Quarter 4 2025/26 Corporate Performance Report including 2026/27 Key Performance Indicators and Targets
NotedExecutive10 papers
AI summaryLancashire County Council Cabinet noted strong year-end performance for 2025/26 and approved a new suite of key performance indicators and targets for 2026/27, with 55% of indicators rated green.
Written from the decision and the officer reportPDF Pro
OutcomeNoted55% of 46 indicators rated green, 29% red
MoneyNo direct financial implicationsSome KPIs link to overall financial position
What happens nextNew KPIs in use from April 2026Highways KPIs to be reported from Q1 2026/27
Who it affectsLancashire residents and servicesAdult social care, children's services, highways
What was decided
Cabinet noted the council's performance in Quarter 4 of 2025/26 against the ambitions of the Council Plan 2025-2030, and approved proposals to improve performance where stated.
Cabinet noted progress achieved against milestones in the Council Improvement Plan 2025-2027, as set out in Appendix 'B'.
Cabinet approved the new suite of key performance indicators and targets for 2026/27, as detailed in Appendix 'C'.
Why
The report is the final corporate performance report for 2025/26, providing an overview against the Council Plan 2025-2030 priorities and proposing new KPIs and targets for 2026/27. Report P1, P2
A more robust approach to performance management, KPI and target setting was applied this year to ensure alignment with the Council Plan, using a consistent RAG rating system. Report P9, P10
For 2026/27, a reinforced Corporate Performance Framework was approved by Cabinet in May 2026 to support the Moving the Dial 2026/27 Delivery Plan, with all KPIs reviewed and re-set. Report P41, P42, P43, P44
What happens next
Senior leadership teams will address areas for improvement through deep-dive activity, scrutiny, partner discussions and redirection of capacity or resources where needed. Report P30
Highways KPIs will be reported from Quarter 1 2026/27 following completion of data migration into CONFIRM, the council's Highways Asset Management System. Report P36, P37, P38
A full list of Q4 performance for all KPIs under each council ambition is included at Appendix 'A', with 2026/27 indicators and targets at Appendix 'C'. Report P26, P44
The money
63.15% Delivery as a proportion of the annual capital plan, reflecting slippage Report P19
Chosen: Approve Q4 2025/26 performance and improvement proposals. Standard year-end performance oversight under Council Plan 2025-2030 Report P4, P5
Chosen: Approve new 2026/27 KPI suite and targets. Reinforced Corporate Performance Framework approved by Cabinet in May 2026 Report P7, P42
Chosen: Note Improvement Plan 2025-2027 milestone progress. Quarter 4 update provided in Appendix 'B' Report P6, P40
Implications
Legal: Section 3 of the Local Government Act 1999 places a best value duty on the council to secure continuous improvement in its functions, supported by this report. Report P51
Legal: The Local Government Finance Act 1992 requires a balanced budget; the report supports this by aligning performance, resource use and financial planning. Report P53
Financial: There are no direct financial implications, though several KPIs link to the council's overall financial position, including capital programme slippage. Report P19, P55
Equalities: Where relevant, actions taken to improve performance consider the impact on equality and diversity. Report P58
Risk: Each KPI includes commentary proportionate to current performance, identifying risks to achieving targets where appropriate. Report P60
Other: Local Government Reorganisation proposals across Lancashire are under development and will require a future review of priorities, KPIs and reporting mechanisms. Report P57
Adults receiving social care and safeguarding services Report P15, P28, P29
Children and young people, including those with Education, Health and Care Plans Report P15, P28, P29
Highways service users Report P36, P37, P38
Local businesses and the Lancashire economy Report P16
Library, museum and community service users Report P17
Council staff delivering digital and transformation projects Report P18, P28
Timeline
10 July 2025: KPIs were agreed by Cabinet to monitor Council Plan delivery Report P8
May 2026: Reinforced Corporate Performance Framework approved by Cabinet to support the Moving the Dial 2026/27 Delivery Plan Report P42
Quarter 4 2025/26: Year-end performance reporting period covered by this report Report P1, P8
Quarter 1 2026/27: Highways KPIs to be reported following completion of data migration into CONFIRM Report P36
Plain English for the jargon
RAG rating: Red, Amber, Green system used to rate performance against targets: green if achieved or exceeded, amber if within 5% of target, red if more than 5% away.
Council Plan 2025-2030: The council's strategic plan setting out ambitions across Better Lives, Economic Ambition, Stronger Communities and Thinking Differently.
Council Improvement Plan 2025-2027: A plan with three priorities to improve performance, strengthen finances and modernise the organisation, with tracked milestones.
CONFIRM: The council's Highways Asset Management System, into which data is being migrated to enable new reporting.
EHCP: Education, Health and Care Plan, a statutory plan for children and young people with special educational needs and disabilities.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5
Resolved
That The performance of the council in Quarter 4 of 2025/26 against the ambitions set out in the Council Plan 2025-2030 be noted; The proposals as set out in the report to improve performance where stated, be approved; The progress achieved to date against milestones within the Council Improvement Plan 2025-2030, as set out in Appendix 'B' of the report, be noted; and The new suite of key performance indicators and targets for 2026/27 which were detailed in Appendix 'C' of the report, be approved.
Word for word from the decision Lancashire & Rossendale published for this meeting.Source: council.lancashire.gov.uk
The report is the final Corporate Performance Report for 2025/26 and provides an overview of performance for the key performance indicators monitoring the delivery of the priorities of the Council Plan 2025-2030.
The report also provides the proposed key performance indicators and targets for 2026/27 to form future performance reports to Cabinet.
Recommendation
Cabinet is asked to:
(i) Review the performance of the Council in Quarter 4 of 2025/26 against the ambitions set out in the Council Plan 2025-2030 and provide any feedback.
(ii) Agree the proposals as set out in the report to improve performance where stated.
(iii) Review the progress achieved to date against milestones within the Council improvement Plan 2025-2030, as set out in Appendix 'B'.
(iv) Agree the new suite of key performance indicators and targets for 2026/27 which are detailed in Appendix 'C'. Background
1. This is the quarter 4 year-end report for 2025/26, setting out performance highlights and areas of improvement against the priorities set out in the Council Plan 2025- 2030. Key performance indicators were agreed by Cabinet on 10 July 2025 to enable the monitoring of progress and delivery. The Lancashire County Council corporate performance dashboard provides more detail for each key performance indictor including trend over time and supporting commentary.
2. A more robust approach to performance management, key performance indicators and target setting was applied this year to ensure alignment with the Council Plan. Ambitious but realistic performance targets were set based on benchmarking, trends and available resources. This included a consistent and transparent RAG rating system:
• Green – achieved or exceeded the target • Amber – within or equal to 5% (not percentage points) of the target • Red – more than 5% away from the target
Overview of Performance
3. Overall, the year-end position shows strong and improving performance across the majority of corporate priorities The Council is delivering tangible results for residents and the local economy, particularly through high participation in education, increased independence in later life, strong economic performance, and growing community engagement.
4. At the same time, performance highlights ongoing pressure points, especially in demand-led services and capital delivery, where performance is improving but not yet consistently at target.
5. Taken together, performance reflects strong progress and delivery against Council Plan ambitions while actively responding to increasing demand, complexity, and delivery challenges.
Ambition Summary Better Lives Overall performance is positive with improvement across most indicators, including 94.7% of 16–17 year olds in education, employment or training (up from 93.5%), strong adult safeguarding performance, increasing independence for adults with learning disabilities, and 58.9% of children with Education, Health and Care Plans supported in mainstream education (well above the 44% target).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.