a bathing water period (May to September).
8. The three tanks would store stormwater until such a time as the sewers have capacity to discharge. The stormwater would then be returned to the sewer network for onward treatment at Preston Wastewater Treatment Works. The location of the proposal is largely dictated by the existing underground sewer network.
Planning policy
9. National Planning Policy Framework
10. Joint Lancashire Minerals and Waste Local Plan – Site Allocation and Development Management Policies – Part One (adopted September 2013)
Policy DM2 Development Management
11. Fylde Borough Council Local Plan: Policy GD7 – Achieving Good Design in Development Policy GD9 – Contaminated Land Policy INF1 – Service Accessibility and Infrastructure Policy CL1 – Flood Alleviation, Water Quality and Water Efficiency Policy ENV1 – Landscape Policy ENV2 – Biodiversity Relevant planning history:
12. None relevant to this proposal.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Development Control Committee at Lancashire & Rossendale and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.